00:02
Things are chugging along nicely at this
point.
00:04
We have a work breakdown structure and
activity list.
00:08
We've got an estimation of their durations
and we stuck some buffers on to cover our
backs. Wow.
00:13
Way to go. But things do look a bit like an
activity soup right now.
00:19
We need to jumble this mess and see how
activities link with each other.
00:24
In other words, we need to understand their
dependencies.
00:28
It's not hard to imagine how some tasks are
dependent on others.
00:33
You can't have the cars delivered without a
showroom, and you can't build your showroom
until you've started digging.
00:39
And you can't start digging until you have
the machinery on site.
00:43
You can, however, start recruiting the sales
team.
00:47
So let's look at the four main reasons why
dependencies exist between
tasks. First logical
dependency. This is just like what I
described.
01:01
You can't put windows in your showroom until
you've built walls.
01:06
Second, we've got resource constraints.
01:09
Lack of resources can affect the sequencing
of tasks.
01:13
Let's say you have to work packages as part
of your showroom project.
01:17
One for performing a financial comparison
between two potential interior designers and
another for preparing a detailed report on
travel expenses.
01:26
But you only have one business analyst and
nobody else qualified to perform the
tasks. The two tasks cannot be completed
simultaneously.
01:35
Therefore, your business analyst has to
finish one before they can start the other.
01:42
Third, we have external dependencies.
01:45
These can be anything from building work
that needs to be signed off by the city to
paint work that can only be done in good
weather.
01:53
You get it. The activities that are affected
by external sources.
01:59
The fourth are called soft dependencies.
02:02
These are applied by the project manager
themselves and could include things like a
task not going forward unless the project
manager has checked the previous task.
02:11
They are called soft dependencies as they are
easily amendable due to the fact that
the project manager set them in the first
place.
02:19
Now let's have a look at the types of
dependencies.
02:23
For again, is the magic number here.
02:29
First we have finish to start, where the
second task
cannot start until the first has finished.
02:37
The task paint.
02:39
The whole room cannot start until you finish
the task by paint.
02:45
Second there is finish to finish where the
second task cannot be finished
until the first has been finished.
02:52
The task, paint the whole room cannot be
finished before task paint the fourth
wall is fully finished.
03:00
Third is start to start where the second
task can only start when the
first starts the task paint.
03:07
The whole room must start.
03:09
So the task paint, the first wall can also
start.
03:14
And lastly the not as common.
03:16
Start to finish where the second task has to
start before the
first can finish.
03:23
Let's step away from the painting.
03:25
Examples for this one and imagine the
construction site needs 24 hour
security. Guard two's shift must start
before
Guard one's shift can finish.
03:36
This way there will be no interruption in
the surveillance for any thieves to sneak in.
03:43
As always, the project manager must take all
these factors into consideration because any
missed dependencies are sure to cause delays
and increase costs.
03:52
Once the project manager has worked out the
dependencies, we can apply the critical path
method. We came across a couple of lessons
ago to potentially find out the shortest time
in which we can complete the project.
04:04
So let's look at this next.