Playlist

Control of the Schedule of a Project

by 365 Careers

My Notes
  • Required.
Save Cancel
    Report mistake
    Transcript

    00:02 Let's start by looking at timelines.

    00:05 How can a project manager see if the project is running on time? Well, they should constantly observe the progress against the plan.

    00:14 After all, we didn't build the project plan, the Gantt-Chart and the milestone table for decoration. They are super useful tools to measure actual progress with. Here is a small slice of our Gantt-Chart and let's have a look at the status of these activities.

    00:33 We can see that the first one has been completed, as has the second and third. The fourth is in progress.

    00:40 We can see we're halfway through.

    00:42 However, the planning documents do not tell us if the actual progress is going at the rate fast enough to complete this on time.

    00:50 So if a stakeholder asks if this talk is on track, well, we don't really know yet.

    00:59 But once we learn about what PMI refers to as the schedule variance, that will change.

    01:06 Then we will be able to confidently answer any questions the stakeholder may have about the progress of a task.

    01:14 So what is the formula for calculating the schedule variance? First we need to know the planned value.

    01:23 This is the amount of work we plan to have been completed up to this point.

    01:28 For example, for the task build walls, there are four main walls to be built, meaning one wall every week.

    01:37 So at the halfway point, the planned value would be two walls complete and work on the third to start.

    01:46 Then we need to work out the earned value, which is the value of work completed to the present moment.

    01:53 In other words, the actual.

    01:55 So as a forward thinking project manager, you ask your chief engineer to complete reports each day on the progress of the construction.

    02:04 For the sake of simplicity, let's assume the main work is building for load bearing walls. You have a target to create a wall every two weeks, ten working days. You may see something like this.

    02:18 Cool. We can see wall one was completed on time while wall two is at 80% completion.

    02:26 That makes our earned value 1.8 walls.

    02:31 So now the formula to see if we're on track.

    02:35 The schedule variance is 1.8 minus two, which equals -0.2.

    02:43 That's right. We're behind schedule, and if we don't catch up, this task will be delayed. But by how much exactly? Let's work out the pace of the work and how significant the delay will be using another tool from PMI.

    02:59 The Schedule Performance Index.

    03:02 The Schedule Performance index is easy to use.

    03:06 We consider the same numbers as before, but this time divide like this.

    03:12 If the scheduled performance index is lower than 1.0, it means there will be a delay. And if it's more than one, then we're ahead of schedule.

    03:21 In our case, 1.8 divided by two equals 0.9, meaning if the team continue at the same rate, they will have completed 90% of the walls by the deadline.

    03:34 Therefore, we will need 10% more time.

    03:38 So we work out 10% of the 20 working days in four weeks being two additional working days needed to complete the task.

    03:47 Can you appreciate how useful this information is? Instead of reaching the deadline and seeing only 90% of the work completed and then relying on the buffer to do the rest, you have given yourself and the project team plenty of time to react.

    04:03 Either you find a solution to quicken the pace, maybe hire more staff or motivate the team. Or at the very least, you can prepare the project for a delay by pushing other tasks back.

    04:14 But that's obviously not ideal.

    04:17 Next, we're going to look at controlling costs.

    04:21 Thanks for watching.


    About the Lecture

    The lecture Control of the Schedule of a Project by 365 Careers is from the course Project Phase: Monitoring, Controlling, Closure (EN).


    Author of lecture Control of the Schedule of a Project

     365 Careers

    365 Careers


    Customer reviews

    (1)
    5,0 of 5 stars
    5 Stars
    5
    4 Stars
    0
    3 Stars
    0
    2 Stars
    0
    1  Star
    0