00:04
Everything you've done to this point the work
breakdown structure, the
activity list, estimating durations,
applying buffers, sequencing
activities, the critical path analysis, the
Gantt-Chart all have been leading
to this point.
00:21
A nice cup of tea.
00:23
Just kidding. Project managers don't have
time to drink tea.
00:27
It's time to build the project.
00:28
Schedule the almighty project plan for all
your information.
00:33
Now we'll give you a tutorial on how to use
MS Project, a super tool that
lets you input dates, link activities to one
another, and all the extra information
you could need. Hi, welcome to our MS
Project
tutorial. This is a super useful tool for
scheduling big
projects with many activities.
00:55
The tool offers many functionalities to help
you create change and
control your project schedule most
efficiently.
01:04
And it's very simple to use.
01:06
It works similarly to excel, just that it is
customized for scheduling
work. Let's see what we have on the main
screen.
01:17
To the left, we have the main table where
the tasks need to be listed
and scheduled.
01:24
To the right, we have the Gantt-Chart field,
which is automatically populated
as you type in your tasks.
01:32
Above. We also have a timeline indicator to
which you can add manually
selected tasks.
01:39
Let's hide this now and focus on the main
part.
01:44
I will expand the main part, swiping the
Gantt-Chart part to the
right. Okay.
01:51
Let's start with the task name.
01:55
You need to type the name in the field.
01:58
Then we have duration where you can select
the duration in
days, weeks or months.
02:06
After you have start and finish, this is
where you need to
select the calendar day on which the tasks
will start and finish
moving further to the right.
02:18
You have predecessors.
02:19
This is the field where you indicate
dependencies between the tasks.
02:24
Then resource names.
02:27
Here you type the name or role of the person
responsible for the task at
hand. The last one is add new column and
from
the dropdown you can see many other options
you can add.
02:41
We won't view them.
02:42
But to give you an example, percentage
complete
by clicking on it, it creates a new column.
02:52
Here you can type how much of the total work
on a certain task is completed
up until now?
Let's see an example.
03:03
Say You need to refurbish your room.
03:06
You would have the following tasks.
03:10
Remove old furniture.
03:13
Before starting anything you need to empty
the room you deem two
days are an appropriate duration and fill it
in.
03:22
Then you need to say which date it should
start.
03:26
Spring sounds good.
03:28
Let's say April 8th.
03:31
By typing it, the tool automatically
calculates the end date.
03:36
It knows it will take two days.
03:40
Resources. Let's say your brother is the
person to do the heavy
lifting. Next.
03:48
Cover the floor so nothing gets dirty during
painting, let's say
one day. Now, this one should start
after we have removed the furniture.
04:00
Right. So we have a dependency.
04:05
We need to use the predecessor's field, and
we have two ways to do
this. Select the two tasks and click on
link tasks.
04:16
There you go. It automatically populates the
start date on the day
after the first task is finished.
04:25
Resource. Let's say your father will be doing
the covering and
painting. Next.
04:33
Paint the room.
04:34
Let's say five days.
04:37
Again, this is dependent on the floor
covering.
04:41
We will do the same.
04:43
But this time we will show you the other
way.
04:47
You can directly type into the predecessor
field the number of the task on
which this one is dependent.
04:54
So to.
04:57
After painting, we will position the new
furniture.
05:00
Let's say two days.
05:03
We will again use the dependency typing
three.
05:08
Finally some decoration using the same logic
and assigning your
sister.
05:20
There you go. You have a plan.
05:23
Now let's see another important
functionality, the
summary task.
05:32
We want to see the painting activities in
more detail.
05:36
We want to add some additional tasks
underneath it.
05:40
Similarly to Excel, we select, let's say,
five rows
below right click and insert task.
05:49
There you go, five new rows.
05:52
Here. We want to plan when to paint the
walls and the ceiling.
05:57
We type them in the same way.
05:59
However, they are now displayed as new
independent tasks.
06:04
We need to indicate they are part of the
paint room parent activity, so we
select them and use the indent task button.
06:13
Now they are all subtasks to the main one.
06:16
Paint the room.
06:19
In the same way we populate their durations
and dates.
06:30
Final point, you can also double click on
each task to open up a
window. Here you can see many details,
including all of the
functionalities we saw.
06:42
For example, predecessor tab gives you
information on all
dependencies, also notes where you can type
additional information on
a task. After completing the plan to the
right,
you can see the Gantt-Chart the MS project
has automatically created for you.
07:05
Okay you now know how to use the tool for
scheduling.
07:10
Do you want to see what our laboratory
project plan looks like?
Let's take a look.
07:16
You see to the right the activity list with
durations, start and end dates
and dependency indicator in the predecessor
column.
07:26
Note, this is the high level summarized
version.
07:30
However, we have 144 lines.
07:34
This means we have the full list, including
many subtasks.
07:40
All activities with a plus sign to their
right and in bold are summary
tasks. Just click on the plus to expand.
07:49
Let's see a few of them.
07:52
Expand prepare land for construction.
07:55
It has three subtasks.
07:57
Assemble band position, safety barriers,
clear site, etc..
08:03
Car manufacturing schedules for six cars.
08:07
By expanding them, you can see all the
production steps identified
recruit personnel.
08:15
Same thing. As explained at the beginning,
MS
project is easy to use and quite useful when
planning projects.
08:25
It is also similar to Excel, so in case you
do not have MS project, you can
also try there.
08:32
Thanks for watching.
08:33
Wow. The project manager needs to go into
loads of detail.
08:36
Right. But how can stakeholders hope to keep
track of how a project is going?
Well, a project manager creates a milestone
table for them in this next
lesson to see how and why we do that.
08:50
Thanks for listening.