00:02
Let's start by looking at timelines.
00:05
How can a project manager see if the project
is running on time?
Well, they should constantly observe the
progress against the plan.
00:14
After all, we didn't build the project plan,
the Gantt-Chart and the milestone table for
decoration. They are super useful tools to
measure actual progress
with. Here is a small slice of our
Gantt-Chart
and let's have a look at the status of these
activities.
00:33
We can see that the first one has been
completed, as has the second and
third. The fourth is in progress.
00:40
We can see we're halfway through.
00:42
However, the planning documents do not tell
us if the actual progress is going
at the rate fast enough to complete this on
time.
00:50
So if a stakeholder asks if this talk is on
track, well,
we don't really know yet.
00:59
But once we learn about what PMI refers to
as the schedule variance,
that will change.
01:06
Then we will be able to confidently answer
any questions the stakeholder may have about
the progress of a task.
01:14
So what is the formula for calculating the
schedule variance?
First we need to know the planned value.
01:23
This is the amount of work we plan to have
been completed up to this point.
01:28
For example, for the task build walls, there
are four main
walls to be built, meaning one wall every
week.
01:37
So at the halfway point, the planned value
would be two walls complete
and work on the third to start.
01:46
Then we need to work out the earned value,
which is the value of work
completed to the present moment.
01:53
In other words, the actual.
01:55
So as a forward thinking project manager,
you ask your chief engineer to
complete reports each day on the progress of
the construction.
02:04
For the sake of simplicity, let's assume the
main work is building for load bearing
walls. You have a target to create a wall
every two weeks, ten working
days. You may see something like this.
02:18
Cool. We can see wall one was completed on
time while
wall two is at 80% completion.
02:26
That makes our earned value 1.8 walls.
02:31
So now the formula to see if we're on track.
02:35
The schedule variance is 1.8 minus two,
which
equals -0.2.
02:43
That's right. We're behind schedule, and if
we don't catch up, this task will be
delayed. But by how much exactly?
Let's work out the pace of the work and how
significant the delay will be using another
tool from PMI.
02:59
The Schedule Performance Index.
03:02
The Schedule Performance index is easy to
use.
03:06
We consider the same numbers as before, but
this time divide like this.
03:12
If the scheduled performance index is lower
than 1.0, it means there will be a
delay. And if it's more than one, then we're
ahead of schedule.
03:21
In our case, 1.8 divided by two equals
0.9, meaning if the team continue at the
same rate,
they will have completed 90% of the walls by
the deadline.
03:34
Therefore, we will need 10% more time.
03:38
So we work out 10% of the 20 working days in
four weeks
being two additional working days needed to
complete the task.
03:47
Can you appreciate how useful this
information is?
Instead of reaching the deadline and seeing
only 90% of the work completed and then
relying on the buffer to do the rest, you
have given yourself and the project team
plenty of time to react.
04:03
Either you find a solution to quicken the
pace, maybe hire more staff or motivate the
team. Or at the very least, you can prepare
the project for a delay by pushing other
tasks back.
04:14
But that's obviously not ideal.
04:17
Next, we're going to look at controlling
costs.
04:21
Thanks for watching.