00:02
It's often the case that an organization will
not have the required resources that a
project needs. Therefore, the project
manager here has the
responsibility to procure what they need
externally.
00:15
By this point, they should be very familiar
with the details of the contract in order to
properly assess the costs and the risks of
any transaction.
00:24
They must be aware of timelines, due dates
and quality levels of all resources they are
procuring. There are three main types of
contract that we will run through
now. It is up to the project manager to find
the best contract because it's
their main tool for keeping track of vendor
work and behavior.
00:44
So the first one is called fixed price, and
it's the simplest type of contract
the vendor commits to doing the work for a
set amount within a certain time frame.
00:55
The pros of this is that any additional
spending will be taken on by the vendor.
00:59
No risk for you.
01:01
Perfect. Or is it?
You see that they are aware that with this
kind of contract, if the costs are higher
than expected, then they will incur losses.
01:12
Therefore, there is a chance they will put a
big buffer on the initial price.
01:18
Or if they find that costs are getting too
high, they may try to decrease the scope or
the quality in order to compensate.
01:25
So know that this is beneficial to use when
the scope is clear to all parties.
01:30
But a good analysis is important prior to
making agreements.
01:35
The second type is called cost plus.
01:38
This is where the buyer agrees to pay any
cost incurred by the vendor performing the
work. This can be a fixed additional fee, a
variable fee, or a
mix of the two. Either way, it gives the
buyer the flexibility to adapt
the spending in accordance with the work
being done.
01:56
But with that comes the risk of covering all
extra costs, along with the chance that
the vendor may keep the work going longer
than needed or adding extra
items to the to do list.
02:09
This contract makes more sense if the scope
is not easy to define, but
proper controls need to be put in place to
ensure money is only spent on things
essential for the project.
02:21
A fancy new haircut for the vendor doesn't
fall into this category.
02:26
The third type of contract is called Time
and Materials, and it's a
mixture of fixed price and cost plus.
02:34
It's where the vendor charges the buyer an
hourly or daily rate.
02:38
For example, when consultants or technicians
charge per day for their
services, it's another good contract to jump
into when the scope is not clear
and the work is more labor based than
material based.
02:52
It runs a similar risk to the cost plus
contract, but that just means the same
countermeasures can be taken.
02:59
Well, there we have three types of contract,
but there can be many
variations and of course they can all be
tailor made.
03:07
The project manager could add incentives for
the vendor to complete work faster or
to a better quality.
03:13
The contract can even include inflation if
the project spans a long time.
03:19
The project manager must have a good
understanding of all risks and benefits that
each agreement can have.
03:25
Then define the most convenient approach for
the project, the stakeholders, and of
course, for the vendor themselves to agree.
03:33
Awesome. So that's how the project manager
can deal with the financial side of
things. But what about the non financial
resources?
Well, join us next lesson where we'll talk
about human resources.
03:46
See you there.