00:00
Now is the time to prepare for action.
00:04
You can do two things when faced with a
risk.
00:07
Change something in advance to eliminate or
lessen the risk, say doing construction in
the summer months rather than the winter
months, for example.
00:15
Or create a plan B in case the risk becomes
reality.
00:19
The former is called mitigation and the
latter contingency.
00:25
The options you have when it comes to
mitigation are firstly to eliminate the
risk. For example, you have planned to have
big modern letters which light
up all spectacular to be put on the top of
your showroom.
00:38
The risk is that this area is prone to
strong winds during some seasons, and
there is a risk of letters falling.
00:45
To eliminate this risk completely.
00:47
You can plan to have them attached to the
facade or have printed letters instead.
00:52
And of course, insurance will cover the
financial risks of any damage if you choose
to keep the original lettering.
00:59
If eliminating the risk is not possible or
not worth the extra costs, then you can
aim to reduce the severity.
01:06
For example, if it's not feasible to delay
construction during the autumn and winter
months, then you can prepare for damage
control by training your team to work in bad
conditions and store equipment that could be
damaged during periods of bad weather.
01:21
If you are diligent, you can prevent major
costs and delays without having to stop
construction completely.
01:28
On top of that, you can reduce the
probability of occurrence if you have
noticed low motivation from a member of your
team and their low productivity risks
causing delays.
01:39
Then you can be proactive in motivating them
by identifying any problems they may
have or by incentivizing the work.
01:47
And if during the project you find these
methods have not worked, you can let the team
member go or employ an extra pair of hands.
01:56
Now, as you can probably guess, these
methods can be combined and
personalized as required by the project.
02:04
Great. So now let's talk about contingency
planning.
02:09
Unless you have eliminated a risk
completely, then a plan B is always a good
idea. Document what you and the team need to
do to limit the damage
from an event and record it in the risk log.
02:21
For example, take the 3D visualization
effects example from our
log. The technology is designed to project
what the cars will look like in
different colors and variations.
02:33
If it's not ready when the showroom opens,
we can still show them the old fashioned way
with booklets and displays.
02:40
It's not ideal, but it is a better outcome
than having no backup plan whatsoever.
02:45
So view your risk log as a living document
that must be constantly updated.
02:51
Risks can rear their head at any point and
previously identified risks can
evolve. A good project manager will keep
updating their risk log.
03:01
As we mentioned, risks, as well as many
other areas of the project planning are
often identified through communication with
stakeholders.
03:09
So how about we take some time to discuss
how our project manager communicates with
everyone involved in the project?