00:01
Hello and welcome.
00:02
This module will focus on the closed
procurements process and the PMBOK
guide. The difficulty and the exam
importance are both
rated as medium because it's one of only two
closing processes in the PMBOK guide,
and it must be done properly because it
could have severe legal implications if not
done properly. But memorization is low.
00:25
There's not a lot of new or complicated
concepts being introduced here.
00:31
The closed procurement process is one of
four procurement
management knowledge area processes, but
this one closed procurements is focused
on ensuring that all of our contracts are
closed.
00:45
Both normally and also under less than
normal conditions, and that's a rule
for the exam.
00:51
All contracts must be closed regardless of
whether it's
normal closure or abnormal closure.
01:01
The particular domain task.
01:04
That the closed procurement process helps us
understand its closing task
three, which says obtain financial, legal
and
administrative closure closure using
generally accepted practices and
policies in order to communicate formal
project closure and
ensure transfer of liability.
01:29
The key themes of this process.
01:33
It is a subset of closing a project or phase
process, but it can also
be done at any point in the project.
01:40
If you've signed a contract during Planning
or early on in executing that
work may be completed and as such, the
contract would be completed
early on in the project.
01:52
But regardless, as you go through the
closing of project or phase
process, you must ensure first that all of
your contracts are
close. And it's about obtaining final
acceptance
of all of the project deliverables as well.
02:10
And making sure that we've got that
financial, legal and administrative closure
and all of the contracts that impact on that
are closed.
02:21
So the particular inputs that we will want
will be the project management plan
and our procurement documents.
02:28
The part of the project management plan that
we will want, especially is our procurement
management plan. We'll need those
procurement documents because
within them and the contracts that make them
up are the conditions for
closure. Now most contracts have a part of
them, which spells
out how they are closed.
02:50
In my experience, though, most project
managers don't know what they are.
02:53
So I do encourage you if you're involved and
delivering anything with a
contract with your buyer or seller, read it
in its entirety,
particularly those conditions for closure,
and they will probably outline
conditions for normal closure and conditions
for abnormal
closure. So some key
concepts you need to be aware of.
03:19
First up. Every contract must
be closed.
03:26
No exceptions, you must be able to prove
that both parties
have agreed that that contract has ended.
03:34
So make sure for the exam, you know, every
contract must be
closed. Of course, the difficulty can be if
a question poses the following
scenario. Perhaps you're working on a
project
and money just dries up really quickly.
03:49
How do you close every contract?
If you don't even have money to close the
contracts?
Well, on that instance, the answer would
probably be do a summary as quick as you
can that the contract was closed because of
exceptional and extraordinary conditions and
maybe get the project sponsor to sign it.
04:08
Contractual closure or close closure of all
procurements is done at the end of a
contract. Remember, it doesn't mean the end
of a project.
04:16
Contracts can be for work done at the
beginning of projects and in which
case by the time they end, you're not even
halfway through a project yet, but you've
still got to close those contracts.
04:28
We know that the research tells us that
many, if not most, contracts
actually end with negotiated settlement, and
this is perfectly fine.
04:38
A negotiated settlement is where you come to
an end of a contract and this loose ends to
tie up, and maybe the contractual terms are
a little ambiguous or even
silent on how to deal with that.
04:49
And so the parties may come to a negotiated
settlement, and this is where they go.
04:54
Well, if you do, that will pay you that and
we'll call it quits.
04:58
Now, that's not uncommon and it's perfectly
acceptable.
05:02
So you will also need to know the typical
conditions that a contract can be closed
under. The first one are the normal
conditions of contract, and
these are spelled out in the contract.
05:14
There's also breach of contract.
05:17
This is where one party breaches the terms
of the contract, in
which case the contract can be closed.
05:24
You'll need to have a robust understanding
of the laws of the country in which you're
operating, though, on how the civil part of
those laws affects
breach of contract.
05:34
It can be different.
05:36
Also, beware of force majeure or act of God
as a reason for
contracts to be closed or terminated.
05:44
So these are the normal conditions that you
may come across for termination of contract,
normal termination or closure, breach of
contract and force majeure or
act of God and our Act of God includes
things like weather events or
earthquakes. I'm not sure if it includes
war.
06:02
You need to check the local laws in your
country there.
06:08
The tools and techniques that you may choose
to use in order to successfully close your
procurement documents and contracts include
procurement audits.
06:17
Obviously, given that your procurement
documents are documents, you'll audit
them, you'll check what they say, how
termination or closure is to
happen and whether that has actually
occurred as per the terms in the contract.
06:32
Or you will use your own organizational
process assets
relating to contractual closure and make
sure you've followed those steps
as well. That's what an audit is about,
making sure the processes have been followed.
06:47
You may carry out procurement negotiations,
as I've already mentioned, most
contracts end with a negotiated settlement.
06:55
And this is because of the usual ambiguity
that exists in many contracts.
07:01
So a way to get through negotiations to end
the contract, as I've already
said, is simply saying one party says you do
this and we'll pay you that and the other
party agreeing.
07:11
But be aware that procurement negotiations
can quickly escalate.
07:16
From negotiation to mediation to arbitration
and finally to
litigation, negotiation is where both
parties
attempt to negotiate a solution.
07:29
Mediation is where they formally negotiate
and they may have
somebody in there helping them to mediate an
agreed solution.
07:39
Arbitration is where both parties agree to
appoint an independent
arbitrator. And both parties will make their
case to the arbitrator,
and the agreement may be that the arbitrator
makes a binding or
non-binding decision.
07:56
Obviously litigation, on the other hand,
well, both parties appear in front of
a judge and the judge's decision is binding.
08:04
So remember that negotiation, mediation,
arbitration and
litigation as the natural path of escalation
of negotiations
gone wrong?
The other total technique that you may
choose to use are your own record management
systems. And this is the place that you
store all of your contract, your
records so they can be accessed easily and
once they are closed, they
can be archived and retrieved easily in the
future.
08:34
Remember, many countries have a statute of
limitation for civil liability and
contracts. And you'll need to keep these
records for at least that
long. Some organizations require you,
though, to keep these records for a
lot longer.
08:50
So your records management system should be
robust enough to cater for your
current needs for storage and retrieval of
your procurement documents, but
also those archival needs so that they can
be found and retrieved
easily many years down the track.
09:09
The particular outputs that will come from
the closed procurement process
include well, closed procurements.
09:17
This is proof that you've you've closed all
those contracts, often letters are
exchanged by all parties agreeing that the
contract has been closed under
normal or abnormal conditions, and they may
also outline the agreements
or negotiated settlements that were arrived
at as well.
09:36
But you must have proof in some way that the
parties agree that
the contracts were closed.
09:42
This will also include proof that all the
payments were made as per the terms of the
contract, and there's no outstanding
payments to be made.
09:51
Now, this can be a little difficult when
you've got a contract that has
a sum of money kept for a difficult period
or a warranty period, which could
be one or two years away.
10:03
If this is the case, you'll need to come to
an agreement with all
parties about how that part of it is handled
by perhaps another part of your
organization. Well, after your project has
finished,
you may also want to update your own
organizational processes as part
of your commitment to continuous
improvement.
10:25
You may want to make sure they're better.
10:28
You may want to identify deficiencies.
10:31
And update your own project management
methodology in relation to procurement
closure activities.
10:39
So in summary, the closed procurement
process
has focused on ensuring that all contracts
are closed.
10:48
No exceptions.
10:49
You must be able to prove that they were
closed.
10:52
And remember, this generally happens as a
result of negotiated settlements
or normal conditions of closure and
contractual
closure must be done before you can close a
project.
11:07
So before you can finish absolute and final
project closure, you
must have closed off all of your contracts
as well.
11:18
So thank you very much.
11:19
This has been an overview and an
introduction to the close procurement
process and the PMBOK guide.