00:01
Hello. This module introduces you to the
sequence activities process in the
PMBOK guide. It's very important that you
pay
particular attention to this module.
00:15
It's one of the more important ones in terms
of the development of our project schedule.
00:21
We're giving it a high difficulty rating
because there may be a lot of concepts here
you haven't seen before, nor applied in your
day to day job, and as such, you're going to
have to remember quite a bit about it as
well.
00:32
So do pay particular attention to this
module and all the other time management
modules that lead up to the preparation and
development of the project schedule.
00:44
The sequence activities process itself is
part of the Project Time Management
Knowledge Area. There are six planning
processes
in project time management and one
monitoring and controlling process.
00:58
The sequence activities process is the third
of the planning processes, which
begin with the plan schedule management
process, which produces our schedule
management plan. Now, our schedule
management plan provides guidance on
how we do the other planning activities and
also our single monitoring and control
activity. So before doing sequence
activities, we've
defined our activities, and what we did when
we defined our activities was to generate
an activities list and some activities
attributes.
01:30
Now in this step, we're going to put all
those activities in order.
01:34
We're going to define the relationships
between them to find what's a predecessor,
what is a successor.
01:39
And we're going to define the dependencies
between them and produce a network diagram.
01:44
But we still don't have our project
schedule.
01:47
We won't have that until we complete the
work and the other three remaining planning
processes. That's estimate activity,
resources, estimate activity
durations and finally, the process that puts
them all together develop
schedule. The particular domain
task that this process helps us understand
better is
planning task, for which is develop the
project schedule
based on the approved project deliverables
and milestones, scope
and resource management plans in order to
manage timely completion of the
project. And in fact, that one domain task
covers
all of the time management planning
processes.
02:35
The key themes of the sequence activities
process are we're going to
take our activities and we're going to put
them in the order in which they will
occur or sequence them.
02:47
Once we've done that, we're also going to
define the types of relationships and
dependencies that exist between our
activities.
02:55
And with all of this information, we're
going to produce a network diagram using the
precedence diagramming method, particularly
the activity on node
diagram. With this, we can then calculate
different
paths through our project, and of course,
once we get to the development of the full
project schedule, the path that we're most
interested in is, of course, the critical
path. The inputs that we will go
looking for. To help us sequence our
activities include, first
up, the schedule management plan.
03:31
Now, of course, this is an output from plan
schedule management process, and the Schedule
Management Plan provides all the guidance we
need to complete all of the other planning
activities and the monitoring and
controlling activities.
03:43
So we'll look to this to give us that
guidance we need on how we're going to do
our sequencing activities work.
03:52
Another input will go looking for is, of
course, our activity list.
03:57
Now, this is an output from the defined
activities process, and it's a list of
all our activities.
04:04
But there's no indication in that list of
which activities are predecessor and which
one is a successor.
04:10
And that's what we're about to do here.
04:13
We'll also go looking for activity
attributes, this is further information about
each of our activities.
04:20
Remember, the activity list will only
contain summary information about
each of our activities.
04:26
So if we want to find out more about the
activities we go looking at the activities
attributes document.
04:33
We may also want a milestone list.
04:36
This will give us the know and milestones at
this first point in their first
iteration of our project schedule.
04:44
We may need to put these milestones in place
so that we know which activities have to be
done before that milestone and which can be
done after.
04:53
We may find useful to have the project scope
statement just to double check that
we've got all of the activities correct and
that we've included the entire scope
in our sequencing of activities.
05:06
We may also find useful particular enterprise
environmental factors, industry regulation,
government standards, things like that that
may provide some input
into how we sequence our activities.
05:19
And of course, the usual suspect of the
organizational process assets,
things like our project management
methodology, tools and templates that we can
use to help sequence the activities.
05:33
Once we have these inputs, we can then go
ahead and choose from one of the three
following tools and techniques as
appropriate that which best suits the
development of our network diagrams.
05:44
The first one is the Precedents Diagramming
Method, or PDM.
05:49
This is the one that produces the activity
on node diagram, and we're going to look at
some of those shortly.
05:56
We're also going to take a look at the
dependency determination, what we're going to
look at here is the dependencies that exist
between our activities
because of course, the dependencies that
exist with the mandatory discretionary,
external or internal will affect and which
order they go in and which
ones have to wait for which are the ones the
final tool and technique we may use
to use a leads and lags.
06:22
Now here we're going to be applying leads
and lags as appropriate.
06:27
So let's take a closer look at some of these
tools and techniques.
06:32
First up, the types of dependencies that can
exist between activities
include a mandatory dependency.
06:40
This means that the successor activity cannot
occur
until the predecessor activity has occurred.
06:48
Remember, that predecessor means comes
first.
06:51
Successor means comes second.
06:55
So a mandatory dependency means that the
successor activity can't occur
until the predecessor activity has occurred.
07:02
So, for example, you can't build the second
floor in a house until you've built the
first. Another type of dependency is the
discretionary
dependency. Now this means that the
successor activity shouldn't
really happen until the predecessor activity
has finished.
07:20
But if you need to, you've got some
discretion there.
07:25
So you really shouldn't install the carpet
in a house until you've painted the walls.
07:29
But if time is of the essence, you might be
able to start installing the
carpet or taking suitable measures to
protect it from the paint being done.
07:41
Another type of dependency is an external
dependency.
07:44
And this is where you need consent, building
consent, town planning consent, any
other consent that you can't control that
needs to come from an external organization
that's called an external dependency.
07:57
An internal dependency means waiting on
others inside your own organization to
complete work before you can continue with
your work on your activity.
08:07
So those are the four types of dependencies
you need to know each one of them for the
exam. Now leads and
lags, you need to know about these as well.
08:19
First up, a lead is the amount of time by
which the start of an
activity may precede the completion of
another activity on which it depends.
08:29
So this means instead of the successor
activity having to wait for the final
completion of the predecessor activity, it
can actually start a few days
earlier. Now, if you are using a tool such
as Microsoft Project,
you'd be able to indicate this with a minus
sign minus two minus three days,
whatever it is, that was your lead.
08:52
Opposite of a lead is a lag.
08:55
And this is the amount of time that must be
added to the completion of an activity before
a dependent success or activity can begin.
09:04
And perhaps the most used example of this is
if you pour a concrete foundation in a
house and you want to start building the
walls.
09:11
You have to include a lag between finished
pouring the concrete and starting to build
the walls to give the concrete time to cure
and become hard enough to start building the
walls. Now, the hardening of the concrete
has no resources attached to it, no
time attached to it, no cost attached to it.
09:28
So we just leave it there as a leg, or
however many days it takes for the concrete
to come up to strength.
09:36
Let's go through the types of precedence,
relationships that exist between two
activities, there are four precedence
relationships that exist now.
09:44
These are the dependencies.
09:46
Remember, those were the mandatory, the
discretionary, the external and the internal
dependencies. These are the relationships.
09:53
The first one is the most common form of
precedence relationship, and it probably
affects over 90 per cent of all activity
relationships.
10:03
Here we have a finish to start relationship.
10:07
What we can see in this instance is that
Activity A is the predecessor
activity. Activity B is the successor
activity.
10:16
Now, if you have a look at the box for
activity a, the arrow comes out of the
right hand side, which indicates that's the
finish of that activity.
10:24
The left hand side of the box is the start,
and we can see that the arrow goes into
the left hand side of the box where B is
marked.
10:33
So this is a finish to start relationship,
which means that B
cannot start until a finishes.
10:41
That's a finish to start type of
relationship.
10:44
And in the exam, most of the scenarios that
you're going to get for the network diagram
questions are going to be finished to start.
10:52
Types of relationships, but watch out.
10:55
Sometimes the question will give you another
type of relationship and
you'll need to adjust your calculations to
take that into account.
11:04
A second type of precedence relationship is
the finish to finish relationship.
11:09
And this instance, we have a as the
predecessor once again and activity
B as the successor here.
11:16
Activity B cannot finish until Activity A
finishes,
and we'll see that the arrow comes out of
the right hand side of the box.
11:25
So Activity A indicating the finish and goes
into the right hand side of
activity. B, indicating a finish to finish
type of relationship.
11:36
Another type of precedence relationship is
the start to start and
this type of relationship activity be the
successor can't start
until activity A starts.
11:49
So you'll see the diagram shows the arrow
coming out of the left hand side of the
activity, a box and going into the left hand
side of the activity
box. That's a start to start type of
relationship.
12:04
The fourth type of presence relationship,
and it's one that I can't get my head around
is the start to finish.
12:10
There's very, very little chance you'll be
asked about this in the exam.
12:14
Basically, what it says, somewhat
counterintuitively, is that activity be as
the successor can't finish until its
predecessor activity
activity a starts.
12:27
So theoretically, it exists.
12:28
But I've never seen it in real life.
12:31
Just be aware of it just in case you're
asked about it in the exam.
12:34
So that's the four types of precedence
relationship finished to start, finish
to finish, start to start and start to
finish.
12:43
You'll need to know each of them for the
exam.
12:47
Once you've done all of these things, you
will produce the following
outputs project schedule network diagrams.
12:56
We're going to have a look at some of these
in a moment.
12:59
They are just a network diagram, though they
still have no resources allocated to
them. And there are still no duration
estimates for each of the activity that we
can add up to our total project schedule.
13:10
So they are not yet a project schedule.
13:13
They are simply a representation of the
different paths of work
through our project.
13:20
We may also choose to update relevant
project documents like our schedule
management plan or parts of our project
management methodology relating specifically
to the sequencing of activities.
13:34
Let's take a closer look at a couple of
examples of a network diagram.
13:38
Remember, we're using the precedence
diagramming method, particularly the activity
on node type of diagram.
13:46
Now it's called activity on node because we
represent the activities on the
nodes. That's those little green boxes.
13:53
The arrows between the nodes indicate the
relationships between each of the
activities. So in this instance, it's a very
small example we can see we
have a milestone called begin and a
milestone called end.
14:06
And in between that we have four activities
A, B, C and D..
14:12
So one of the paths through our diagram
could be begin a end.
14:17
Another path through our diagram could be
begin b d end,
and a third path through our diagram could
be begin c
end. Remember, we still don't know which is
the critical path and to have
added durations and completed a forward path
and a backward pass
to figure out the critical path.
14:39
So here we can see that Activity D is the
successor
activity to Activity B, which is the
predecessor.
14:47
Let's take a look at a slightly more
complicated example.
14:51
It's the same thing.
14:52
There's just a lot more activities in this
one.
14:55
So, for example, take a look at activity C
. You can see that it has multiple
predecessors.
15:03
It has a as a predecessor, activity h as a
predecessor,
an activity K as a predecessor.
15:12
So it's what we call a merge activity as it
merges multiple
predecessors. And if you take a look at
Activity A, it has
multiple successes.
15:23
It has C as a successor activity, if as
a successor and activity I as a successor.
15:32
So it's what we call a burst activity.
15:36
Obviously, there's many paths through this
diagram begin
a B end is one, a longer one
is begin.
15:46
K-C-D-E end.
15:51
There are lots of paths through this diagram
and to map them all out in this instance, if
we did, it manually would take us a lot of
time.
15:59
So that's where it's better to use project
management software rather than writing these
things out manually.
16:05
Now in the exam, you'll need to be skilled
at putting together a network diagram just
like this and commenting on relationships
between different activities.
16:14
So start practicing putting together network
diagrams.
16:19
There is another way to show how work can
flow through a project and
for the exam, this is what you need to be
aware of.
16:26
It's called the graphical evaluation and
review technique, or GERT.
16:30
And it's simply a diagramming technique that
allows for loops and branches instead
of just plain sequential linear progression
through a network diagram.
16:39
So, for example, we may be putting together
material for a course
and presenting it so we would show the flow
of work as review the
material as one activity, develop the course
as a second activity as
a successor activity.
16:55
Another successful activity called present
course.
16:58
But then we show that loop that feedback
loop back to review material.
17:03
So for the purposes of the exam, just know
that GERT or the graphical
evaluation and review technique is a
diagramming technique to show the flow
of work between activities.
17:15
But it has feedback loops and branches.
17:18
The main one that you're going to use is the
precedence diagramming method, though, with
the activity on node diagram.
17:26
So in summary, the sequence activities
process takes our
activity list and arranges the activities in
the order in which they will occur
by defining predecessors and successes.
17:40
It also defines dependencies and
relationships between them, and as a
result, we can produce a network diagram,
particularly an
activity on node diagram.
17:53
This has been an introduction and overview
to the sequence activities process and the
PMBOK guide.