00:01
Hello and welcome.
00:03
This is an overview of the estimate activity
durations
process from the PMBOK guide.
00:10
It's very important that you pay particular
attention to this module and the other time
management planning modules as well, because
they all culminate
in the development of the project schedule
and in the exam, there's always quite a few
questions about the development of and the
representation of the project
schedule. And you will probably have to
complete a network diagram
as well. The difficulty level is rated as
high.
00:39
Because most of these concepts you may not
have come across before nor used in your
day to day job.
00:46
And as such, with the new concepts that
we're introducing to you, there's a moderate
or medium level of memorization required for
this particular module.
00:57
The estimate activity durations process
itself is part of the project
time management knowledge area.
01:04
In fact, it's one of six planning processes
in this
area, and those six also have a seventh
process are monitoring and
controlling a process called control
schedule.
01:20
The estimate activities, duration process
comes after the defined
activities process, the sequence activities
process the estimate
activity resources process because each of
those previous processes
provides necessary information to enable us
to put together
individual estimates of activity durations.
01:42
And once we've done that with all of that
information combined, we can then go
on to develop our project schedule.
01:49
So do pay particular attention to this
module, particularly the
estimating techniques that we're going to
introduce to you.
01:58
The good news about those estimating
techniques is they're also used in cost
estimation as well.
02:04
So you'll see them again in that module.
02:09
The estimate activity durations process
helps us understand.
02:14
The following domain task.
02:16
And remember, the exam is based on the
domain tasks.
02:21
In this instance, it's planning task for
develop the project schedule
based on the approved project deliverables
and milestones, scope and resource
management plans in order to manage timely
completion of the project.
02:36
And in fact, that single domain task task
for covers
all six of the time management planning
processes.
02:46
So it's all about planning, what you're
going to do with your project schedule, then
doing it to create a project schedule.
02:56
The key themes of this estimate activity
durations process.
03:00
Well, it's to use all of the previous
information from each
of the other time management planning
processes.
03:09
Taking that information and estimating a
duration for each activity,
once we've got individual activity
durations, we can add all of those up
to give us a total project duration.
03:25
Let's start with the inputs.
03:28
And there's quite a lot of inputs here when
you think about all the information that you
could use to estimate duration, there are
quite a few.
03:36
So let's start with the schedule management
plan.
03:39
Of course, as the planning document that
guides our time management
activities, it will provide guidance on the
methods, the tools and
techniques we're going to use to estimate
activity durations.
03:53
It will also provide guidance on the
expected accuracy of our estimates.
03:59
And how we do rolling wave planning and
successive iterations and get better at our
estimates as well, so ensure that you have
your scheduled management plan and of
course, that's an output from the plan
schedule management process.
04:14
Well, you may also want our activity list
and activity attributes.
04:18
These are both outputs of the defined
activities process one of the earlier
time management planning processes.
04:26
Because of course, this these things, the
activity list and activity attributes give
us all the information about the activities
that we're going to do on the project.
04:35
And of course, what we're seeking to do here
is to estimate a
duration for each of those activities.
04:43
We may also want our individual activity
resource requirements.
04:47
Now these are an output from estimate
activity resources.
04:51
The immediate prior planning process.
04:55
This gives us the resources that we have
available to complete the activity work.
04:59
And of course, if we've got senior more
experienced staff to do the
work, they may do it faster but cost more.
05:07
If we've got junior staff, they may do it
slower.
05:11
That cost less, and therefore our duration
estimate will be more.
05:15
We may also want the resource calendars,
which are an output from some of the
human resource management processes.
05:22
These tell us when resources are available,
what sort of work week do they have?
When as vacation time?
When are they not available?
Because they're part timers.
05:32
So we need the resource calendars because
this will affect the durations.
05:36
And remember, that activity duration can
mean two things the duration of the
activity can refer to the amount of work
taken to do the activity.
05:45
For example, an activity could take two
days.
05:49
But the duration could also refer to the
amount of time it takes to do that two day's
work. You may not be able to do it in two
days because of
resource constraints.
06:00
Maybe they're not available two days a week
and therefore that two days
work could actually take a week to complete
because the resources have
other commitments.
06:10
This is particularly the case in week matrix
or functional forms of
organization, where the resources may not be
allocated full time to your
project. So take care when estimating
activity durations that you're
clear about the actual duration of the work
to be done.
06:29
That's important for cost purposes, but in
the actual time taken to do that
work, that's important for the project
schedule.
06:38
We may also wish to go get our project scope
statement.
06:41
This is to double check that we've captured
all of the project's scope, but also to see
which parts of our project scope have been
well defined and which ones are
subject to rolling wave planning and still
yet to be defined because we
can't do activity duration estimates very
accurately for those parts of the project
scope, which are yet to be defined.
07:03
We may also wish to have our risk register,
and that's, of course, as an
output from some of the risk management
planning processes because the risk
register will identify key areas of our
project that are
subject to duration, estimating risk and we
need to know those now
so we can take that into account and perhaps
add contingency reserves for
time at this point in the project.
07:30
We may also want our resource breakdown
structure, which is an output from the
estimate activity resources process.
07:38
It'll tell us all the resources that we have
available to us because at this point, with
estimating durations, we may want to provide
feedback to that particular
process and do another iteration of that.
07:50
We may want to change the resources that we
have available to us if the durations don't
stack up, if they're taking too long.
07:57
We may go looking for more senior staff
rather than junior staff or bigger
machinery rather than smaller machinery.
08:04
And of course, like many other processes, we
may wish to use enterprise
environmental factors, government
regulations, industry standards which affect
how long tasks take, and also organizational
process
assets such as our project management
methodology or any blank templates
we've got for estimating activity duration.
08:30
So we take those particular inputs that are
useful to us, and we can apply
any of the following tools and techniques
that we find useful in order to develop our
individual duration estimates for each of
our activities.
08:43
The first being exPERT judgment and as we
know, exPERT judgment
is the most popular tool within the Bot
guide and you are an
exPERT. Your project team members who are
actually going to do the work are
very valuable exPERTs as well, and you
should always ask the
people who are going to do the work for
their duration estimate of the
work. Don't be the sort of project manager
who tells people how long
the work will take.
09:14
You won't get an accurate estimate, but X,
but more importantly, you won't
get buy in from your team.
09:21
So always take the time to ask the team
members who are going to be doing the work
for their duration estimate of the work.
09:29
It's generally more accurate.
09:31
And you'll also get buy in from them.
09:34
But just a word of warning people tend to
give
estimates that they think you want to hear.
09:42
Usually, this is overly optimistic
estimates, so just be aware of that
when asking people for their estimate of the
activity durations.
09:53
The next estimating technique that we may
want to use is analysis, estimating
now analysis estimating simply means taking
an analogy, something
similar we've done before and using that to
forecast the
duration of an activity we're doing now, and
we'll have a closer look at that
in a moment. Another tool in technique that
we may wish to use
is parametric estimating.
10:20
Now, in this instance, the word metric is
simply Latin for number
. So parametric estimating takes two numbers
and
multiplies them together to get a duration
estimate for activities.
10:35
And we'll have a closer look at that one in a
moment too.
10:39
One of the formula that you're going to need
to take into the exam is the three point
estimating formula.
10:47
So in those first few moments in the exam
when you're writing down your brain dump
include the three point estimating formula
as part of that brain dump.
10:57
It's useful when we have a scenario of an
optimistic estimate, a
most likely estimate and a pessimistic
estimate.
11:07
It's a little bit of a formula we can use to
help put in an actual number
based on those three figures.
11:14
We'll have a look at that in a moment.
11:17
Another total technique, we may find useful
group decision making
techniques. Things like brainstorming the
nominal group
technique where you get the group to figure
out which ideas should go forward or
perhaps the Delphi technique.
11:33
The Delphi technique is a great way to
solicit information from exPERTs
anonymously and avoid peer pressure,
bullying or groupthink.
11:43
We'll have a look at that again in a moment
to reserves analysis
with any duration estimate, you should be
prepared to put in a
contingency reserve now.
11:54
A contingency reserve is for known unknowns.
11:58
It's for known uncertainty or identified
uncertainty in your project.
12:02
And there's many methods to do it using
historical information, such as we
know that we routinely underestimate our
activity durations by 10 per cent
perfectly valid way of adding 10 per cent
onto your duration estimates.
12:17
There are also more sophisticated methods of
developing reserves as well, and we'll look
at those more closely when we come to do
quantitative risk analysis.
12:28
Analysis estimating is simply taking a
similar activity from a previous
project to estimate the duration of an
activity we're about to complete.
12:38
So for example, we may have completed a
project recently say in the last
year where a particular activity took two
days to complete.
12:47
And we know that this time around, the
activity is twice as big.
12:51
So our analysis is to make would be four
days.
12:56
Obviously, the great thing about analogous
is debating as it can be done very quickly.
13:01
But the accuracy may not be what we need at
this point, depending on
how relevant the information about the
previously completed activity is and how good
our estimate of the magnitude of this
activity is compared to that one.
13:16
We're also seeing analogous estimating used
later on in our cost
estimating module.
13:22
So look out for that.
13:25
Parametric estimates take one number and
multiply it by another
number to give us our duration estimate.
13:33
So for example, if we know that we can
excavate 10 meters of trench a
day and we have 30 meters to do so, our time
estimate, well, that's
three days for that particular activity.
13:46
We're taking two numbers and multiplying
them together, and we will also see
parametric estimating as a valuable tool and
technique for the cost
estimating processes as well.
13:58
Now, pay particular attention to 3-point or
PERT
estimates. There will always be questions in
the exam which require
you to calculate three point estimates.
14:11
They're often called PERT estimates because
they are part of the program evaluation and
review technique, which also gave us things
like activity on know diagrams and
the critical path method.
14:22
So you may sometimes see it referred to as
the PERT formula.
14:26
The more proper name for it, though, is the
three point estimating technique because we
have three points.
14:32
We have an optimistic estimate, a most
likely estimate and a pessimistic estimate.
14:38
Now there are two forms of this formula.
14:41
The more uncommon form of the formula is to
simply add up those
three estimates the optimistic the most
likely in the pessimistic and get
a simple average from them, in which case we
would divide by three.
14:55
And that would give us a simple average of
those three numbers, and that would be the
number that we would put into our activity
duration estimate.
15:04
A more complex form of the equation, though.
15:08
Takes those three numbers.
15:10
And here you'll see the formula is T for
time, we'll see this
exact formula appear and cost estimating
with that T replaced by
a C for cost.
15:22
So I choose to remember it without the T and
without the sea and simply
as our optimistic plus four times our most
likely
plus our pessimistic estimate divided by
six.
15:36
And this time what we're getting is a
weighted average, not as simple average.
15:41
Remember, for the simple average, we simply
divided by three because there were three
numbers with the weighted average.
15:48
There are now six numbers.
15:50
There's a single optimistic number, a single
pessimistic number, but there is
for most likely numbers.
15:58
Obviously, we are giving greater weighting
to the most likely estimate now,
as an aside, you can get quite complex with
this and change all of those
weightings. As long as it adds up to six,
there's plenty bits of software that will
help you do that.
16:14
However, for the exam, it's one optimistic,
one
pessimistic and for most likely, and we take
those and divide
by six. Once we have that, we can also
calculate a
standard deviation.
16:30
Now, the standard deviation we can use to
give a range of certainty
of delivery of a particular duration
estimate, and we'll have a look at an example
in a moment. Now, the actual formula for
standard deviation is very
complicated and something that statisticians
would love to look at.
16:48
Our formula that you need to remember for
the exam is what we call a heuristic or rule
of thumb. It's a very simplified version of
the big standard
deviation formula.
16:58
And in this instance, we're simply going to
take our pessimistic from it,
subtract our optimistic and divide by six.
17:08
P minus o divide by six gives us our
standard
deviation, and I'll show you an example of
that in just a moment.
17:18
There is another variable we can get, and
it's called the variance.
17:22
And it's simply the standard deviation
squared.
17:26
Now for the purposes of the exam.
17:30
You need to know if you're presented with
the variance and asked to
calculate a range of uncertainty.
17:37
One standard deviation two standard
deviations.
17:40
Three standard deviations.
17:41
Either side of a mean the first thing you
must do to that variance is to
calculate the square root of it to get the
standard deviation.
17:49
Watch out for that in the exam.
17:52
So let's take a look at some examples.
17:55
Here we have the three point estimate.
17:58
Let's say we have a pessimistic estimate of
15 days for a particular
activity, an optimistic estimate of five
days for a particular
activity and a most likely estimate of eight
days.
18:12
This is how we would calculate our three
point estimate.
18:16
We would take five plus eight times for plus
15 and divide
that by six.
18:23
So we get five plus 32 plus 15 divide by
six,
which gives us 50 to divide by six, which
gives us a three
point estimate of eight point sixty six
days.
18:37
And that's the estimate that we would put
into our activity duration estimate
if we were using that technique.
18:46
For your exam study, make sure you put extra
emphasis on understanding this
formula and doing some calculations to make
sure you get the right number.
18:59
Let's take a look at standard deviations
now, standard deviations are
useful to determining the total amount of a
population within a normal
distribution.
19:10
And we know that one standard deviation
either side of the mean contains
68 per cent of the total population and that
two standard
deviations either side of a mean, contains
95 per cent of the
total population and three standard
deviations either side.
19:28
The mean contains ninety nine per cent of
the population.
19:33
As an aside, and as we'll see when we come
to quality management, six
standard deviations, or Six Sigma contains
ninety nine point nine ninety
nine per cent of the population.
19:45
But for now, we just need to know one
standard deviation, two standard deviations
and three standard deviations either side of
the mean.
19:52
And you will need to know those figures for
the exam.
19:56
So let's take a look at our previous
example, where we had a mean of eight
point sixty six days.
20:04
You'll recall we had a pessimistic estimate
of 15 days and an
optimistic estimate of five days.
20:11
So let's calculate our standard deviation.
20:14
It's our pessimistic minus our optimistic
divide by six.
20:19
So in this case, it's 15 minus five divide
by six,
which gives us 10 divide by six, which is
one point sixty six
days. Therefore, we could say if we wanted
to
express a 68 per cent certainty that our
range
was, we are 68 per cent certain we could
deliver this
activity in eight point sixty six days plus
or minus one point
six six days.
20:49
Or if we wanted to say with ninety five per
cent certainty the
range at which we could deliver this
activity, we would say it's eight
point sixty six days plus two standard
deviations, which is
three point thirty two days.
21:05
And that's the value in determining a
standard deviation to be able to
communicate a range of certainty and
uncertainty for a duration
estimate. So make sure you take into the
exam those figures for standard
deviations. Sixty eight per cent for one
standard deviation.
21:22
Ninety five per cent for two standard
deviations, ninety nine per cent for three
standard deviations and no, the formula.
21:30
And once again, even though t for time as
present in this
formula, I prefer to remember it simply as p
minus.
21:37
So over six, because it's exactly the same
formula when we come to cost,
except the T is replaced by a C.
21:46
Group decision making techniques, I've
mentioned them already, but let's take a
closer look at some of them.
21:52
What we're trying to do here is to get a
group of people to come up with some ideas,
using group creativity techniques and in
terms of tools and techniques, and then PMBOK
guide. There is a big overlap between group
creativity techniques and group
decision making techniques.
22:08
There is a big overlap here.
22:10
I've combined the two, so we may get a group
of experts together
and we want a particular decision made.
22:17
So first up, we start with brainstorming
about all the particular decisions that we
could make. We could use the nominal group
technique, which is then taking
all of the ideas and decisions that we could
make.
22:29
Remember in this instance about individual
activity duration estimates.
22:34
And we asked the group to vote on which ones
are further worthy of further
exploration. That's the nominal group
technique.
22:42
One of my personal favorites, though, is the
Delphi technique.
22:46
Think about this if you have a group of
exPERTs together in the room and you
ask for their opinion.
22:53
What normally happens is the loudest person
wins.
22:57
Introverts, junior staff tend not to speak
up so much, the Delphi
technique helps us get around that instead
of bringing people together in a room.
23:06
What we do is invite them to participate in
our survey or information
gathering. We don't tell them who else is
involved in the survey.
23:16
We give them questions and we ask them to
provide their considered responses to those
questions. We then take all of those
responses and send them out to all the
participants in the Delphi technique.
23:28
And without identifying any of the other
authors, we ask them to read the
feedback received and if they wish to, they
can then change their answer based
on their. It's a great way not only to get
creative creative techniques, but to also
get decisions made.
23:44
So once we have those.
23:47
Another thing to think about is when you're
trying to make decisions, particularly about
duration estimates is the actual way that
final decisions will be made.
23:56
Here are some useful techniques to consider
before making the decision
about how the decision will be made.
24:03
Will you have a consensus, as in the
decision will not be made until
everybody agrees on the particular duration
estimate?
Will you require a simple majority?
Or will you require a firm majority before
you agree to that
decision, or will you appoint a single
decision maker whose job it is to take
everybody's opinions on board and then make
the decision?
It's worthwhile giving all of these things
sorted out beforehand, and they could all be
captured in your schedule management plan.
24:39
The outputs that we may produce from
estimate activity durations
are our individual activity duration
estimates.
24:48
And once again, the information about each
of the activities in our activity
list is now growing.
24:54
We have the resources allocated to them by
the previous process is to make activity
resources. And now we have individual
duration estimates, estimates
allocated to them as a result of this
process.
25:07
But remember, we still don't have a project
schedule that comes
next. We may also choose to update
significant and relevant
project documents like our Schedule
Management Plan or parts of our project
management methodology as part of our
continued commitment to continuous
improvement. So in summary, the estimate
activity
durations process takes information from the
previous time management
planning processes.
25:38
And applies that to give us individual time
estimates for each
activity. Thank you.
25:46
This has been an introduction to the
estimate activity durations process in the
PMBOK guide.