00:02
Hello and welcome.
00:03
This module will cover the control costs
process of the PMBOK
guide. It's particularly important that you
pay very close
attention to this module.
00:14
There will definitely be multiple questions
in the exam about the content of this
module, and that's why it's rated so highly
with exam importance,
difficulty and memorization, particularly
the areas of the
module relating to earn value management,
where you're going to have to
remember up to 20 different formula and take
them all into that
exam with you.
00:39
Remember practice your brain dump practice
writing
down those mnemonics and the formula that
you need to know, including
all of these formula.
00:52
The control costs process is one of four
processes
in the project cost management knowledge
area.
01:00
It's the only monitoring and controlling
process, though the other
three processes are planning processes and
they are the planned cost
management process which produces our cost
management plan, which of course
will need to control cost.
01:17
And the other two planning processes are the
estimated cost process,
which gives us activity, cost estimates and
our budget.
01:27
The determined budget process, which
combines our individual activity
cost estimates with our project schedule to
give us the cost,
baseline or budget.
01:41
The particular domain task that the control
cost process helps
us understand better is the monitoring and
controlling task one
which says measure project performance using
appropriate tools
and techniques in order to identify and
quantify
any variances and corrective actions.
02:07
The key themes of the control costs process
are that we are
going to take the cost management plan and
appropriate and
specific tools, such as the earned value
management technique to determine if the
project is performing on budget.
02:23
Are we ahead of budget?
Are we behind budget, but then using this
information?
Forecasting possible or likely future cost
performance.
02:38
The particular inputs that we will find
useful are our
project management plan, particularly our
cost management plan,
because that provides guidance on how we're
going to look at cost
performance on our project.
02:55
We may also want to look at our change
management plan and of course, the
other aspects of the project management plan
that we will want are the baselines.
03:05
Yes, we will want the scope baseline.
03:07
Remember, that's the scope statement, the
work breakdown structure and the work
breakdown structure dictionary.
03:13
Well, want our schedule baseline or our
project schedule, but the one that we'll
really want is our cost baseline or budget.
03:22
We'll also want our project funding
requirements.
03:27
This is an output of developed budget.
03:33
This tells us when we need the money and the
timing of the funds coming in.
03:39
We'll also want some raw work performance
data about how we're
performing in relation to cost.
03:47
Now, one of the key elements of any
controlling process is that the
inputs always include a description of the
work that we plan to do
and some information about the work that's
actually going on here.
04:02
You can see that the first two inputs the
project management plan and the project
funding requirements are a description of
the work we plan to do on the
project. The work performance data is a
description of
the work that's actually performing on the
project.
04:20
The tools and techniques will come to
shortly, always have ways to detect variance
between those two.
04:25
And of course, if we find variance between
those two, we must act.
04:29
That's the essence of the plan.
04:31
Do check cycle.
04:34
The final input that we may find useful are
organizational
processes, parts of our project management
methodology dedicated
to controlling costs.
04:48
The particular tools and techniques that we
can use, if appropriate to control
our costs include the earned value
management technique,
and we're going to spend quite a bit of time
in this module going into this in depth and
all the associated formula.
05:06
But in essence, what it does is it takes a
snapshot of
historical information, and using these
formula turns it into useful work
performance information that can comment on
not just cost
performance, but also scheduled performance
as well.
05:24
We can then use these metrics to do some
forecasting and
extrapolate from historical performance what
a likely or possible future
performance will be.
05:36
So, for example, we'll be able to get a
forecast estimate at
completion. We can also use the to complete
performance
index. Which is a metric that tells us how
fast
we need to work to either hit our original
budget at completion
or our new estimate at completion.
05:59
Of course, as part of controlling costs will
carry out performance reviews,
particularly those about our cost
performance, are we
experiencing variances?
Did we routinely underestimate or
overestimate what are the trends we're
observing? These are all aspects of
performance reviews relating to cost.
06:21
We'll find it easier to do this if we use
appropriate project management
software, which of course, is no point
trying to do this with pen and paper.
06:31
We'll use project management software,
everything from a plain old
spreadsheet right up to dedicated project
management software right
up to a full ERP systems that run entire
organizations.
06:46
And that part of doing this as well, we may
choose, if appropriate,
to carry out reserves analysis.
06:54
Now we've already allocated reserves to our
project when we
determined the budget and estimated the
costs.
07:03
We allocated contingency reserves, and we
may have even set up a
process for accessing management reserves as
necessary during the
control cost process.
07:14
We're going to reexamine those decisions and
see if that's still
accurate. Do we need more contingency
reserve because of increased
uncertainty? Or should we be giving some of
that continued reserve up and back to
the organization for other projects to use?
Do we need to make a case for accessing
management reserve with the
permission of management because of
unexpected uncertainty in the project?
These are all part of reserves analysis at
this point and the project.
07:49
Let's go through the value management
technique now, pay particular
attention because there will be several
questions in the
exam about this.
08:00
And before we get onto the formula, it's a
good idea to start by
explaining what it is in terms of a graph.
08:09
Here's some real data from a project I did
many years ago.
08:14
Now, the Dark Green Line, that's our
approved project budget, and
that's normally the only line that a lot of
project managers ever deal with.
08:24
Any point on that line is our planned value
or PV,
the value of work we plan to have created at
this point in time in the
project. Now, the total PV, that point right
at
the end of that line is our budget at
completion.
08:43
Our BAC, our original approved project
budget.
08:48
Now, the other line that a lot of project
managers do track is the red line.
08:53
That's our actual cost spent to date.
08:56
And as you can see, for most of the project,
our actual costs tracked
below our planned value and at the end of
the project, our
actual costs are below our total PV, which
is our budget at
completion. But the one that most project
managers
don't track is that light green line, the
earned value,
it's a hard one to track and takes a bit of
extra effort.
09:25
But that is actually the value of work we've
created at any point in a
project, not what we had planned to do, but
the work that we created at any
point in the project.
09:36
And that's absolutely necessary to us for
without it.
09:40
You could have the following scenario a
project manager comes up to you.
09:45
Maybe you're the project sponsor or the
client and they say to you, I'm here to tell
you good news about the project with 50 per
cent of the way through the
project, and we've only spent 20 per cent of
the budget.
09:57
It's all going good.
09:59
Of course, what they haven't told you is how
much work they've done.
10:03
Maybe they've only done 10 per cent of the
planned work, in which case the projects in a
lot of trouble. So that's the missing part
of the equation.
10:12
The earned value.
10:14
So we're going to need all three of these
and the budget at completion
in order to do our earn value management
calculations in the
exam. Often the hardest part is not applying
the
equations that you've learnt, but getting
those four numbers out of the
scenario successfully.
10:35
So practice extracting budget at completion,
planned
value, earned value and actual cost from the
scenario you're
presented with. Let's start with the first
of the
formulas. Cost variance.
10:53
Cost variance is the difference between what
you've done should have cost you
and what it actually costs you, and the
formula is cost variance
CV equals earn value minus actual
cost. So let's take a look at a simple
example.
11:11
We have got a more complex example coming up
at the end of this, but according
to your project plan, you should spend $18
to make three widgets.
11:21
You've produced three widgets, but you've
spent $20.
11:26
Your earned value was $18.
11:29
Your actual cost was $20.
11:32
Therefore, your cost variance is negative
$2.
11:36
Now, a negative cost variance is bad.
11:40
We don't want that a positive variance is
good.
11:46
The next formula is not in relation to cost,
but it's in relation to
time. So remember that even though this
process is called the
control costs, the earned value management
technique also gives us
information about time performance on the
project.
12:03
So SV equals schedule variance and the
formula is earned
value minus plan value.
12:10
And it's the difference between how much
you've accomplished and how much you had
planned to accomplish by now.
12:18
So, for example, according to your project
plan, at this
point in time and the project, you should
have produced five
widgets for a value of 30 dollars.
12:32
You've produced three widgets with a value
of $18.
12:36
So your planned value was $30 at this point
in time in the
project, but you've only produced three
widgets with a value of
$18. Now we don't know what it cost to
produce those widgets, by the way, but the
value given to each one was $6 each.
12:53
You produce three of them.
12:54
That's $18 of earned value.
12:56
Therefore, 18 minus 30 gives us a schedule
variance of
negative 12.
13:02
And once again, remember a negative number
is bad.
13:07
So for both cost variance and schedule
variance, a positive number is
positive. A negative number is negative.
13:17
Next, we're going to take those variances,
though, and turn them into something
useful. How relevant is a negative
$12 variance?
We don't know that.
13:31
Is it relevant to a $100 project, a thousand
dollar project, a million dollar
project turning those into indices helps us
understand the
magnitude of them.
13:42
The first one is SPI or our scheduled
performance index.
13:47
It's the ratio of how much you've
accomplished to how much you plan to
accomplish. And it's every divide by
PV. Remember, that schedule variance was EV
minus
PV if I is EV divide by
PV. So, for example, you've produced three
widgets
with $18.
14:12
You should have produced five widgets worth
$30.
14:15
Now, before using those same numbers, we
ended up with an SV of
Negative 12.
14:21
But this time we divide the two numbers, so
we get 18
divided by 30.
14:28
And this time we get an index of 0.6.
14:32
This means for every days, if it were
putting into this project, we're
getting 0.6 of a day's return.
14:40
Now that's definitely not good.
14:42
Obviously, for an index, one is perfect
means we're right on track
below. One is not good and above one is very
good.
14:51
So for example, if our SPI was 1.2, it would
mean
for every day we worked on this project, we
were getting 1.2 Days return.
15:04
Cost performance index or CPI?
It's the ratio of how much it should have
cost to how much it actually cost for a given
period of time.
15:12
And the formula CPI equals earn value
divided by actual
cost. Remember that cost variance equals
every
minus AC.
15:24
Same parameters this time divide EV divide
by AC.
15:30
So, for example, in September, you should
have made three widgets at a cost of
eighteen dollars. You spent 20 dollars to
make them your
cost. Performance index for September is
0.9.
15:43
This means for every dollar you're putting
into this project, you're getting 90 cents
return. Now, that's not good.
15:51
So once again, if the index is below one,
that's not good
above one, that's good.
16:00
Let's talk about CPI cumulative and non
cumulative forms of cost performance
index. You will encounter these in the exam
and it's important to know the
difference. The default position, by the
way, is CPI, with a little see
above it to represent cumulative CPI, and
that is your cost performance
index right from the beginning of the
project, not just for any given period of
time. So, for example, by now, you should
have made 10 widgets
at a cost of $30.
16:30
You've made 10, but it cost you $40.
16:33
So for your entire project, you'll CPI with a
little cumulative sine is
0.75, and we know that's not good for every
dollar being invested.
16:42
We're making 75 cents now.
16:45
Non cumulative CPI is useful when you've
experienced atypical
variations in price, for example
fluctuations that you do not expect to
see again. This is when we would use non
cumulative CPI,
which is calculated for a specific period of
time in the project that avoids the atypical
variance. So, for example, in the graph, we
can see that roughly a third of the way
through cost spending spiked.
17:12
It could have been to do with fuel price
increases, or maybe a spike in
inflation. Now, if we use CPI, cumulative
right from the beginning of the
project will take into account that atypical
variance.
17:25
So instead, we may wish to just calculate
CPI for the period after
that. Remember, though,
for cost performance index and schedule
performance index greater than one as great
below one, not so good.
17:44
Here's some other handy hints to help you
remember the formula we never earn value is
used in a formula at nearly always comes
first.
17:52
Remember if it's a variance, schedule
variance or cost variance, it's
EV minus something.
18:00
If it's an index, it is EV divide by
something
except for CPI, which will get onto in a
moment if the formula
relates to cost cost variance or cost
performance index use
actual cost.
18:17
If the formula relates to schedule, schedule
variance or should you Performance
Index use planned value or PV.
18:27
Let's take a look at some other formula now.
18:29
So now that we've used those group of
formula to take a snapshot of
both cost and time performance on our
project, it's time to use that
information to forecast likely future
scenarios.
18:43
And one of the ones that everybody wants to
know is, well, great.
18:47
You've told me how much it's cost you to
date on the project.
18:49
What do you now think this project is going
to cost at the end of it?
And for that, we use the estimate at
completion formula.
18:57
Now I've seen books that lists 16, 17, 18
different
formula for counting estimate completion for
the
purpose of the exam.
19:08
We're just going to give you four formula.
19:10
So try and remember each of them.
19:13
The first one to calculate our new estimate
at completion is to simply
take our original budget at completion and
apply our cost
performance to date to it, fairly simple.
19:26
So we take our budget at completion and
divide it by a cost performance.
19:31
And there you can see we can either use non
cumulative CPI
or cumulative CPI, depending on which one's
more appropriate for us to
use. So for example, if our project was to
create
300 widgets for nine hundred dollars and we
had a
CPI of 0.7 five.
19:53
So our budget at completion was nine
hundred, we divide that by 0.7
five. We now think our project is going to
cost
$1200. Not nine hundred dollars.
20:04
Twelve hundred dollars now.
20:09
Let's take a look at another formula.
20:11
This one simply says that our estimate at
completion equals our actual
cost, plus our estimate to complete.
20:21
This formula simply takes what we've spent
to date and adds to
it the remaining work to be done.
20:29
Now, some people, in order to calculate the
estimate to complete, will go back to
first principles, estimating and re estimate
the amount of work to be done
and simply add that to the actual cost spent
to date.
20:44
So, for example, your project was to create
three hundred
widgets for nine hundred dollars.
20:52
You've created one hundred widgets for four
hundred dollars and you
estimate it will cost another $700 to create
the next two hundred.
21:03
So our actual cost is four hundred dollars,
our estimate to complete
a $700.
21:11
Using this formula.
21:12
Our estimate to complete or estimate at
completion is
$1,100. Now this brings up an interesting
point.
21:21
We're going to show you four different
formula for estimate at completion.
21:25
I can guarantee you that if you use each of
the formula on the same
scenario, you will get four different
answers.
21:33
So in the exam, it should be pretty obvious
which one you should use.
21:39
Here's the formula number three for estimate
at completion.
21:42
In this instance, we take our actual cost
and we add to that
back minus EV, which if you think about it,
is
just another way of saying the value of
remaining work to be done at the project.
21:57
If we take BAC to represent our total planned
value was
simply subtracting from our total planned
value the value of work we've done already.
22:08
So this formula takes our actual cost and
adds to it the remaining
value of work to be done on the project.
22:16
So, for example, if your project was to
create 300 widgets for
nine hundred dollars and you've created 100
widgets with an actual cost
of four hundred dollars but an earned value
of only three hundred, meaning you still
have $600 dollars of value left to create
your estimate at
completion, using that formula will be
$1000.
22:42
The final formula is actually my favorite
formula, and it's the one that I routinely
use in my projects.
22:48
It's also the most complex because it takes
into account our actual
cost. The remaining value of work on the
project, but then also our cost
performance and our time performance to
date.
23:02
The three previous formulas didn't take into
account our time performance to
date, whereas this one does with the
inclusion of Spy.
23:13
So this formula estimate at completion
equals our actual
costs plus back minus EV divided
by our cost performance index times our
scheduled performance index.
23:27
So let's take a look at the example here.
23:31
If your project was to create 300 widgets for
nine hundred dollars, you've
created one hundred widgets with an actual
cost of four hundred dollars, but an
earned value of only $300, according to the
plan, you should have
created one hundred and fifty widgets by
now.
23:48
You still have $600 of value left to create.
23:52
But it will likely cost you $1200 to create
that value.
23:56
Put all those numbers into that formula, and
you have an estimate at completion of sixteen
hundred dollars.
24:04
Now we've shown you four formula for
estimate completion.
24:07
It is important that you take all of those
formula in.
24:11
We're fairly confident you're going to get a
question in the exam about estimate at
completion, but we can't tell you which
formula they're going to expect you to use.
24:19
So take all four of the men.
24:20
Better yet, if you can remember the logic
behind all of the formula, it will help you
to remember them. Otherwise, simply rote,
learn them.
24:28
Make sure, though, that they are part of
your brain dump at the beginning of the
exam. Some other formulas, the
estimate to complete, which is simply how
much more it's going to cost to
finish this project.
24:43
So this is a nice, logical thing that is
simply the difference between what you
now think it's going to cost your estimate
at completion and your actual
cost spent today.
24:56
So based on your current calculations, you
expect it will cost
$100,000 To build your house.
25:03
They've already spent $60,000.
25:05
There's your actual cost.
25:07
So your estimate to complete is simply
$100,000 minus
$60,000.
25:13
You need $40,000 more and funds to complete
this
project. The variance that
completion is perhaps one of the easiest to
understand.
25:26
It is simply the difference between what you
originally thought this project was going to
cost your budget at completion and what you
now think it's going to cost.
25:35
Your estimate at completion.
25:37
So the formula is simply basi minus EIC.
25:43
So, for example, you hoped your house was
going to cost $80,000, but
it's actually looking like it's going to
cost $100,000.
25:52
So our back was $80,000, our estimate at
completion is now
$100,000. So a variance at completion is a
negative number and
remember negatives not good in this case
negative $20,000.
26:10
One of the final formulae we've got to show
you is the two complete performance
index, and this is simply a calculation the
rate at which you have
to go to achieve the desired outcome.
26:23
Now this is the speed at which you need to
work to hit either your
new estimate at completion or your original
budget at completion.
26:33
So the formulas are very similar with the
exception of changing
BAC and EAC between them.
26:40
So you'll see if you want to calculate your
to complete performance index to achieve your
budget at completion.
26:47
It's BAC minus EAC divide by BAC minus
AC. And if you want to calculate your TCPI
for your new
estimate at completion, the first part of
the formula is the same
back minus EV.
27:04
But this time it's divide by AC minus AC.
27:09
So in this instance, having a ratio above
one is bad,
below one is good.
27:15
So if you had a two complete performance
index for your EAC of
0.9, it would mean to achieve your AC, you
simply
need to put in 0.9 Days effort for every day
being worked on the project.
27:31
So remember, this is the only time that less
than one is good and greater than one is bad.
27:37
So let's take you through a big example and
see if you can work this out.
27:42
Now the key to this example and the exam
questions is getting those first
four numbers out successfully.
27:50
This is the budget at completion.
27:52
Your actual cost, your planned value and
your earned
value. You must get those four numbers out
of the scenario
correctly. Otherwise, remembering the
formula doesn't matter.
28:05
You put the wrong numbers in, and the
chances are there could be an answer
waiting for you based on the most common
errors people make and extracting those
parameters. So let's say you are the project
manager
on a project to build 40 kilometers of road
at a cost
of $10000 per kilometer over 20 months.
28:30
Ok. At 14 months into the project, you've
built
22 kilometers of road and spent a total of
two hundred and five thousand
dollars. So let's get those first
four numbers out of the scenario, the first
one.
28:49
What is our budget at completion?
This is our originally approved budget for
this project.
28:55
And that's simply $400000.
29:00
We're approved 40 kilometers of road to
build at a cost of $10000 per kilometre.
29:05
Therefore, our back four hundred thousand
dollars.
29:12
What about our actual cost that's usually
the next easiest one to get out of there?
Here it's right in front of us, it seems
very clearly that at this point in the
project, we've spent a total of
$205,000. So that's our actual cost.
29:29
$205,000.
29:33
Let's work on our planned value and then our
earned value.
29:37
So our plan value is calculated using time.
29:42
So we need to look at how far through this
project we are in terms of time.
29:47
And use that as a percentage on our budget
at completion.
29:51
So in this example, we are 14 months into a
20
month project.
29:58
14 into 20 is 70 per cent.
30:02
So, then our plan value, at 70 per cent of
our budget at
completion. Remember, our budget completion
is
$400,000. 70 per cent of that is
$280,000. Now this is a simple example.
30:20
Obviously, we're assuming a linear spin
throughout our project.
30:24
In the absence of having a graph in front of
us that we can read off, showing our actual
proposed spend using that method is the best
we have.
30:33
You may be presented with a graph where you
can read off exactly what you'd plan to
spend, but if not, simply take the
percentage of time through the project
and multiply that by your budget at
completion.
30:47
Let's take a look at the last number earned
value, EV.
30:51
This is often the most difficult to get.
30:54
This is the value of work created at this
point in the project, not the
actual cost, but the value.
31:01
So we know what we've done.
31:02
We've built twenty two kilometers at this
point in the project.
31:08
And we know, according to our original
approved budget, that each kilometer is worth
$10000 to us.
31:16
So ignore what it cost us.
31:19
The value is $220,000, that's our earned
value.
31:25
So there we are.
31:26
Those are the four numbers you need to get
out a budget at completion of
$400,000. An actual cost of
$250,000, a planned value of $280,000
and an earned value of $220,000.
31:45
Now if you get all of those out successfully
and use the right formula, you should be
able to calculate cost variance, cost
performance index schedule variance,
should your performance index estimate at
completion, estimate to complete and
variance at completion.
32:01
And if you want to do this as an exercise,
give yourself some bonus points for using at
least three different formula for estimate
for completion.
32:09
But he has some answers to help you along.
32:12
First up, there are the first four numbers,
and I do stress you must get those out of the
question successfully.
32:20
If we get those out, we see for this
example, we have a cost variance of
positive $15,000.
32:27
And remember, positive is good.
32:30
We have a cost performance index of 1.07,
which means for every dollar we're
putting into this project, we're getting a
dollar and seven cents return.
32:39
That's good as well for schedule variance.
32:41
However, though we have a negative number
negative $60,000
and that translates into an SPI of 0.79.
32:51
That means we're behind time for every day
that we've been working on this
project. We're only getting 0.79 Days
return.
33:00
Now, just a word of caution for the exam.
33:04
Be careful with your rounding techniques.
33:07
They may be slightly different, so always
round to two
digits. And if your calculations are within
a dollar or two of the
answers, that's probably the right answer.
33:19
Now, if we take all of those numbers and
apply them to the following, we'll just use
to estimate at completion formula here.
33:26
The first one budget at completion divide by
Cost Performance Index says
that we now think this project remember,
instead of costing $400,000, will
now cost us $373,831.
33:41
If we use the other estimate at completion,
when the big one, my personal favorite,
this time we get an estimate of completion
of
$. You can see between those two calculations
is quite a
difference. One is indicating that we're
coming in under budget.
34:01
The other is indicating that were coming in
over budget.
34:05
And that's why our estimate to complete and
our variance at complete
calculation all depend on which estimate at
completion formula you
use. So take care to use the correct one.
34:17
And as I've already said, that's why I
prefer to use the longer estimate at
completion one because it takes into account
our time performance to date as well as our
cost performance.
34:30
So after using all of those tech tools and
techniques in this control cost
process, we will turn our work performance
data into relevant
work performance information that we can
understand and make sense of.
34:44
And obviously, in this instance, we can see
we've got our cost information and our
schedule information, and we've got our
forecasting information there with our cost
forecasts. As a result of controlling costs,
we may also
generate some change requests, making
changes to whatever we plan to do or
what we're actually doing.
35:04
And don't forget, these change requests go on
to be inputs into the form
integrated change control, where they will
be assessed and processed, and decisions
made, according to our particular change
management plan.
35:17
Some of the other outputs we may make, if
appropriate, we may update our
project management plan or any part of it
just to improve it a little bit.
35:26
Tweak it a little bit.
35:27
We may choose to update project documents
like our lessons learned or historical
information, and we may also choose to
update as a result of our
commitment to continuous improvement.
35:38
Our organizational process assets to always
make sure we're doing
great cost control in our project.
35:47
So in summary, the control cost process uses
the cost
management plan to provide guidance to all
of our cost monitoring and controlling
activities. And the biggest part of it is
the use of the earned
value management technique to gather
information about cost and time performance
to date. And then using formula like
estimate at completion
to forecast a likely future time and cost
performance.
36:16
So I want to stress this.
36:18
You need to remember all of those formulas
and have an understanding of them for the
exam. I can't tell you how many questions in
the exam
will require you to use the formula or which
particular formula you will need.
36:33
You just need to take them all in with you.
36:38
So thank you. This has been an introduction
and overview of the control cost
process of the PMBOK guide.