00:01
Hello and welcome.
00:03
This module covers the develop schedule
process of the PMBOK
guide. You'll see that it's rated high for
difficulty
memorization and exam importance.
00:17
There will definitely be questions in the
exam on this topic, so pay
particular attention.
00:23
You will be expected to complete a network
diagram or be presented
with a completed network diagram and asked
questions about it.
00:34
It's rated high for difficulty because a lot
of these concepts you may never have used
before in your day to day job because a lot
of them are what actually goes on
behind the scenes of project management,
scheduling software
and in terms of memorization.
00:50
It's rated very high as well because of all
the new concepts we have to
introduce you to.
00:56
There may also be hidden within project
management software and done automatically
so the developer schedule process.
01:05
Is the sixth of six planning processes and
the
project time management knowledge area.
01:14
There is a single monitoring and controlling
process in this knowledge area as
well. And that's control schedule, but the
developed schedule process is the
culmination of all of the previous planning
processes and the
work that they've done.
01:31
We started off with a development of our
schedule management plan,
and we used that to guide all the rest of
our planning work.
01:41
We defined our activities and produced an
activity list and activity
attributes. We sequenced our activities and
produced an activity on
node diagram showing predecessor and
successor relationships
and the dependencies between activities.
01:57
We then estimated the activity resources.
02:00
And with that information, we estimated
individual activity
durations. Now we're going to bring all of
this information together to
produce our project schedule.
02:14
The developed schedule process helps us
understand the following domain
task monitoring and controlling task for
which
says develop the project schedule based on
the approved project
deliverables and milestones, scope and
resource management plans in order
to manage timely completion of the project.
02:36
Now, the single domain task actually covers
all of
the time management planning processes, so
it's pretty important for
the exam that you pay attention to this one.
02:50
The key themes of the developed schedule
process are, as
I've already mentioned, we're going to bring
together all of the outputs from the
other time management planning processes to
produce an agreed upon
project schedule.
03:08
Once we have that.
03:10
Not only can we determine individual
activity durations, but we'll be able to
determine the entire project duration or
parts of a project duration.
03:20
And calculate the critical path.
03:24
Using the network diagram, and we're going
to show you how to do all of
that. So pay particular attention to this
module.
03:35
There are quite a number of inputs, most of
them are outputs from the previous
time management.
03:43
Knowledge area processes, but see if you can
spot within these inputs
outputs from other knowledge areas such as
risk or
cost or human resources.
03:55
So the first input that we would go looking
for would be our schedule management plan
because of course, the planning document
provides guidance on how we do the
work in the project, and that includes the
planning work.
04:08
And as I've said, the develop schedule
process is the culmination of all our
planning work. But that doesn't mean it's
the end of our planning work.
04:17
Don't forget that project management is
always subject to iterations and
progressive elaboration.
04:24
So we may initially start with a fairly
loose project schedule.
04:28
Then, as we know more information about the
project, our schedule becomes more defined.
04:33
There may also be changes that we encounter
in our product project, which
define or define changes to our project
schedule.
04:42
The Schedule Management Plan will guide us
on all of these activities.
04:45
So that's why we go looking for the schedule
management plan.
04:49
It's one of our primary inputs.
04:51
We may also want the activity list and
activity attributes both
outputs from the defined activities process.
04:59
One of the earlier time management knowledge
area processes.
05:04
We may also want our project schedule
network diagrams.
05:09
That's an output from the sequence
activities process.
05:13
We may want our activity resource
requirements, so we know what resources are
available to complete the work.
05:20
That's an output from the estimate activity
resources process.
05:26
The resource calendars.
05:28
Direction output from some of the processes
and the human resource management knowledge
area, and they define the constraints upon
resource availability.
05:37
So if it's people, it could be the resource
calendars determining and
defining the regular work week public
holidays vacation
time if the resource calendar is for
machinery.
05:51
It may define when machinery is available to
you and when it's not.
05:56
And this is particularly important if you're
working in a weak matrix or functional form
of organization where this constant
negotiation and renegotiation for
resources on your project.
06:09
We also want our activity duration
estimates, which are an output from
estimate activity durations.
06:16
One of the previous time management
knowledge area processes.
06:21
We may want our project scope statement so
we can double check that we've captured the
entire project scope and of course, the
scope statement is an output
from the defined scope process out of the
scope management knowledge area.
06:36
We may also want our risk register, which is
an output from
several of the risk management planning
processes because the risk
register is going to identify uncertainty
about our
project schedule and we need to build into
our project schedule.
06:54
That uncertainty and account for it and also
communicated.
07:00
We might also want projects, staff
assignments, which is an output from some of
the human resource management processes.
07:08
These are specific assignments for project
staff on a particular part of the
project and the roles they'll take and the
work they're expected to do.
07:19
We may want our resource breakdown structure
just so we can double check we've
accounted for all of the resources that we
need.
07:27
We may also want to take into respect
enterprise, environmental factors and
organizational process assets as appropriate
for the development of our projects
schedule. So once we have all of those
inputs,
we can then choose which of the following
tools and techniques are most
appropriate to use in order to develop our
approved
project schedule, which of course, is the
goal of this process.
07:56
The first tool and technique that we may
choose to use is schedule network
analysis, and this is where we're going to
use our network diagrams
and we're going to complete a forward pass
and calculate the project
duration. And then we're going to complete a
backward pass and calculate
slack or float in each of the activities.
08:18
And then using the critical path method,
take that information
from our schedule network analysis and
determine which of the many paths through our
project is in fact, the critical path or
paths.
08:32
Keep in mind for the exam, they can be more
than one critical path through a
project. However, many critical paths there
are, they will
always be the same duration and there will
be no slack or
float on the critical path.
08:48
Now, just a word on slack and float.
08:53
We know that the PMBOK guide is made up of
what is generally considered good
practice most of the time and most projects,
and during the preparation of the
PMBOK guide, a whole lot of useful project
management information was gathered
now for the purposes of making a concise
body of knowledge.
09:12
A lot of that information was not included in
the Pembroke guide.
09:17
A lot of it was put to one side, but the
PMBOK guide clearly recognizes the
value of all of it, but it's chosen to
simply include.
09:27
Just those bits that the majority thought
were more important.
09:31
What's interesting is one of the other
things that the PMBOK guide does is
attempt to give a single terminology because
as we know, the profession of
project management often uses multiple words
to mean the same things.
09:46
And the PMBOK guide offers a single
terminology or lexicon for the
profession, except when it comes to the word
slack and
float. It's one of only.
10:00
Two times in the hole of the PMBOK guide
were two words are used to
mean exactly the same thing.
10:07
So feel free to use the word slack and float
interchangeably,
and that applies to free float and free
slack.
10:15
Total float and total slack as well.
10:19
Of course, free float or free slack is the
amount of float or slack and
activity heads in it before it affects the
next activity in the
path. Total float, or total slack, is the
amount of
float or slack and activity heads in it
before it affects the total
project duration.
10:41
Another method we could use is the one
developed by Eli Goldratt, and that's
critical chain method, where we insert
non-working time
buffers into particular parts of our network
diagram when
we know we have uncertainty in our
durations.
10:59
And we want a no surprises approach.
11:02
So we insert non-working buffer time into
our network
diagram and we can use that buffer up like a
bank account.
11:11
There are several different ways to handle
unused buffer.
11:15
But for the purposes of the exam, if you see
a question referring
to buffer.
11:22
You know that it's referring to critical
chain method.
11:26
We may also wish to use resource
optimization techniques,
techniques such as resource leveling to get
the most efficient allocation of resources.
11:36
However, a commitment to resource
optimization can have impacts
upon our project duration and we need to
take that into account.
11:45
We'll have a look at another example
shortly.
11:48
Other tools and techniques we may choose to
use modeling techniques,
particularly those using software using what
if?
Scenario analysis or Monte Carlo analysis.
12:02
So if in the exam, you see a reference to a
supercomputer or
a computer being used using linear
regression or mathematical models
to figure out different permutations of your
project schedule, you're using
modeling techniques and most likely what if
scenario analysis or
Monte Carlo analysis?
We may also choose to use leads and lags as
appropriate.
12:28
Now, if you recall from estimate activity
durations, we use leads and
lags as well as a tool.
12:36
There we were, applying leads and lags.
12:39
Here we are, adjusting leads and lags once
again to put
together our project schedule.
12:47
We may also choose to use some schedule
compression techniques.
12:52
Now this occurs when we present our project
schedule to stakeholders
and they tell us, do it faster.
13:01
We may wish to investigate the use of either
crashing or fast
tracking as a way to do the project or parts
of the project
faster. We'll cover this again shortly.
13:14
But remember, the two most popular forms of
schedule compression technique
are crashing, which involves allocating more
resources to an
activity to do things faster and therefore
generally it costs money.
13:29
The other technique is fast tracking, where
we would
optimally like to do activities in sequence.
13:37
But because their discretionary
dependencies, we choose to do them
overlapping and take on a bit more risk.
13:43
So I have a question in the exam implies
spending money to
speed up the project schedule that's
crashing.
13:52
Or alternatively, if it asks you which
technique to use and you have no more money
available to you.
13:57
You can't use crashing and you would have to
use fast tracking the
final tool and technique that we may find
useful as a scheduling tool.
14:07
Usually this is in the form of software.
14:10
And there are many, many, many fine forms of
project management scheduling software out
there on the marketplace.
14:18
I do recommend becoming very proficient in
them.
14:21
And as I said at the beginning of this
module, a lot of what we're about to cover is
what actually goes on behind the scenes of
the project management software.
14:31
So for the exam, you need to know all of this
because there will be questions on it and
your day to day life.
14:37
You may never need to use these things
again, but you'll have a greater
understanding of how you're scheduling tools
are working.
14:46
So let's take a closer look at some of those
tools and techniques.
14:51
The first being resource optimization
techniques using a resource
histogram. Now the graph in front of you.
14:59
That's a histogram and that shows our
project
schedule and the resources that we need in
each time period.
15:08
So as we can see here, there's a lot of work
being done early on in the year in January.
15:13
But if you have a look at April, there's
very little work being done at all.
15:17
But we've got our project duration.
15:20
And how long we expect our project to take.
15:23
But overall, it's not a very efficient
allocation of resources.
15:27
And also, we may find out that we're subject
to a maximum number of
resources. And this case, the dotted red
line indicates the maximum
numbers of hours per week we have for senior
designers.
15:40
And that is one hundred and seventy five.
15:43
But there are clearly times in January
where, according to our first
pass at our project schedule, we need more
than one hundred seventy five hours.
15:52
Obviously, if we had budget, we could bring
in consultants or contractors to fill that
gap. What we may choose to do is instead
level the
resources to get a more efficient allocation
and not incur these
costs because as well as there being an
oversubscription of resources in
January, take a look at April.
16:14
If those staff are on salaries, they're
sitting around doing nothing for
April. So during the development of your
project schedule, you may look
at greater efficiencies of resource
optimization, and you may look at the
consequences of moving some of that work in
January.
16:31
Later on, in order to get below the maximum.
16:37
But that decision may impact upon the total
project duration
and may make it longer in the same way that
moving some of that work to the
down period in April.
16:48
So you don't have staff sitting around doing
nothing may also extend the
project duration.
16:56
Your decisions about resource leveling will
come down to the primary constraints on your
project as your project primarily
constrained by resources, by
time or cost that will dictate the extent of
resource leveling that you
undertake. Now, most resource leveling is
done by project management
software. I certainly would never encourage
you to sit down with a piece of graph paper
and try and do it yourself.
17:22
But be very careful when using project
management software to do resource leveling,
because unless you've input individual
resource calendars for each
individual resource in their software,
choosing the automatic option can lead to
some interesting results.
17:40
Modeling techniques, we can use these to
give us different
permutations of different scenario
possibilities, and we may want to try
and figure out which is our most likely
outcome of a particular project schedule.
17:54
And this case, we're going to need a
computer.
17:58
And we're going to use that computer to run
through many simulations with different
probabilities and different outcomes and
give us likely outcomes for our schedule
for a project.
18:09
Now for the exam, you just need to know that
modeling techniques
involve a computer linear regression and if
so.
18:20
They are generally going to be what-if
scenario analysis or
Monte-Carlo analysis.
18:27
Just as an aside, Monte Carlo analysis got
its name because it was used
during the development of the Manhattan
Project in World War Two and one of the
uncles of one of those developers like to
gamble at the casinos and Monte
Carlo. Critical chain
methodology, remember, this module is going
to focus mainly on critical
path methodology.
18:54
So in the exam, make sure you read the
question carefully Is it talking about
critical path methodology or critical chain
methodology?
Critical chain methodology was developed by
Eli Goldratt, and what it
does is it adds a schedule buffer between
activities.
19:13
Now this buffer is based on transparent
information.
19:17
It's based on historical information and
knowing uncertainty.
19:22
It's not a case of simply padding of
estimates.
19:26
Remember, for the exam, padding of estimates
is considered unethical.
19:31
Now, padding is simply making up a number
with no justification
for either cost or time estimates.
19:38
Here, though, these buffers are based on
expert opinion,
historical information and a lot of other
factors.
19:47
And the primary focus of putting these
buffers in is to make sure that no activity
exceeds its float.
19:54
So it means that you've identified some
uncertainty, in particular activities or
chains of activities.
20:00
Based on historical information, perhaps,
and we've decided to put a buffer in there of
three days or five days or seven days.
20:08
And it means that should the activity use
none of its buffer, it will finish
before that buffer starts.
20:14
But if that uncertainty eventuates, it can
use some of that buffer up
and you still don't affect the end project
duration.
20:24
Now, different organizations have different
rules and policies about what happens to
unused buffer, whether the project duration
is brought forward or the
buffer can be then used for other parts of
the critical chain for the purposes
of the exam. You need to know critical chain
means buffers.
20:43
So if you see a question referring to
schedule buffers or Eli Goldratt, it is
referring to the critical chain method.
20:53
The outputs from the developed schedule
process include our schedule
baseline. Are we going have a very close
look at this in a moment with a large
example? The schedule baseline is, of
course, one of three
baselines in the profession of project
management.
21:10
The other two being our scope baseline and
remember the scope baseline as
our scope statement, plus our work breakdown
structure, plus our work breakdown
structure dictionary.
21:21
We also have our cost base line or budget.
21:25
Sometimes is also a quality baseline.
21:28
But we use our baselines to measure project
performance and we compare
what's actually going on to the baseline.
21:36
And if we find a difference between what's
actually going on and the baseline, remember
we act on it.
21:42
We always make sure that our baselines and
what's actually going on are equal.
21:47
We may choose to change what we are actually
doing or change the baseline
whatever we choose to change.
21:54
We use our approved change control process.
21:57
We produce the project schedule.
22:00
We produce individual schedule data about
different aspects of it.
22:06
We've reduced our project calendars, which
tell us when our project will be occurring
and we know it won't be occurring.
22:13
We also may choose to give updates to our
Project Management Plan and all
of its subsidiary plans, documents and
baselines as a result of our
first and subsequent attempts at putting
together our project schedule.
22:27
Remember, our first go at putting together a
project schedule could have huge implications
for project cost or quality or stakeholder
expectation management.
22:37
So as a result of the iterations we do
preparing our project schedule, we
may wish to update other parts of our
project management plan.
22:47
We may also wish to update significant
project documents, particularly lessons
learned and also our project management
methodology.
22:58
Here's one way that's typically used to
represent a project
schedule. The Gantt-Chart.
23:06
You notice Gantt-Chart has always spelt with
a capital, G.
23:11
It's a surname of Henry L.
23:13
Gantt-Chart, who was a mechanical engineer
in the early part of the 20th century, who's
first credited with using this particular
form of chart to show relationships
between activities, and it is the most
popular form of showing a
project schedule.
23:29
I'm sure that you've prepared a Gantt-Chart
in your time using project management
software. A milestone
Chat is particularly useful as well for
showing significant parts of our
project schedule the milestones we need to
meet remember a
milestone has no duration, zero duration and
as an
aside, it's always represented by that
diamond shape that's an international
standard for representing the milestone.
24:01
Another great thing about the milestone Chat
is it's a very effective form of
communication for senior managers.
24:09
Sometimes is a question in the exam, which
says something like you've been
called into a meeting with senior managers
who want to know about your project schedule.
24:19
What is the best form of information you can
take them?
Well, because senior managers are busy and
they want succinct information.
24:27
You don't take in your whole project
schedule, you've taken your milestone
chart. Show them the high level information.
24:38
As I've already mentioned in terms of
schedule, compression techniques or speeding
up the schedule, there are two main
techniques you have available to you.
24:47
Crashing is where you add more resources to
the activity
and therefore it generally costs money.
24:54
These resources are generally in the form of
approving over time or bringing in external
consultants or hiring extra machinery from a
higher company.
25:04
So adding those extra resources in order to
do the work faster generally
costs money.
25:10
So remember that in the exam, look for that
clue.
25:13
And the question does the schedule
compression technique involve more money?
Then it's probably crashing.
25:20
And if you don't have any more money, you
can't use crashing as a preferred
technique to speed up the schedule.
25:28
The other schedule compression techniques
that you'll be asked about include fast
tracking. And this is generally where you
would have preferred to do
activities and sequence activity A then
activity B, but in
order to make things faster, you start
activity B prior to the end
of activity A.
25:49
Obviously, it relies on a discretionary
dependency between the two
activities, and you're taking on board an
extra bit of risk as well.
25:59
And you can't have the same resources
allocated to activities A and B, they
generally work best when there's different
resources allocated to them to keep those to
schedule compression techniques in mind for
the exam crashing and fast
tracking. Now we're going to take a closer
look
at the critical path method, and this is
going to involve completing a network
diagram. So pay particular attention to the
next part in this module
because you will be asked questions in the
exam about the critical path method.
26:32
You will be expected to either complete
network diagram, comment on an already
completed network diagram or make some
changes to an existing network diagram.
26:42
So the critical path method is a way to
figure out how long a project is
going to take, but also how long an activity
can be
delayed before delaying the entire project.
26:56
And of all the potential paths through our
project, which one or
multiple are our critical path now?
Any critical path in our project means that
if an activity on that
path is delayed, our total project duration
will be extended.
27:13
Hence, why we call it the critical path.
27:17
We focus on that.
27:18
That is where we pay most attention to.
27:22
Of course, during a project, our initially
identified critical path can
change if there's very big delays on
activities that aren't on the critical
path. The critical path can change, so watch
out for that as well.
27:38
Now we're going to take you through an
example of putting together a network
diagram, using an activity on node diagram.
27:47
I'm going to use a node that looks like
this.
27:50
Each of the nodes has this information in
it.
27:54
In the top left hand corner is going to be
the early start, which is the
earliest an activity can start in.
28:02
The top right hand corner of the node is
going to be the early finish.
28:06
And that's the earliest this activity can
finish.
28:10
And the bottom left hand corner.
28:12
We're going to have the late start, which is
the latest this activity can start.
28:18
The bottom right hand corner is going to
have the late finish, which is
the latest.
28:25
This activity can finish in the top line in
the middle.
28:29
We're going to indicate the duration of the
activity.
28:33
In the middle, we're going to put the
activity ID number or description.
28:38
And the bottom line in the middle, we're
going to indicate the slack or float and that
activity. So let's take you through an
example.
28:47
This is the information that we're going to
use and turn this into a network
diagram. You may want to write this down and
practice putting together your own
network diagram.
28:58
So we've got activities a, b, c, d, e, f,
g and H.
29:05
We've got our duration for each of them.
29:08
Activity A has three days duration activity,
g four days
duration and so on.
29:15
And we've also indicated the predecessors
for each of our activities.
29:20
So Activity D, for example, has a duration
of two days and it has
activities B and C as predecessors.
29:29
Now for this example, we are assuming a
finish to start relationship
between all of our activities, which makes
it nice and easy for us.
29:38
But what chart in the exam?
Sometimes they start to start or finish to
finish
relationships. There may even be finished to
start with a lead or
lag applied.
29:51
So you need to practice your network diagram
with each of those scenarios in it.
29:56
So let's take the information in this table
and put together our network diagram
will then complete a forward pass to figure
out our total project duration
and then we'll complete a backward pass to
figure out our critical path.
30:11
So the first thing that we must do is put
together our network diagram using that
information about predecessors and
successors.
30:20
Here is the network diagram for that
information.
30:23
You'll see that Activity A is our first
activity and it has three days
duration. A successor to Activity A is
Activity B
with five days duration.
30:35
Also, Activity C with four days duration.
30:40
Activity D has two predecessors activities
B and C, and so on.
30:48
And we've indicated.
30:50
What the durations are for each activities
and at the end of this first step.
30:55
What we have is a network diagram using the
precedence
diagramming method, specifically the
activity on node diagram.
31:04
But we don't have our project schedule yet,
do we?
There's no project duration and there's no
critical path.
31:11
These are the next steps we're going to
complete.
31:15
So the next thing we do is we calculate a
forward
pass. And this is where we move from left to
right.
31:25
And as we move through the network diagram,
we calculate the early start and
the early finish of each of the nodes.
31:34
Now the way we do this is we start with the
early start and
we add that.
31:40
Well, add to that the the activity duration.
31:44
Now I can see you looking at activity, a
going well, hang on a moment.
31:48
One plus three should equal four.
31:52
Let's take a closer look at that, though.
31:54
So Activity A begins at the beginning of day
one.
32:00
It's three days long.
32:02
So at the beginning of day one, then day
two, then it ends at the end of day
three. So we're going to say that Activity A
is three days
long. It begins the earliest it can start is
the beginning of day one,
and the earliest it can finish is actually
the end of day three.
32:20
There are some other methods of calculating
this which would have it start at zero
and that, but we won't use that for the
purpose of the exam.
32:28
You will use this numbering technique.
32:30
Just be aware there are some textbooks out
there which use a slightly different
numbering technique. This is the numbering
technique that's in the PMBOK guide.
32:37
So activity a.
32:40
The earliest it can start is the beginning
of day one.
32:43
It has three days duration, so day one day
to day three.
32:48
It ends at the end of day three.
32:52
Now, take a look at Activity B, it's an
immediate predecessor to activity
A.. So the earliest it can start is in fact
the beginning of day
four. Remember activity a end at the end of
day
three? Activity B begins at the beginning of
day for
activity B has five days duration.
33:15
So beginning of day four day, five day, six
day
seven end of day eight, that's five days.
33:23
So the earliest activity B can finish is day
eight
activities. C also has Activity A as a
predecessor,
and it two can start at the beginning of day
four.
33:38
It has four days duration, so it starts at
the beginning of day for day
four day five day six.
33:45
The end of day seven is the earliest
activity C can finish.
33:51
So let's continue with our forward pass and
look at activity D
now, of course, Activity D has two
predecessors Activity
B and Activity C.
34:05
So the earliest activity D can start.
34:10
Is after the lighter of its two
predecessors.
34:14
Now, of course, activity see ends at the end
of day seven, but
Activity B doesn't end till the end of day
eight.
34:22
So Activity D, which is a successor to both
of those,
can't start.
34:29
Until the beginning of day nine.
34:31
So the early start for activity day is the
beginning of day nine.
34:35
It has two days duration.
34:37
So that's the beginning of day nine end of
day 10 for its early finish
activity. A has an early start at the
beginning of day eight, which is immediately
after the early finish of activity.
34:49
See on day seven.
34:51
Activity E has six days duration beginning
of day 8, 9,
10, 11, 12.
34:58
End of day 13 as the earliest activity can
finish.
35:03
We go on to calculate activity, if once
again it has
two predecessors.
35:10
So we look at each of the predecessors
Activity D and Activity A,
and we look at each of the early finishers
activity.
35:20
D has an early finish of day 10
activity A has an early finish of day 13, so
it has to be the
higher or later of the two predecessors that
affect activity
if in this case, activity A.
35:36
and day 13.
35:38
So activity if can start at the beginning of
day 14.
35:42
It has five days duration.
35:44
So days 14, 15, 16, 17 end of day 18, that
becomes
the early finish for activity.
35:52
If Activity G only his one predecessor and
that's
activity A.
35:59
So it can start immediately after the early
finish of activity a day
13 so it can start at the beginning of day
14.
36:07
So the early start for Activity G is day 14.
36:11
Four days duration takes us to an early
finish of day 17,
and now we come to the last activity in the
network diagram activity H.
36:22
Again, it has two predecessors activity if
and
activity G, the higher of the two
predecessors, early finish
is activity if with 18.
36:35
So activity H, the early start is the
beginning of day 19.
36:41
It has seven days duration, so that means it
ends at the end of day
25 and that's a forward pass.
36:50
Now we don't have a project schedule
completely yet, but what we do have
is a project duration and that's twenty five
days.
37:00
Forward path left to right.
37:03
Calculating early start and early finish the
entire way and with a forward
pass, we end up with our project duration.
37:11
Now let's take a look at a backward pass.
37:14
This is where we move from right to left.
37:17
Calculating late start and late finish.
37:20
Pay particular attention to the backward
pass as it may take you several attempts to
understand it. What we're going to do in
this instance is calculate the
late finish and the late start now for
Activity H, which is
the last activity in our network diagram.
37:38
The late start and the late finish are the
same as the early start and the
early finish.
37:45
You can see an activity h.
37:47
We've calculated the amount of slack or
float in that task that's calculated
by subtracting the early start from the late
start or the early
finish from the late finish.
37:59
It will give you the same answer.
38:01
So in this case, using the early start and
the late start 19 minus
19, we can see we've got zero slack or float
in activity
h. So let's work backwards now from right to
left.
38:15
The next one we want to work out is the late
start for activity if and the late
start for activity G.
38:22
This time we look to the successor
activities and we look to
the late start of our successor
activities. In this case, the late start of
activity is eight day
19. Therefore, the late finish for both
activity if an activity
G is day 18.
38:44
Now we can simply subtract the duration from
those late finishes
in order to get our late starts.
38:52
One of the tips I have is that the
difference between your early
finish and your late finish will be the same
as the difference between your
early start and your late start.
39:05
So for activity F our late finish is day 18.
39:11
A late start as day 14.
39:14
We can see that our slack or float is zero
for activity if
for activity G, on the other hand, our late
finish is day
18. Which makes our late start day 15.
39:29
Now, if we subtract one of our earlies
either our early start or early
finish from the equivalent late start or
late finish.
39:37
So 15 minus 14, we get slack or float of one
day,
which means that activity g the earliest it
can start as day 14, the
latest it can start without affecting the
project.
39:49
Duration is, in fact, day 15.
39:52
It has one day slack or float.
39:54
Now let's continue with our backward pass
and calculate the late finish and late start
for activity D and the late finish and the
late start for activity e
activity D is the simpler to calculate.
40:07
So let's start with it.
40:09
It has a single successor activity activity.
40:12
If so, the late finish for activity D is
immediately
before the late start for activity.
40:19
If so, in this case, the late finish is day
13.
40:24
With a two day duration.
40:25
The late start becomes day 12.
40:29
Now, if we subtract our early start from our
late start, 12 minus
nine, we get three day slack or float in
activity day.
40:38
We like that activity.
40:40
It's got three day slack or float in it
activity a.
40:44
On the other hand, has two successor
activities, so we need to look at them
both. And look at the smaller of the two
late stats
activity. If has a late start of day 14
activity G has a
late start of day 15.
41:01
So the one that we want is activity if and
it's late start of day 14.
41:06
So activity a it's late finish becomes day
13
immediately before the day 14.
41:13
Late start of activity if.
41:16
With six days duration, the the late start
becomes
day eight, and there's no difference at all
between our early start and our late
start, so we have zero days slack or float
and activity a.
41:31
Working backwards again.
41:33
Activities see has a single successor
activity.
41:38
So the late finish for activity C is day
seven, which is immediately
before day eight, the late start for
Activity A with
four days duration.
41:49
The late start becomes day four.
41:52
Once again, there's no difference between
our early start and our late start.
41:56
So the slack or float is zero days.
42:00
Activity B, its late finish is immediately
before
the successor activity activity D, so that's
a late
finish of day 11 with a duration of five
days, it has a late start
of day seven.
42:17
The difference between our late start of
seven and our early start of four is three
days, so Activity B has three days slack or
float in it
and finally coming all the way back to
activity A..
42:31
So remember, we look at both of its
successor activities, activity B
and Activity C, and we look for the smaller
of the two late
stats, which in this case is activity.
42:43
See with a late start of four days, which
means that activities a
late finish is the end of day three.
42:52
It's got a three day duration.
42:54
Therefore, it's late start is the beginning
of day one.
42:57
Once again, there's no difference at all
between our early start and our late start,
so the total float is zero.
43:04
Now we've completed a forward pass to find
out our project duration and a backward
pass to work out our critical path.
43:11
And this is how we work out our critical
past.
43:14
We take a look at all of those activities
with zero slack or float in them.
43:18
So that's activity a.
43:22
See? A.
43:27
If. And H.
43:31
And that is our critical path through this
network diagram, A,
C, E, F and H.
43:39
Of course, with a bigger network diagram with
a lot more activities, you would find
multiple critical paths.
43:45
But remember, they're always the same
duration and there's no slack or
float on any of the activities in there.
43:54
So if any of the activities a f or h are
delayed,
our total project duration will increase
beyond 25 days.
44:02
And that's why we pay attention to the
critical path.
44:06
Now, keep in mind throughout your project if
Activity D, for example, was
delayed by more than three days.
44:14
Then it would probably become on the
critical path.
44:17
So the critical path can shift during a
project as well.
44:23
So in summary, the developed schedule
process takes
together all of the schedule information
we've produced as a result of all of those
other schedule management or time management
planning processes.
44:38
The defined activities, the sequence
activities, the estimate, activity resources,
the estimate, activity durations and also
takes information from other knowledge
areas in the PMBOK guide, such as risk
management, human resources puts
them all together to produce a project
schedule.
44:56
And with that, we can identify a project
duration and also the
critical path.
45:03
As I've already said in this module, please
pay particular attention to the
development of the critical path and
completing your own forward pass and backward
paths. There are always questions in the
exam which require you to be
able to do that in summary.
45:19
Thank you very much for listening.
45:21
This has been a module on the develop
schedule process in the PMBOK
guide.