00:02
Hey, time to have a look at the critical path
method.
00:06
It is one of the project manager's best
tools when scheduling a project
timeline. Let's jump to the laboratory
project and assume, because you're
an awesome project manager, you have done
everything you need to up to this point.
00:20
And of course, you're still as cool as a
cucumber.
00:23
You have your list of activities and their
durations with buffers.
00:28
And bear in mind, this is a snippet of the
activities that would be involved in a
project. You will see that later.
00:35
Things get very detailed, but in the
interest of time, I will demonstrate what we
need with a shorter list of activities.
00:42
What you must do as project manager is
identify the longest
chain of dependent activities required to
complete the project.
00:51
This is called the Critical Path.
00:54
It is critical because delays to this path
will certainly cause delays to the whole
project. One of the best ways to plot the
critical path is to put
the information in a network chart with
boxes and arrows.
01:08
This works well because it shows all the
tasks and all the durations
in the boxes and all dependencies, the
arrows making it as easy
as pie to chart a critical path.
01:21
Okay Using our work breakdown structure and
activity list,
let's begin.
01:29
So we have our full workstreams showroom
construction,
car selection and production.
01:36
Visual Effects development and staff
recruitment and preparation.
01:40
Each stream can be executed in parallel,
starting with A, O,
K and M respectively.
01:48
Now let's see how each stream flows and how
or if
they intertwine.
01:56
Excavate foundations follows prepare land
for construction works
build foundation structure follows excavate
foundations, build
showroom spaces follows build foundation
structure and so on.
02:13
The majority of these are logical
dependencies.
02:17
But remember, they can always be resource,
external and soft
dependencies to consider.
02:24
For example, if design interiors must follow
C
Build Foundation structure, these do not
seem dependent.
02:34
However, the chief engineer needs to
participate in the design
activities, although he will not have the
available time before the main part of the
construction is done.
02:45
This makes it a resource constraint.
02:48
There we have it now.
02:50
As you can see a through to I is the longest
stream.
02:55
This is the path you will need to be the
most vigilant with, as any
delay here will postpone the whole project.
03:03
This is the critical path.
03:07
With the non-critical paths, you have extra
time where a delayed task
won't halt the overall timeline.
03:14
And this is called a float.
03:17
As you can see, the cast selection and
production stream has a float of two weeks.
03:22
Therefore, if a task is delayed within this
float, it won't affect the project
directly. However, if there is a delay
longer
than the float, then this non-critical path
becomes the critical path.
03:36
Yes, that's right.
03:38
The critical path is dynamic and can change
during the project, so you
will need to monitor it carefully as the
work progresses.
03:46
Once you've done, here is a major step to
creating the project schedule.
03:52
But there's one more thing you can do to
further help yourself, and that is by
making a Gantt-Chart.
03:59
And next lesson will be taking a good look
at that.
04:03
Thanks a lot.