00:01
This module covers the defined activities
process in the PMBOK guide.
00:07
It's really important that you pay attention
to this because it's the first of the
activities we do in order to produce the
project schedule, and that's why we give it
such a high exam importance.
00:18
The difficulty is rated as medium because
you may not have done this before.
00:23
Memorization is low, though, because none of
the concepts should be completely new to you.
00:29
So the define activities process is part of
the project time management knowledge area.
00:34
In fact, it's the second of six Planning
activities.
00:38
But after the production of the schedule
management plan by the plan schedule
management process, it is in fact the first
of the activities that we go through in order
to end up producing our project schedule.
00:51
So if you follow those processes through, we
see that first, we define the activities and
produce an activity list.
00:57
We then we take those activities and we put
them in the sequence in which they occur
and indicate the relationships and
dependencies between them with a network
diagram. We can then go off to usually first
estimate activity
resources and then with that information,
estimate the activity durations.
01:15
And with all of this information combined,
we can then develop the schedule.
01:20
So the defined activities is the necessary
first step in that process
of producing a project schedule.
01:28
Of course, once we have our project
schedule, we can then control the schedule
and look at what we think we should be doing
against what we're actually doing and look
for variants. So the particular domain
task that the defined activities process
helps us understand better
is the planning task for which says develop
the project schedule
based on the approved project deliverables
and milestones, scope and resource management
plans in order to manage timely completion
of the project.
02:00
And of course, the single domain task
actually covers all six
of those project time management processes.
02:10
So in summary, the key themes of define
activities
process includes take our project scope,
particularly
the WBS, and break it down from work package
level down further
down to activity level.
02:26
And once we've done that, we produce an
activity list for our project.
02:33
So we start with potential inputs that we
may find useful.
02:37
The first one is, of course, the project
management plan, particularly the
schedule management plan, as part of it,
because it's the schedule management plan,
which tells us how we're going to do this
activity.
02:50
The next most important input will, of
course, be the scope baseline.
02:54
Now remember, the scope baseline is made up
of three elements the
scope statement, the WBS work breakdown
structure and the WBS
dictionary. The one that we're particularly
interested there as an input is, of course,
the work breakdown structure.
03:11
Remember, the work breakdown structure has
used decomposition to break
down our project scope from deliverable to
sub deliverable to work package level, and
that's where it stopped.
03:22
We're going to go one step further and break
them down to activity level to get our
activity list.
03:29
We may also find enterprise environmental
factors and organizational process
assets useful to us in developing our
activity list.
03:39
The particular tools and techniques that we
may find useful include
decomposition. Now we saw decomposition used
as the primary
tool and the creation of the work breakdown
structure.
03:52
And when we used it there for the creation
of the work breakdown structure, we took our
project scope statement and we use
decomposition to break it down from
deliverable to sub deliverable to work
package level and remember for the purpose of
the WBS. That's where we stopped at work
package level.
04:10
For the purposes of producing our project
schedule, though, we want an activity list,
so we take it one step further and produce
our activities.
04:19
We decompose that one step further down to
activity level.
04:23
The difference between work, package and
activity can be a somewhat arbitrary
distinction. Often, a work package is
described and defined as
a level of work that can be reliably
estimated for cost, a level of work that can
be reliably estimated for time.
04:39
A level of work where the benefits of
decomposing it even
further don't outweigh the costs of doing
it.
04:47
And some people will also say that a work
package is the level at which can be assigned
to a single person.
04:54
Regardless of your definition of the work
package, though, the activity is listed as
below that. So defining an activity means
coming down to those exact
hourly things that need to be done half day,
things that need to be done.
05:08
Those are activities, not work package.
05:11
The other tool that we need to be aware of
is rolling wave Planning.
05:16
Now, rolling wave Planning is a critical
part of the profession of project management,
and what it tells us is that as we proceed
through a project, particularly a long
term project, we may choose to plan in
detail.
05:29
That time period, immediately in front of
us, perhaps we're on a 12 month
project, and what we will do is plan in
detail, perhaps the
month or two directly in front of us,
perhaps from two to six months.
05:43
We don't plan in as much detail and for six
to 12 months out, our
detail is even less.
05:50
But as we move through the project, we keep
re-planning it.
05:55
That's what rolling wave Planning is.
05:57
It's a form of progressive elaboration.
06:00
The third total technique that we may find
useful is, of course, the most popular total
technique in the PMBOK guide, and that's
expert judgment.
06:08
So remember you're an expert.
06:10
Your project team members are experts and
other people that you choose to consult or
experts. And as a general rule, always
involved the people doing the work
and defining the work.
06:21
So here we're trying to define the
activities, so we should always go and
talk with those people who are going to do
those activities and they will have the best
information to help us define them.
06:34
The outputs that we may generate as a result
of defining our activities
are our activity list.
06:42
And this is exactly what it says it is.
06:44
It is a list of all the activities on our
project.
06:48
Obviously, we'll give each one a number as
part of our configuration management system.
06:53
But there it is, the single list.
06:55
Now, it's not a project schedule at this
point.
06:58
It doesn't have dependencies and
relationships.
07:01
It doesn't have durations attached to it,
and it's not presented in a network diagram
or Gantt-Chart format.
07:07
All it is is a list of all the activities
that we're going to use.
07:12
This activity list is an output from this
process will go on to be used as an
input into some of the other time management
planning processes.
07:22
In addition to the activity list, we may
also choose to produce activity
attributes. Now, throughout the PMBOK guide,
there's often
what I call a primary document and a
secondary document.
07:35
We saw this already with a WBS and the WBS
dictionary.
07:40
Here we see it again with the activity list
and the activity attributes, the
activity list itself can be seen only.
07:47
Summary Information about each of the
activities by the activity
attributes can tell us more information
about each of the activities.
07:55
How did we arrive at that activity?
What do we know about that activity?
What constraints may be upon that activity?
So we may also choose to produce an activity
attributes
document to complement our activity list and
give us more information
as a result of producing our activities,
though, we may also produce a milestone
list. It may become apparent at this point
that certain milestones
need to be hit, and we produce that
milestone list, which said we've got to hit
this milestone at this point.
08:27
The next milestone at that point and the
milestones themselves can become
activities. Remember, though, when we come
to assigning duration to a milestone,
a milestone has zero duration.
08:39
That's very important when we come to doing
our project schedule.
08:42
So now what we have after doing the defined
activities process is our
activity list, our activity attributes and
our milestone list.
08:51
Each of these outputs will go on to be
inputs into other time management
planning areas as we iteratively do the work
to build up our
approved project schedule.
09:04
So remember, the activity list is an output
as a list of all the activities that we're
going to do on the project.
09:11
Remember, it's subject to progressive
elaboration.
09:13
We may not know all of them over the whole
project, but instead breakdown those in the
immediate future.
09:19
The activities attributes a more detailed
description of the activities, and that
milestones list identifies all of the
important milestones as a separate and
distinct list, and some of them may have
come from our project charter.
09:34
So in summary, the defined activities
process and the PMBOK guide
focuses on the development of the activity
list as the first step
in the sequential production of the eventual
project schedule.
09:48
This has been an introduction and an
overview to the defined activities process in
the Pim Bot guide.