00:02
Even with planning, the project will change
and grow.
00:07
This needs to be recorded formally and we're
going to use our laboratory project to
show you how. All right.
00:15
So you're holding your kickoff meeting.
00:18
And Lamborarri's HR manager, has asked if we
need to hire anyone who speaks a
language other than English.
00:26
This is a good point that you hadn't thought
of.
00:30
The marketing manager is also there and they
confirm that with the expected
clients it would be a good idea to have at
least one Spanish speaking member of staff
and one Russian speaking employee.
00:43
The HR manager says that it is doable, but
the time needed for the hiring process would
be around 11 weeks rather than the eight
initially planned.
00:52
This means that your action is to update the
activity, recruit personnel
in your project plan.
00:59
You are the person who needs to complete it.
01:01
And as you know, this is a task which you
can complete in a day.
01:05
You mark this down to.
01:08
Something to point out.
01:09
Even if there is a relatively simple task
and you are the one responsible for it, don't
assume that you will remember because
firstly this can lead to
mistakes. Secondly, other people on the
project need to know what is happening
and to trust that you are being thorough in
your execution.
01:28
And thirdly, this can be a record for future
projects where similar
actions may help you with planning.
01:36
Now imagine you're a month into your project
and you hold a project update
meeting. The marketing manager shares a
problem regarding the activity
order furniture and tech with the sub task
select vendors,
which by the way is line 45 of your project
plan.
01:54
They tell you that the design agency will not
be able to prepare the work in the next two
months as they are over-encumbered with
other clients?
But you have estimated five weeks for
creating the furniture.
02:08
Two months are not okay.
02:10
Your project is now in week 22 and the
construction company is
already working on the final stages of
construction.
02:17
The roof works.
02:20
So you ask the marketing director to search
for another design
agency. However, they explain that they
cannot help, and it's the
finance manager assistant who deals with the
vendors.
02:32
After speaking with them, you set a deadline
of two weeks and fill it into your project
diary. Nice job, project manager.
02:41
As you can see, projects change and evolve,
but with a clear and concise project diary,
everyone can see their commitments and when
the project manager is on top of it, there is
a lot less room for delays and mistakes.
02:54
The Project Diary is a great tool during the
execution phase, but since the tool is only
good as its user, a project manager needs to
be able to manage all the work and people
involved. In the next few lessons, we will
discuss just how the project
manager can do this.
03:10
Keep in mind, the popular name for this tool
is a project action log.
03:15
So in your next project, use this as the
fancy cover for your diary.
03:19
See you in the next lesson.