00:01
This module covers the developed project
management plan process from the Project
Integration Management Knowledge Area.
00:09
It's very important for the exam because it
covers the development of the project
management plan and as we know, planning is
absolutely essential for good
project management.
00:20
The difficulty is low because you've
probably done this already before, and
memorization is medium because there's some
things you may not have heard of before.
00:28
So pay particular attention to the
development of the project management plan.
00:34
This is the project integration management
knowledge area with all six of its
processes outlined there.
00:41
We can see that the developed project
management plan is the single Planning
process and this particular knowledge area.
00:51
In relation to the domain tasks that this
particular knowledge area
supports, it's Planning Task nine, which is
developed
the Change Management Plan by defining how
changes will be addressed and controlled in
order to track and manage change.
01:07
What isn't an exact domain task alignment?
Because this process covers all of the
planning processes and doesn't directly map
back to a domain task in the examination
content outline.
01:21
The key themes of the developed project
management plan process are
always and without exception.
01:28
Prepare an appropriate plan or plans to
guide the work you are going to
do. Now what is appropriate for you and your
project may be different to
somebody else's project as well.
01:40
The key to successful project management is
appropriate levels of Planning.
01:44
Not too much.
01:45
Not too little.
01:48
The other key theme is that the project
management plan and all of its subsidiary
documents and baselines, well, they are all
an essential element of project
success when done appropriately.
02:01
So let's start by looking at the inputs into
the developed project management plan
process. The first is our project charter.
02:09
Remember, the project charter is the single
output from the developed project charter
process. So we must have that first.
02:18
The other inputs are, well, all the other
outputs from all the other Planning
processes. This is all the other iterations
of all the other
plans, the baselines, the registers that we
create, they all
become inputs here.
02:32
This isn't a discrete process, it's a highly
iterative process.
02:37
We may produce a first iteration or very
draft project management plan and
then as the other Planning processes are
completed, we include that work in the
further development and further iterations
of our project management plan.
02:52
Other inputs that may be useful to us as
appropriate things like
enterprise environmental factors.
02:59
This could be such things as the
organizational culture of risk.
03:03
Do we take lots of risks and therefore do
little Planning?
Or are we very risk adverse and do lots of
Planning?
Wider enterprise environmental factors
include other industry regulations
about the amount and type of Planning that
we must do before proceeding.
03:19
Relevant organizational process assets that
we may choose to use include our
project management methodology and perhaps
we have a blank template
for a project management plan.
03:32
So we take these inputs and to these inputs,
we apply where
appropriate, the following tools and
techniques.
03:39
The first being expert judgment.
03:41
And remember that you are an expert.
03:44
Your project team members are experts.
03:46
The project sponsor and client are experts
and any other consultants that you choose to
use to help you develop your project
management plan are all experts.
03:56
And in order to get information from these
experts, you will use a
variety of facilitation techniques.
04:03
These could be meetings where you go over
all the possible things that could be in your
project management plan and decide which
will be included and which will be excluded.
04:12
They could be brainstorming techniques to
facilitate some lateral thinking and out of
the box thinking they could be formal
workshops where somebody guides the
participants through development of elements
of the project management plan.
04:27
You will be the ultimate judge, of which
tools and techniques are useful to you,
your project and the development of your
particular project management plan.
04:36
So once we've taken the possible inputs that
may be useful to us and
applied the tools and techniques
appropriately, we will then develop our
particular project management plan and that
is the sole output from the developed project
management plan process.
04:51
The project management plan itself goes on
to be an input into many, many, many
other Planning processes and also some
executing processes as well.
05:02
So the project management plan.
05:06
Is what we're going to use when we're doing
work to check the work that we're doing
against what we plan to do, so without it,
we don't know if we're on
track or not, and that's why we prepare a
project management plan.
05:19
The project management plan itself can be
summary and small, or it could be
very detailed.
05:26
It all depends on the size and complexity of
the projects that you are doing this.
05:31
The main thing is here we use our project
management plan to detect variants,
and if we detect variance between what we
plan to do and what we're actually doing,
we act.
05:43
According to our project management plan to
either change what we're planning to do or
what we're actually doing to ensure that at
all time, the project stays on track, and
that's a key part of successful project
management at all times in a project what
you plan to do, which is captured in the
project management plan and what you're
actually doing, the executing work must
match.
06:05
And once again, if you find variance between
the two, you must either
change what you plan to do or what you are
actually doing via
your approved change control process.
06:17
So your project management plan will also
spell out how changes are
assessed and how decisions are made on any
part of your project management
plan or what you're doing.
06:28
So the Change Management Plan is a very
important subsidiary plan of the
Project Management Plan.
06:36
As we've discussed, the project management
plan could be summary or detailed.
06:40
And what about the contents of the Project
Management Plan?
Well, the contents can include any or all of
the following, if appropriate.
06:48
So the Project Management Plan can include a
scope management plan, a schedule management
plan, cost management plan, quality
management plan, process improvement
plan, human resource plan, staffing
management plan Communications
Management Plan Risk Management Plan Change
Management Plan
Configuration Management Plan Requirements
Management Plan Procurement
Management Plan Contract Management Plan.
07:14
All of those are outputs from their
respective Planning processes.
07:18
The other elements of the project management
plan can include a milestone list.
07:22
These are the significant schedule
milestones that we must meet.
07:26
They can include the resource calendar, the
scope baseline, the schedule baseline, the
cost baseline, maybe even a quality baseline
may also include the stakeholder
management plan and Risk Register.
07:39
So in summary.
07:41
Always start your project management with
the appropriate level of Planning and record
this in your particular project management
plan because remember, your
project management plan should always
reflect the size and complexity of the
projects that you are doing.
07:58
And in conclusion, what we've covered is the
developed project management plan process
from the project integration knowledge area,
and this has covered the development
of the Project Management Plan, all of its
subsidiary plans and
baselines.