00:02
Hello. This module takes us through the
estimate activity resources process
and the PMBOK guide.
00:09
Pay particular attention to this module and
all the other time planning
modules as well.
00:16
They are very important in the exam because
each one contributes to the development of
our project schedule and there will be
questions in the exam about all
aspects of your project schedule, including
its development and understanding
it. And there will probably be at least
three or four questions requiring you to do a
network diagram.
00:37
The difficulty is rated as medium because
it's probably some things in this module that
you haven't used in your work before.
00:43
But memorization is low because none of the
concepts are that difficult.
00:50
So the estimate activity resources process
itself is one of
six planning processes in the Project Time
Management Knowledge area.
01:00
The Project Time Management Knowledge Area
has seven processes in total, with the
addition of a single monitoring and
controlling process control schedule.
01:09
The planning processes start with the Plan
Schedule Management process, which
produces our Schedule Management Plan, which
guides all of the rest of the planning
activities and the monitoring controlling
activity as well.
01:24
Estimate activity resources is the third of
the planning activities which end
up developing our project schedule, the
first being defined
activities where we produce our activities
list.
01:38
The second being sequence of activities
where we take our activities and we put them
in the order in which they occur, defining
the relationships and the dependencies
between them. The estimate activities,
resources process, which is the focus
of this module, allocates an estimated
resources to those
activities because generally speaking, we
estimate resources
first so that we can then estimate durations
because the amount of
resources that we have will affect the
duration estimate.
02:09
For example, if we have two people
completing a task or four people
completing a task, this will directly affect
the duration of that task or
activity. So once we have that information
and we've defined the
activities sequence, the activities estimate
the activity resources estimated, the
activity durations, we can put all this
information together to produce a
comprehensive project schedule.
02:37
The estimate activity resources process
helps us understand the
following domain task.
02:45
planning task for which says develop the
project schedule
based on the approved project, deliverables
and milestones, scope and resource management
plans in order to manage timely completion
of the project.
02:59
In fact, this particular domain task task
for covers all
of the six planning processes and the
Project Time Management Knowledge
area. It's all about planning what you're
going to do and completing the
project schedule.
03:17
The key themes of the estimate activity
resources process are that what we're
going to do is to take a look at the
activities that we've forecast we're going to
do and estimate the resources required.
03:30
But then also what resources are available to
complete the activities in the schedule?
Now this is an important point because we
may estimate the resources we
want to do the work and then through a
process of negotiation, find out we don't
have all those resources available when we
want them, particularly in a weak
matrix or functional form of organization.
03:52
And as such, our first estimate of the
project resources may not be our
final estimate, and there may be a lot of
negotiation that has to happen.
04:02
And obviously, these negotiations will have
an impact on project duration.
04:07
So that's another reason why we go and
estimate the activity resources first so we
can verify which resources are available to
us.
04:18
There are quite a few inputs that we can use
to help us produce a list
of our activity resources.
04:26
Starting with, of course, the schedule
management plan, remember, good project
management starts with a plan and in this
case it's the schedule management plan, which
is an output from the plan schedule
management process.
04:39
It's going to guide all of our planning and
monitoring control activities.
04:43
So of course, we go looking for that.
04:45
The activity list and the activity
attributes both outputs
from the defined activities process.
04:53
We're going to need those as well because of
course, we're trying to estimate the
resources for each activity and we need that
information in order to estimate
the resources. The resource calendars now
these are an
output from some of the HR processes, the
human resource processes and what
resource calendars are, are they are
calendars which set the availability of
particular resources.
05:17
Now with people, the default resource
calendar would, of course, be five days a
week, excluding weekends, starting at eight
or nine o'clock in the morning, going
through to five or six p.m.
05:28
at night with an hour for lunch.
05:29
That's a default resource calendar.
05:31
And onto that, we might add public holidays,
but then we might also want to add on
vacation time.
05:38
There may be individual resource calendars
for particular resources, which indicate that
there may be part time or only available to
work on your project at certain times.
05:47
And that's why we need the resource
calendars for all of our activities so we can
see when the resources are actually
available.
05:56
We may also want the risk register.
05:59
This is because the risk register may
contain an assessment of risks
around our resources, their availability,
what the chances of
getting them are, how negotiation with
functional managers can affect the resource
allocation over the life of the project.
06:15
So we need to take those considerations into
account.
06:20
We may also want our activity cost
estimates.
06:23
Now these are an output from one of the cost
management
processes. Because we need to know how much
we've
forecast each activity will cost, because
this will tell us whether we can use
senior engineers or junior engineers,
whether we can use internal staff or
external consultants.
06:44
The cost of resources is extremely important
in estimating which
resources we want and which resources we can
get.
06:52
So make sure you have access to your
activity cost estimates now.
06:57
The activities cost estimates is an output
from the estimate,
costs process and the cost management
knowledge area.
07:05
So this is a great example of the
interrelationship between different
knowledge areas and the PMBOK guide.
07:13
Although they're presented as separate and
discrete knowledge areas, they are in fact
incredibly interrelated and often use
outputs from one
knowledge areas process into completely
separate knowledge area
processes. And again, we may go looking for
enterprise
environmental factors, things like
regulations about resource availability,
health and safety regulations, perhaps is
some external regulations about the amount
of people that must be present on a work
site.
07:44
We will need to know all of these things in
order to do our resource estimating
better. And, of course, organizational
process assets.
07:53
These are things like our project management
methodology and any relevant
processes that affect how we estimate our
activity
resources. The
particular tools and techniques that we may
choose to use, if appropriate, include
expert judgment when, as we already know,
expert judgment is the most
often used tool and technique throughout
the PMBOK guide.
08:18
And remember, you are an expert about
estimating activity resources,
your team members, the resources themselves
are experts on estimating
activity resources.
08:29
Your project sponsor.
08:31
The client. External consultants.
08:33
They're all possible relevant experts that
you may choose to
consult in order to get accurate resource
estimates.
08:42
You may also choose to use alternatives
analysis.
08:45
This is where you consider all the possible
ways to utilize resources to deliver
that activity. Should you use people?
Should you use machinery?
Should you use internal staff, external
staff?
Super experienced staff that may be more
expensive as compared to junior staff
who may be cheaper but less experienced.
09:06
You have to look at all the different
possible alternatives.
09:10
You may also go looking for published
estimating data.
09:14
Now this can be published estimating that
data that your company has
internally on what resources are available
and how much work they can
do. Or you may choose to go outside of your
company or organization.
09:27
There are many professional and commercial
companies which will provide you estimating
data on what resource availability is like
and how much work particular resources
can do. A fourth potential toll and
technique
is bottom up, estimating now bottom up,
estimating, and we're going to
see this tool and technique used in other
areas, particularly estimating processes
means taking a work breakdown structure and
breaking all of your work
down to its component parts.
10:00
Here we could stop at work package level, but
we could also go down further to
activity level.
10:05
And then for each of those activities, we
can estimate the resources required.
10:11
Now it's called bottom up estimating because
they're at the bottom level of our work
breakdown structure.
10:17
And what we can do is aggregate or add up
all of those resource estimates
upwards to get an aggregated or total
estimate of resources
for a particular deliverable or sub
deliverable.
10:30
Bottom up estimating is usually considered
to be a very accurate form of
estimating. But as I've described, it takes
a lot more time than, say,
top down estimating, which simply allocates
resources from the top
down. A final tool and technique we may find
useful
is project management software.
10:52
Obviously, we're probably not going to sit
down with some lined paper and try and map
out all of the resources that we want.
11:00
Reconcile those with the resources that are
actually available and put those resource
estimates back into a network diagram.
11:07
So having access to project management
software and there are many, many examples
globally of great project management
software that does do resource estimation and
feeds that information back into the
development of our project schedule.
11:20
You may even have your own.
11:25
If we do all of these things, we will
produce the following outputs.
11:29
The first is a list of all of our activity
resource requirements.
11:33
So now our activities list has grown with
more information.
11:38
We now have on it a description of the
resources that are
available to complete their activity.
11:45
And remember, we need this information to go
to the next step, which is
estimate activity durations.
11:53
So get those resource requirements all
sorted out.
11:56
Do your negotiation, put your risks around
it and get your list of activity
resource requirements.
12:03
We may also choose to produce a resource
breakdown structure.
12:08
Now, the resource breakdown structure is one
of four breakdown structures mentioned in
the PMBOK guide.
12:14
The other three are the work breakdown
structure, the risk breakdown
structure and the organizational breakdown
structure.
12:22
The thing that they all have in common is
they're all graphical de
compositions of a higher level concept.
12:29
And I'll show you an example of a resource
breakdown structure in a moment.
12:33
The final output that we may choose to put
together is updating our project
documents. We may choose to update our
schedule management plan or any
other organizational process assets that we
have that help us to
estimate activity resources.
12:55
So here's an example of a resource breakdown
structure.
12:59
The resource breakdown structure is I've
already mentioned as a graphical
decomposition of the resources we need.
13:06
So this example shows Project Alpha.
13:09
I'm not sure what that's for.
13:10
It could be a software project or a
construction project, but we've broken it
down into the higher level categories of
resources that we need.
13:18
We need some designers, we need some
engineers, and we need some testers.
13:23
But then with the designers, we've broken
that down even further and to senior
designers and junior designers and under
junior designers, we've broken that down
even further to say that we need some
administrative staff as well.
13:36
So that's what the resource breakdown
structure can do for you is break down all of
your resource needs for the project into
their component parts so you can double check
you've captured all of the resource needs.
13:49
So in summary, the estimate activity
resources process and the PMBOK
guide uses a variety of tools and techniques
to
estimate the resources that we need to
complete
the activities we're going to have to do on
the project.
14:07
But remember, we have to compare what we
need to the resources that are
actually available, and we may have to do
something about that if what
we need and what's available don't match.
14:21
And if we come across that, we will feed any
resource constraint information back
into the schedule development, particularly
the next step, which is the estimating
activity durations process.
14:34
So thank you very much.
14:35
This has been an overview and an
introduction to the estimate activity
resources process in the PMBOK guide.