00:01
Hello and welcome.
00:03
This module covers the determined budget
process from the PMBOK
guide. The exam importance is very high
because
the project budget becomes our cost baseline
for the project and usually
our stakeholders always want that question
answered.
00:20
How well are you doing in terms of cost?
The difficulty is rated as medium because
most project managers do cost
management and budget management very well.
00:31
And the memorization is generally pretty low
because you've seen most of these concepts
before, not too much new to come.
00:41
The determined budget process is one of four
processes in the
project cost management knowledge area.
00:49
It's the third Planning process after plan
cost management, which gives
us our cost management plan.
00:57
And provides the the cost management plan
provides advice on how we estimate our costs.
01:04
The determined budget actually combines
outputs from the
estimate cost process and also the developed
schedule process
from project time management to give us our
project budget.
01:18
And of course, once we have our project
budget, we can then control costs by
using that as a baseline and comparing
actual cost performance to what
we think should happen on the project.
01:31
The particular domain task that this process
helps us understand better
is Planning Task 2, which says develop the
cost management plan
based on the project scope, schedule
resources, approve
project charter and other information using
estimating
techniques in order to manage project costs.
01:54
And in fact, this single domain task covers
all three
of the cost management planning processes.
02:05
The key theme of this process is to take the
individual
cost estimates and also the project schedule
combined
them and develop the project budget.
02:20
The potential inputs that we could use,
first and foremost,
obviously will want our cost management
plan.
02:29
It's our guide.
02:31
It shows us how we're going to develop our
budget, what tools and techniques we are
going to use, what software we are going to
use, the level of certainty that's
acceptable. The metrics will use it's all
there in our cost
management plan.
02:46
So we will want that.
02:49
We'll also want our scope baseline and
remember the scope baseline
contains those three elements the scope
statement, the work breakdown
structure and the work breakdown structure
dictionary.
03:03
We'll want individual cost estimates and the
associated
documentation, the basis of estimates, both
outputs from the estimate
cost process.
03:17
Well, also want, and most importantly, need
the project schedule
for without it.
03:22
We cannot turn our cost estimates into a
project budget
because the project budget is simply costs
over time.
03:31
So we need the time component and the
project schedule is an output
of the developed schedule process from the
Project Time Management
Knowledge Area. We may also want our
resource calendars
because our resource calendars give us
constraints about when resources are
available and when the costs will be
incurred.
03:55
One other input that we may want are
agreements that we've signed,
contracts that we've signed, particularly
because these
agreements or contracts may be very clear
about when costs will be
incurred and when payments will be made.
04:13
Obviously, when we begin to budget for when
costs will go out of our
organization and when we'll get costs coming
in, some contracts specify
monthly payments.
04:24
Others specify milestone payments.
04:26
Others specify money upfront or money
withheld at the end.
04:31
We need all of these factors in order to do
an accurate project
budget. So go looking for any agreements and
read them very
carefully in relation to when the money's
coming in and when the money's
going out. The final input that we will find
useful will
be organizational process assets, and these
will be parts of our project management
methodology that relates specifically to the
development of the budget.
04:59
They may define the format we use, the
accuracy of the content or even the
software we have to use.
05:07
So once we have those inputs, we can select
from the following tools and techniques
those that are most useful to us and most
appropriate.
05:16
The first being cost aggregation.
05:20
Now, call segregation in this sense means
taking the costs and
aggregating them in each time period in
which they are
incurred. So you may aggregate your costs
weekly or
monthly or quarterly.
05:38
So we're not adding them up on an activity
basis when they're aggregating and adding
them up on a time basis, and we've got an
example coming up in a moment to show you.
05:49
We may also choose to use reserves analysis
in order to try
and build up either a contingency reserve or
a management reserve.
05:59
Now, a contingency reserve is a specific
sum allocated to identified uncertainty on
your
project. It can be built up in many ways,
ranging from
historical information that you generally
under.
06:16
Estimate your budgets through to actual
individual analysis of
uncertainty relating to the rate of
inflation on all of the materials that you
plan to procure and add all of those up, and
then they become your contingency
reserve. You can also use quantitative risk
analysis to build
up a quantitative risk contingency reserve.
06:39
There's many ways to build up a contingency
reserve, but what they all have in
common is they're all used legitimate,
transparent,
defensible techniques for developing a
contingency reserve as
opposed to padding of an estimate.
06:55
Now, padding is considered to be unethical,
and you should never pad an
estimate. Padding means simply making up a
number, pulling a number out
of thin air with no justification behind it.
07:09
Developing a contingency reserve properly
means having the ability to justify it.
07:13
Now don't forget with any contingency
reserve, if that contingency reserve isn't
used, it's returned back to the
organization, not kept to the side to use for
future and identified uncertainty.
07:25
Remember that point for the exam as well that
may be different from your current
experience. The other type of reserve that
we may choose to build up is a
management reserve.
07:36
Now, the contingency reserve is always under
the control of the project manager
and approved as part of the project budget.
07:43
The management reserve, however, is not, as
the name implies, the
management reserve is under the control of
management.
07:52
A lot of organizations have as a particular
percentage of their total capital
spin, say, five per cent or 10 per cent, as
allocated as management
reserve. And the purpose of management
reserve is if a project
encounters unknown, unknown unknowns or
unforeseen
uncertainty, it can apply to management to
use that reserve
to help it out financially.
08:17
So for the purposes of the exam, make sure
you understand the difference between
contingency reserve and management reserve.
08:26
Another tool or technique we may choose to
use is the expert judgment.
08:32
Obviously, when putting together a budget,
the types of experts you may wish to consult
well, you for a start or as project manager.
08:40
Your project team members, members of your
organization's finance and
accounting team may want to help you as
well, as well as external
consultants specializing and cost estimating
and data preparation
professions such as quantity surveyors, for
example.
08:58
Another total technique that you may find
useful is historical
relationships. And this is a way for you to
benchmark your
current budget forecasts against recently
completed
projects. Just by checking what their spend
profile was,
when did they spend most money?
When did they spend the least money?
What was the shape of their budget?
How easy was it for them to get the money
coming in?
What problems did they had paying money out?
So look at your historical relationships
with budget to help improve your own
current budget.
09:34
Now, the final total technique, its funding
limit reconciliation.
09:39
This is something you may need to take into
account and determine in your budget.
09:44
Your organization may have some limits on
when it has the funding available to
it, and it's certainly not uncommon for an
organization to
say for this calendar year or this financial
year, we only
have $1 million available.
10:01
Yes, we want to do your project, but we
simply can't afford it this year.
10:06
And therefore, due to funding limit
reconciliations, your project may
be put off until the following year.
10:13
The other way to look at funding limit
reconciliations, particularly for government
departments who often operate on a use it or
lose it basis as
as you near the end of that financial year
and you've got funds that you haven't
spent yet, your push to spend those very
quickly.
10:31
Otherwise, you may lose them.
10:33
So take into account the funding limit
reconciliation issues when putting together
your project budget.
10:42
Let's take a closer look at some of those
tools and techniques, as I've already
mentioned, the contingency reserve is part
of the approved project budget under
the control of the project manager and is
for known unknowns.
10:56
The key point for the exam is if that
uncertainty doesn't eventuate,
then you don't keep the contingency reserve
for something that may or may not happen in
the future. You return it to the
organization.
11:08
This may be different from your current
experience.
11:11
The other type of reserve is the management
reserve, which is under the control of
management, and a project manager can apply
to use it if they
encounter unknown unknowns.
11:23
So for the exam, make sure you understand
the difference between contingency reserves
and management reserves.
11:31
Once you've done all of these things, you
will produce your cost baseline.
11:37
This is your project budget.
11:40
It's the baseline by which you're going to
measure cost and financial performance on
your project going forward.
11:46
It's also one of three common baselines used
in the profession of project management.
11:51
The other two being the scope baseline and
the time or
schedule baseline.
11:59
You'll also have your project funding
requirements.
12:02
This is particularly important where you
have to take specific consideration of
how your project will be funded.
12:10
Some projects have to be funded through
external sources, credit
facilities, bank overdrafts, loans.
12:18
Call on shareholders funds and each of these
comes with a
cost. And it may be that you need to take
into account
the cost of project funding.
12:31
And as we've already discussed with the
funding limit reconciliation technique,
you want to look at the timing of your
project funding as well.
12:41
Another output that you may choose to update
is your project documents.
12:46
These are just anything as part of your
commitment to continuous improvement.
12:49
Any part of your methodology relating to the
development of the project budget.
12:55
So let's take a closer look at the
difference between costs and budget.
13:00
Using these diagrams.
13:03
Now, this is a simple spreadsheet showing
individual cost
estimates for defined activities.
13:10
So over on the left hand side, we have
developed code code testing,
site acceptance, testing, installation at
client site commissioning
and hand over.
13:22
And we have cost estimates for each of
those.
13:25
You can see our cost estimates for
developing the code is a total
of $21,500 spread out
over January $5000.
13:37
February $7,500 and March
$9000. You can also see our cost estimates
there
for code testing, site acceptance testing,
installation at client site
commissioning and handover handover has a
total cost estimate of
$5,750 planned to be incurred in September.
14:00
So those are individual cost estimates and
through the process of aggregation,
we can put cumulative totals into January,
February, March,
April, May, June, July, August and
September.
14:15
And then we add those up to get a running
cumulative total so that we can see over our
project. We start by spending $5000 in
January.
14:24
We spend an additional $7,500 in February to
give us a total spend
of $12,500 and so on and so on.
14:33
So those figures up there, our individual
cost estimates, when we put them into this
diagram, what we get is our project budget
and that's
that line which shows our planned spend on
the project.
14:47
Now, interestingly enough, that point at the
end is our
budget at completion.
14:55
This is particularly important to know when
we come to the earned value management
technique and the control costs module.
15:04
Because we need to know that budget at
completion in order to calculate our own
value management calculations.
15:11
So there we are.
15:12
That's the difference between costs and
budget.
15:18
So in summary.
15:22
We've looked at the use of the cost
management plan, individual cost
estimates and the project's schedule to
produce an agreed and approved project
budget in the developed budget process.
15:37
Thank you. This has been an introduction and
overview of the develop budget
process in the PMBOK guide.