00:01
Hello and welcome.
00:02
This module will focus on the perform
quantitative risk analysis process
in the Bot guide.
00:10
The difficulty is rated as high.
00:13
Because many of you won't have dealt with
true quantitative risk analysis in
your projects. If you have dealt with
quantitative risk analysis,
then you can change that red down lower.
00:26
Memorization and exam importance are both
ranked as medium once again
because quantitative risk analysis is not
done by many
people in the way that the PMBOK guide
suggests.
00:41
The Perform Quantitative Risk Analysis is
one of six processes in
total in the project risk management
knowledge area.
00:51
It is one of five Planning processes.
00:55
Make sure you understand the distinction
between quantitative risk analysis
and qualitative risk analysis, qualitative
risk analysis,
which we covered in a separate module, is a
subjective analysis of
probability and impact and is done quickly
on all risks in the
project. Quantitative risk analysis takes
time and money and
computers generally.
01:21
And it uses mathematical modelling and
statistical analysis to give us a
quantitative or objective analysis of
probability and or
impact on our project.
01:34
So do make sure you understand the
difference between those two.
01:41
The particular domain task that the perform
quantitative risk analysis
process helps us to understand better is
develop the risk management
plan by identifying, analyzing and
prioritizing project risks
and defining risk response strategies in
order to manage uncertainty
and opportunity throughout the project
lifecycle.
02:03
Obviously, the key word in that sentence is
analyzing, well, performing
quantitative analysis.
02:12
The key theme of the quantitative analysis
process is that while
qualitative ranks them quantitative assigns
an actual
value to them using mathematical modelling
and statistics.
02:26
But in order to do it, we do require that
prioritized list of
risks from qualitative analysis.
02:33
So generally speaking, we do quantitative
after
qualitative. So please make sure you know
the difference and the
relationship between qualitative and
quantitative risk
analysis. Here are some of the inputs that
we may find
useful in completing quantitative analysis.
02:55
First up, obviously our risk management plan
because this is the plan that
tells us how we're going to do this, what
level and depth and content we're going
to use. It's going to reflect our risk
tolerance or risk aversion.
03:11
We'll also want our cost management plan and
our schedule management plan
because they will give us the quantities we
need.
03:20
The dollars or the time are the usual
quantities we want.
03:25
When we do quantitative analysis, we need to
express it and either dollars or
days. And that's why we need our cost
management plan and our schedule management
plan because they'll provide guidance on
which particular metrics we're using
and their particular approach to
quantitative risk management that we may
choose to use with them.
03:46
We'll also want whatever iteration of our
risk register we currently have, whether it's
the first iteration or the one hundredth
iteration will always want that
as an input to add quantitative risk
analysis to it or to
update previous quantitative risk analysis.
04:03
Because remember, these Planning processes
and risk management
aren't separate discrete processes that we
do one after the other, then stop.
04:13
These are all interrelated and happening
concurrently throughout the entire life of
the project. So here the risk register is an
input could be
any form or iteration of the risk register.
04:27
Particular enterprise environmental factors
will include industry standards for
quantitative analysis.
04:34
And they may also include particular
proprietary models owned by
others that you're using.
04:42
You may have your own organizational process
assets specifically addressing
quantitative risk analysis as well.
04:48
And if you do, they will be a very useful
input into this process.
04:56
The particular tools and techniques we may
choose to use include data
gathering and representation techniques,
quantitative risk analysis and
modelling techniques, and I'll show you some
of those in a moment.
05:08
And of course, expert judgment.
05:11
And once again, remember you're an expert.
05:14
Your project team members are experts.
05:16
In this case, though, you may want to reach
out to industry
specialists in your particular area and
their
expertise and quantitative risk analysis of
your particular risks.
05:31
So let's take a look at some data gathering
and representation techniques.
05:36
A great way to get data from people or
stakeholders is
interviewing focus groups, workshops,
surveys,
questionnaires, they're all great way to get
information
and expert judgment, as well as being a tool
or technique for deciding
on quantitative risk analysis is also a
great way of getting data
from people as well.
06:04
Here's an example of a quantitative
probability and impact assessment,
and you may want to compare this example to
the model on qualitative
probability and impact assessment to see
what the difference is between them.
06:20
In the qualitative risk assessment for the
financial one,
we gave it a probability of four out of five
and an impact of three out of
five. We multiplied those together to give a
score of 12 out of a
possible score of twenty five.
06:36
And we ranked it like that.
06:38
But that's qualitative risk analysis.
06:40
It was subjective.
06:42
It was done quickly.
06:44
Now, if we were to perform quantitative risk
analysis on the same risk
this time, instead of taking somebody's word
or opinion on what the
probability is, we would do some serious
research to give us an actual
percentage probability of that risk
manifesting.
07:02
And this research may take time, and it may
take consulting experts and paying
them for their time. We'll also want to get
an actual
value of the impact.
07:13
In this case, we're using dollars.
07:16
We could just as easily use days.
07:20
And this financial impact, we may need to
bring in quantity surveyors or other
professionals to tell us the actual
financial impact if that
manifests. So in this instance, instead of a
probability of four out of
five and an impact of three out of five,
that qualitative risk analysis gave us
for a total assessment of 12 out of 25.
07:42
Here we have a 46 per cent probability.
07:47
And a $35,000 impact, and if we multiply
those two together,
we get a quantitative risk assessment of
sixteen thousand one hundred
dollars. Now, here's a little tip, one
way to build up a transparent, defensible
contingency reserve.
08:08
Is to simply aggregate or add up all of your
quantitative probability and
impact assessments.
08:15
And this example, we've added them all up
and we've got
$50,674 as the total quantitative risk
uncertainty.
08:26
Now that could become a contingency reserve,
it's defensible.
08:30
It's transparent.
08:32
Keep in mind with your contingency reserve,
though.
08:35
If that technical risk doesn't eventuate,
then you must return the $20,489
back to the organization and not simply keep
it aside for other unidentified
risks. So that's an example of how
quantitative risk
analysis differs from qualitative risk
analysis.
08:56
And keep in mind, even though I've used
dollars here, we could have just as easily
used days and count the contingency reserve
for time on
our project. Other aspects of quantitative
risk
analysis and modelling that you need to know
about include sensitivity analysis
usually represented in a tornado diagram.
09:18
Now, sensitivity analysis takes a look at
different parts of your
project. In this instance, the diagram takes
a look at software, human
resources, hardware testing and
installation, and gives us a
range of sensitivity both negative and
positive.
09:37
So we can see that the software part of our
project is highly sensitive
to risk, and there's so much uncertainty in
there that we could have a highly positive or
a highly negative outcome, whereas the other
end of that tornado diagram is the
installation. It's not very sensitive to
risk, so
this way gives us a way to look at which
parts of our projects are most sensitive to
risk. And of course, the value in that
information is we can focus on those
areas. Now we're going to take a closer look
at a
specific type of quantitative risk analysis
and modelling.
10:14
This is called a decision tree and it shows
how to make a decision
between two or two alternative strategies or
choices.
10:24
When you have some information about
probability, you will
probably get some form of decision tree in
the exam.
10:32
So we'll go through the slowly and but you
must understand the logic behind it.
10:39
So let's take a look at this example.
10:42
Here we have the decision are we going to
build a new
plant or factory or upgrade our existing
factory?
Now, if we build our new factory, we'll see
that it costs
us one hundred and twenty million dollars.
11:00
That's that negative one hundred and twenty.
11:02
That's the cost of building our new factory.
11:06
It's big. It's exciting if we simply upgrade
our existing plant
or factory. It's not going to cost us $120
million dollars.
11:15
It's going to cost us $50 million.
11:18
The upgrade isn't as exciting and we don't
need to start from pure foundations
again. So we've got that information.
11:26
A cost of $120 million to build a new
factory and $50 million to
upgrade an existing factory.
11:33
Now, regardless of whether we choose to
build a new factory or upgrade our
existing factory, our marketing team have
told us that
there is a 65 percent chance of strong
demand for our product and 35 percent
chance of weak demand for our product.
11:50
And you'll see that represented with both
the building and the upgrading
options. 65 percent chance of strong demand
and 35 percent chance of
weak demand. So let's take a look at what
happens if we build a new factory.
12:05
Well, if strong demand eventuates in the
market and there's a 65 percent
chance of that happening, we will make $200
million.
12:14
Wow, that's fantastic.
12:16
But we would have spent $120 million on
building the factory to
make that $200 million.
12:23
So that gives us a neat path value of $80
million.
12:27
And there's a 65 percent chance of making
$80 million.
12:32
Now, if weak demand eventuates in the
market, we would have spent $
120 million to make $90 million.
12:41
So that gives us a net path value there of
negative $30 million.
12:46
And there's a 35 percent chance of losing
$30
million. So if we want to figure out the
expected monetary
value of building a new plant, we simply add
together.
13:00
65 percent of $80 million and 35 percent
of negative $30 million.
13:08
And if you calculate those and add them up,
they give us an expected monetary
value of that particular note of $41.5
million.
13:18
Okay, let's take a look now at the same
exercise, though, with
upgrading our existing plant, not building a
new one, simply upgrading our existing one.
13:27
Remember, the upgrade only costs $50
million, not $120 million.
13:33
But the demand doesn't change.
13:35
So if strong demand eventuates from our
product.
13:42
Will only make one hundred and $20 million,
not $200 million.
13:46
Remember, our big flash new factory could
make many, many more products.
13:51
Our upgraded plant can't quite make as many
products.
13:55
So if strong demand eventuates will make
$120 million,
so we would have spent $50 million to make
$120
to give us a net par value of $70 million.
14:08
And there's a sixty five percent chance of
that occurring.
14:12
If weak demand eventuate for our Produkt.
14:17
Will make $60 million.
14:19
And we would have spent $50 million
upgrading the plant to make $60 million.
14:24
Therefore, we have a net pass value of $10
million and there's a
35 percent chance of that occurring.
14:31
So we simply now add together a 65 percent
chance of making
70 million and a 35 percent chance of making
10 million.
14:41
Add those two together and we get an
expected monetary value of
$49 million for upgrading the existing plant.
14:50
So when we now compare those to expected
monetary
values. For the building, the new plant or
factory, we hadn't
expected monetary value of $41.5 Million
for
upgrading the existing plant or factory.
15:05
We have an expected monetary value of $49
million.
15:09
So therefore, based on our quantitative risk
assessment, we would choose
to upgrade the existing plant.
15:18
But can you see the information and our
decision as only as good as the
information going into it?
So if our marketing people are completely
wrong with their forecasts of strong and weak
demand? Then the model doesn't mean
anything, so it's only as good as the
information that's going on now for the
exam.
15:37
You may get a decision tree like this or you
may get a shorter one.
15:41
The key thing is to multiply the probability
and impact together over all of
the links in the chain and add them
together.
15:54
Computer modeling when it comes to doing
quantitative risk
analysis, we are generally using computers
of some sort to do mathematical modelling
or some form of statistical analysis.
16:06
So in the exam, if you see any reference to
linear regression techniques or any
form of statistical analysis, we're
generally using computers.
16:15
And it's going to be focused on quantitative
risk analysis.
16:19
And the two most popular ways of doing this
are with Monte Carlo, or it's
often called What If analysis as well.
16:26
They're very similar, and what they
basically do is take a
computer and look at all the possible
outcomes and the probability of each
and give you a range of uncertainty.
16:38
So out of all the possible outcomes, you can
see the probability of each and which ones
are the most likely and which ones are the
least likely.
16:46
You may have use something like this before.
16:50
There's many great bits of software out
there to help you do quantitative risk
analysis. We won't go into them in depth,
just know for the exam.
16:59
Quantitative risk analysis involves computer
simulations, mathematical modelling,
statistical analysis, decision trees, all
hard technical
analysis. And remember, that's how
quantitative analysis differs
from qualitative analysis, which is
subjective done by experts very
quickly. The single output from this process
is simply
project document updates, and of course, the
main project document you will
update will be the risk register.
17:31
And just to stress this, the risk register
is a very live document in your
project. It's not something you do once pet
yourself on the back and then put it away and
store it. It's not.
17:42
The risk register is a document that you
were referring to all the time you're
examining and re-examining.
17:48
Did you identify all the risks?
Are there any new risks?
Are there risks that have disappeared now?
Was your analysis correct?
Was it too optimistic?
Too pessimistic?
Well, your responses correct?
Were your proactive ones put in place?
Were your reactive ones all ready to go?
And one of the other reasons I found to keep
your risk register as a very live
document. It's not just because of the
technical information that it contains,
but it also creates buy-in and understanding
from project team
members and understanding that you take risk
management seriously on your
project. So in summary, the quantitative
risk
analysis assigns an actual time or dollar
value to risk using
mathematical or statistical methods.
18:37
It's not usually done on all risks, and it's
usually done after qualitative risk
analysis with that prioritized list of
risks.
18:48
So thank you very much.
18:49
This has been an introduction and overview
to the perform quantitative risk
analysis process and the PMBOK guide.