00:02
In this module, we're going to look at the
Perform integrated change control process
from the PMBOK guide.
00:08
It's important that you pay particular
attention to this module because it has a
high importance in the exam.
00:13
We're going to emphasize that all changes,
no matter how small or large must be
accounted for must be recorded and must go
through a change control process.
00:23
So the difficulty level of medium is
attributed to the fact that you may not
currently manage all of your changes in this
way.
00:30
The memorization, however, is low.
00:32
There's not a lot of new concepts here.
00:36
The Perform Integrated Change Control
Process is part of the Project Integration
Management Knowledge Area.
00:42
It's one of two monitoring and controlling
processes in this knowledge area, along with
monitor and control project work, but
monitor and control project work looks at all
the work that you're doing and whether what
you plan to do and what you're actually doing
are equal. The Perform Integrated Change
Control Process manages those
changes that occur when you detect variance
between what you plan to do and what
you're actually doing.
01:10
The domain task alignment for this
particular process is the monitoring and
controlling task one which says manage
changes to the project by
following the Change Management Plan in
order to ensure that project goals remain
aligned with business needs.
01:28
The key themes of this module are this is the
part where you make
changes if required, always via the approved
change control
process, whatever that may be, your
particular change control process will suit
you and your projects and the complexity of
those projects.
01:45
But you must have one and all changes must
go through it.
01:49
So you should always have a documented,
appropriate change control process
that shows how all changes will be assessed
and documented.
01:58
And a third key theme is a project manager
should always have delegated authority
to ensure the project is not held up with
small changes.
02:07
And this delegated authority should allow
them to make and approve small
changes to time and cost and resources
without having to report back to a steering
committee or change control board.
02:20
So let's take a look at the inputs into this
process.
02:23
The first one is the project management
plan.
02:26
This is because the Project Management Plan
contains as one of its subsidiary plans,
our Change Management Plan, which sets out
how we're going to manage
change in our project.
02:38
We're all also going to want to have some
work performance reports.
02:42
Now this is the raw performance data that's
been turned into work performance information
and made usable and understandable, and then
presented in a usable format in the form of
work performance reports.
02:54
Obviously, we also want the change requests
that have been raised out of all the other
monitoring and controlling processes.
03:00
This is where they come to.
03:02
This is where we consider them.
03:03
This is where we decide whether to approve
or decline them.
03:07
We may also wish to consider enterprise
environmental factors and relevant
organizational process assets, things like
our change control
templates and our project management
methodology.
03:20
The tools and techniques that we may choose
to use, if appropriate, our
expert judgment now I've mentioned several
times that this is one of the most
often used tools throughout the whole of the
Bot guide, and it recognizes that you are an
expert when it comes to change management.
03:36
Your project team members are experts when
it comes to change management.
03:40
The project sponsor, members of the Change
Control Board, the client and other external
consultants may be useful to and deciding
whether to approve a change or not.
03:50
You may also choose to use meetings,
specifically change control meetings, the
Change Control Board should meet regularly
and consider in an efficient manner the
changes presented to them.
04:02
You may also choose to use other change
control tools.
04:06
These are the information systems you use to
track and control and
monitor and let people know what's going on
with the changes in your project.
04:16
Here is an example of a sample change
control process.
04:19
It's generic, but it will give you the idea
of what your change control process could
look like. All projects should have a
process flow diagram like this,
which explains how changes are managed.
04:30
Here we can see right at the beginning that
a potential change has been identified.
04:35
First up, the project manager documents that
change request in accordance with the Change
Management Plan and the agreed change
control process.
04:43
The next box allows the project manager to
assist the level of change under their
level of delegated authority if they have
the delegated authority to
make the change. They can either approve or
decline the change and then update all the
relevant project documents.
04:59
If the change request is greater, then the
level of project managers delegated
authority. Then it has to go to the Project
Steering Committee or Change Control Board,
and they will then either approve or decline
the change request and whether it's approved
or decline. The project manager will then
once again update all
relevant project documents.
05:20
As a result of taking those relevant inputs,
applying to them, the relevant tools and
techniques, you will generate some approved
change requests.
05:29
Now the approved change requests are exactly
what they say they are.
05:32
They are change requests that have been
considered by either the project manager
under delegated authority or the Change
Control Board or Project Steering Committee,
and they have been approved.
05:44
They now represent changes to project
baselines or project scopes of
work or project budgets.
05:50
Any of these things will have to be changed
as a result of that.
05:53
Remember that the baseline is where we
started, plus all approved
changes. We may also generate a change log.
06:02
A change log is our register of all the
changes in the project, and we've got an
example coming up in a moment as a result of
approving changes.
06:11
We may also go back and change part of our
project management plan.
06:16
Its subsidiary plans, documents or baselines
and other relevant project
documents as well.
06:23
Here is an example of a change log or change
register.
06:27
You see, we've given every change its own
unique number there.
06:31
And on this example, we've got numbers
twenty three, twenty four, twenty five,
twenty six and twenty seven.
06:37
Now that numbering system is important
because in the exam, you're going to be asked
about the configuration management systems
in your project.
06:44
Now, configuration management takes many
forms.
06:47
It's any system you have in place to track
any aspect of your project.
06:51
Here we're giving each of our changes a
unique number so we can track
them. Your configuration management system
could also be your cost accounting system,
your document control system, your parts
numbering system.
07:05
So watch out for that question in the exam
about configuration management.
07:09
This change log would change.
07:11
Register then provides a very brief
description of the types of changes
requested. We've also provided an assessment
of them.
07:18
Are they high or low impact on our project
where the decision is at?
Is it approved, declined and process?
And then finally, we've also indicated
whether or not we've gone on to check was the
approved change request implemented as
approved.
07:35
So in summary, the Perform Integrated Change
Control process is the part
where you take those change requests that
have been raised by any individual in the
project, you consider them, you assess them,
you document them and you make those
decisions about them and record those
decisions in the appropriate place.
07:53
Remember, whatever else happens on your
project that all changes without
exception must go through an approved change
control process.
08:02
So if there's a question in the exam that
paints a scenario that you've got a very
small change and seems to imply that you
should proceed without considering it or
documenting it, that's not the right answer.
08:14
Regardless of the size of your change, you
should always document it and then look to
your agreed change management process as to
how your process that change.
08:24
So that wraps up our introduction to perform
integrated change control
process.