00:01
This module looks at the create WBS process
from the PMBOK guide.
00:08
It's extremely important that you pay
particular attention to the WBS or work
breakdown structure.
00:14
It's often regarded as the absolute backbone
of project management
because without it, we can't do good time
and cost estimates.
00:23
And that's why there's such a high ranking
with exam importance in terms of difficulty.
00:27
There's a medium level of difficulty because
there are some things we're going to
introduce you to which you may not currently
do or even be aware are capable of doing
in the profession of project management.
00:38
And the same applies for memorization.
00:41
There are some new concepts we're going to
introduce you to here as well.
00:44
But do please pay particular attention to
the creation of the WBS and
understanding the importance of the WBS in
project management and also
for the exam?
The Create WBS process is part of the
project scope management knowledge
area, and it is the final of four planning
processes in this
particular knowledge area.
01:09
The first planning process plan, Scope
Management, gave us our Scope Management
Plan, which provides guidance on all the
rest of our scope management activities.
01:18
The Click Requirements Process gave us our
requirements, documentation and our
requirements traceability matrix.
01:25
We then used that information to define both
our project and product
scope with a defined scope process.
01:33
So the creation of the WBS is really the
culmination of those planning
processes. There are also two monitoring and
control processes in the
scope management knowledge area, and they
are the validate scope process and the
control scope process.
01:49
The domain task that the create WBS process
helps you to understand better is
Planning Task 2, which is develop a scope
management plan based on the
approved project scope and using scope
management techniques in order to define,
maintain and manage the scope of the
project.
02:06
So it's a fairly big task.
02:09
The single task takes us through those four
planning processes in the
scope management knowledge area.
02:15
This task takes us through the plan scope
management, the click requirements,
defined scope and create WBS processes all
in this one domain
task. The key themes of the create
WBS process are.
02:33
What we're going to do now is we're going to
take our project scope statement and we're
going to break it down to work package level
with a process of decomposition.
02:42
With that, we're going to create our work
breakdown structure or WBS.
02:48
And The WBS is seen as the backbone for
project management because it's absolutely
essential to have one.
02:54
Without it, we can't do accurate estimating
of cost and time and the people or
resources we need on the project.
03:01
Remember that because the work breakdown
structure is a graphical representation
of the project scope.
03:08
If it's not in the WBS, it's not part of the
project.
03:14
The scope baseline is the scope statement,
plus the
WBS plus the WBS dictionary, all three of
those
components joined to give us our scope
baseline, and with that scope baseline,
we can then measure what is actually going
on and see if there's a variance between what
we expect to go on with the scope baseline
and what is actually going on.
03:37
So remember, the WBS is critical to project
success.
03:41
In fact, so critical if you get a question
in the exam, which presents a
scenario which indicates you do not have a
WBS and ask
you what you should do next.
03:53
The correct answer is stop and complete a
WBS before
proceeding. The inputs
that you may find useful in the creation of
your work breakdown structure or
WBS include.
04:09
The scope management plan.
04:12
This is the plan that provides the guidance
on all of our scope management activities,
including the creation of the WBS, so
obviously we will want to refer to
that in the development of our WBS.
04:25
The project scope statement is an essential
input here, because the WBS is a
graphical representation of our project
scope statement.
04:33
So we need it.
04:35
Now keep in mind that the creation of our WB
is can be an iterative process as well,
reflecting the iterative development of the
project scope statement.
04:44
We may also want our requirements
documentation to double check that our
WBS captures all of the agreed requirements
for the project.
04:55
Other useful inputs include relevant and
appropriate enterprise, environmental
factors and organizational processes such as
our project management
methodology and blank WBS templates.
05:11
With these inputs, we can apply the following
tools and techniques to end up
producing our work breakdown structure.
05:18
The most important tool technique that we
can use is simply decomposition, and
this is simply the process of taking a total
project scope and breaking
it down into its component parts.
05:31
And what we are going to do with the process
of decomposition is take our entire project
scope. Break it down into deliverables, sub
deliverables and then down into work
package level. And that's where we'll stop
for the purposes of the work breakdown
structure. The other tool and technique we
can use as expert judgment,
obviously as a project manager, you are an
expert in the creation of WBS Your
Project. Team members who will do the work
in the WBS should also be consulted as
experts on the WBS.
06:01
So let's take a close look at some of these
elements decomposition.
06:06
Decomposition is a technique that involves
breaking down elements of the project scope
statement into their component parts for the
WBS.
06:15
We only go as low as the work package level.
06:19
When we come to look at our project
schedule, we can go lower to activity level.
06:25
So for the WBS will start at deliverable
level, then come down to sub deliverable
level, then down to work package level and
once again when we come to
develop, the project schedule will go lower
than that down to activity level.
06:38
But right now, for the creation of the WBS
work, package level is as low as we go.
06:46
Here's an example of a work breakdown
structure.
06:49
Here at the top level, we've got the new
house, we've given it a number
1.0. We come down to the deliverable levels,
the sub deliverable
levels and finally down to work package
levels.
07:03
Below this, we would find activity levels
down there.
07:07
Now, just to note, when preparing a work
breakdown structure, each of those nodes,
that's those boxes with brief informationen,
it also has a number assigned to
it. We'll talk more about this shortly in
terms of the configuration management system,
but each one of those numbers can link back
to our cost accounting system so that we
can accurately see where we're spending our
money on the project.
07:33
Defining the work package can be a bit of a
mystery.
07:37
But here's some easy tips to help you
determine whether it's a work package, a
deliverable or an activity.
07:43
First up, a work package cannot easily be
decomposed any further.
07:48
Decomposing at any further takes a lot more
effort than it's worth.
07:52
But it's small enough to be reliably
estimated for time and small
enough to be reliably estimated for cost.
08:00
Often it can also be assigned to a single
person to complete the work.
08:06
So while there is no absolutely clear
definition of the work package, these should
give you some guidance.
08:12
Remember, below the work package is the
activity level and will need those activities
to produce a great project schedule in a
later module.
08:22
The outputs from the create WBS process are
our scope
baseline. Now the baseline is absolutely
essential.
08:31
It's one of three baselines in project
management, the other two being
cost and time and occasionally people out of
third in there the quality
management one. But the scope baseline is
our forecast of what we
expect to happen with our project scope.
08:48
And obviously when we come to monitoring and
controlling our project scope will want to
know what we thought was going to happen so
we can compare it against what is actually
happening. And that's the importance of our
scope baseline.
09:00
Now the scope baseline is made up of three
distinct and separate elements.
09:04
They are our scope statement, our work
breakdown, structure and work breakdown
structure dictionary.
09:11
The other outputs that we may have a project
document updates.
09:15
As a result of creating our WBS, we may wish
to update other
assets that we have things like our WBS
template or our processes
that guide us on how we prepare our WBS.
09:30
So let's take a closer look at work
breakdown structures.
09:34
First up, remember they are based on project
deliverables.
09:38
They are built from the top down.
09:40
We use the tool and technique of
decomposition to prepare them.
09:45
They are the total representation of the
project scope.
09:48
The team doing the work should always help
put the WBS together.
09:53
And remember, most importantly, no work
breakdown structure means no
project. So if you get a question in the
exam, which indicates that you're completing
a project without a WBS, well, the answer is
stop the project and complete the
WBS. The thing about the exam is often
they'll paint scenarios
of certain things that you don't have.
10:14
Maybe you don't have a risk register or a
communications plan or quality assurance
plan. The answer in those instances is often
will keep going with the
project and develop one of those things as
fast as you can.
10:28
When it comes to the WBS, though, the answer
is always stop the project and prepare a
WBS. The other element of project
management, where you would also stop a
project if it didn't exist is, of course,
the project charter.
10:41
So you can see the WBS is just as important
as the Project Charter in ensuring
that you have a successful project.
10:49
Here's some other examples of WBS you can
break a WBS is down in numerous
ways. So here's a very generic example,
which breaks a project down into
phases. It also breaks it down into
deliverables, also
subprojects as well.
11:04
So there's many ways to graphically show how
your WBS is breaks down the
scope of your project.
11:10
Once again, you can see each of the nodes
has a unique identifying number
as part of our configuration management
system, and each of those numbers would
ideally link back to our cost accounting
system.
11:24
Here's another example of a work breakdown
structure, this time for a generic
aircraft system..
11:30
Here we've broken down all the deliverables
and sub-deliverables down to work package
level, and once again they've each got an
identifying number on the node.
11:40
This is where we often see the WB is
represented, though not many of
us would ever see the WBS represented
graphically as that breakdown
structure. We usually tend to see the WBS is
represented in
the left hand side of a chart like this, a
typical Gantt-Chart.
11:59
And there you can see the indents of each of
the elements of the WBS is
representing the success of the levels.
12:07
Now, out of curiosity, the work breakdown
structure is one of four
breakdown structures in the PMBOK guide.
12:15
Remember, the WBS work breakdown structure.
12:18
The other three are the resource breakdown
structure, the risk
breakdown structure and the organizational
breakdown structure.
12:27
And what they all have in common is they all
take a higher level concept and break it down
into its component parts.
12:34
Now, I've mentioned a couple of times the
configuration management system here in The
WB, yes, it's represented by each of the
numbers on the nodes in the
WBS, and it's a unique number given to it.
12:47
This is part of our overall configuration
management system, which actually takes many
forms. But what it does do is enable us to
track and
surveil different parts of our project.
13:00
Other examples of our configuration
management system include version
and status control on documents.
13:07
For example, this is a draft document.
13:09
This one's confidential.
13:11
This one's for construction.
13:13
Version control on software, are you using
version 1.0 or version one point
two? The numbering of parts were materials
needed for
your project to make sure you're using the
right part at the right time.
13:27
Another example is giving each change
request on your change.
13:30
Register a unique number so you can track
it.
13:34
So those are the elements of your
configuration management system.
13:38
The other element that we want, apart from
our work breakdown structure as our work
breakdown structure dictionary.
13:46
The work breakdown structure dictionary is a
document that provides more detail about
each of the nodes on the WBS, as we've
already seen by the
examples of the WBS I've given you, we can
put onto each node a
unique identifier number as part of our
configuration management system, and we can
put a brief description of the work to be
done.
14:08
The WBS Dictionary provides additional
information about each of those
nodes on our WBS.
14:16
So, for example, we may have a node on our
WBS that looks similar to
this. Here we have a node rather typical
node, and
you can see that it has some summary
information about this particular plumbing
task. We can see it's got its unique
identifier one point three point two
point one, and it relates to putting
plumbing into a house.
14:37
We can also see a summary of the cost, the
duration and the amount of
people needed to do the work.
14:45
That's what we would say on a normal WBS
node.
14:48
However, the WBS dictionary provides a whole
lot more information,
and here you could see if we did have a WBS
dictionary, it would refer to this node like
this. 1.3.2.1 is the plumbing work, and this
work
includes all of the internal work to provide
water plumbing throughout the house.
15:06
And it excludes remember in our scope, we've
got to put what we're not going to do as
well. It excludes any work related to
provision of gas reticulation.
15:15
It also excludes any work related to the
provision of external irrigation.
15:20
The cost for the work is estimated at
thirteen point five thousand dollars, based
upon the contract provided on the 13th of
January 2014.
15:28
The estimate was completed using parametric
estimating expert judgment and published
estimating data and is valid for three
months.
15:36
The work is forecast to take six days to
complete, and it is assumed that the work
will be completed without interruptions and
that two plumbers will be available the whole
time so you can see there the simple node of
the WBS provides summary
information. The WBS dictionary provides a
whole lot more detailed
information. So the scope baseline are
those three things together, our scope
baseline is our agreed and
approved scope statement that includes what
we are going to do and also what we're
not going to do.
16:09
Add to that our work breakdown structure and
add to that our work breakdown
structure dictionary.
16:15
Those three elements make up our project
scope baseline.
16:20
And once again, remember we need the scope
baseline so that when we come to
check if we're providing the scope we agreed
to, we compare what we're
actually doing to what our baseline says we
think we should be doing.
16:34
And once again, if there's variance between
those two, we act to make sure that there's
not. So in summary, the create
WBS or work breakdown structure process, it
takes the project
scope statement and breaks it down into its
component parts from deliverable to
sub deliverable to work package level using
the decomposition tool.
16:59
We use the WBS to represent all the
deliverables, sub deliverables and work
packages on our project.
17:05
And remember, the scope baseline is our
scope statement and The WBS
and The WBS is dictionary.
17:12
Perhaps most importantly, do remember you
must have a WBS for your
project. No, WBS means no project.
17:21
This has been an overview of the create WBS
process from the PMBOK guide.