00:03
So how does this all affect our cost?
Will we complete the scope within the
budget?
Well, let's be proactive and find out, shall
we?
We know what planned value and earned value
are, the value of the work
planned and the value of the work completed
respectively.
00:22
We calculate the cost variance to learn if
we are on budget and the cost performance
index to learn if the rate of our spending
will allow us to remain within budget for
this activity and the project as a whole.
00:34
So first things first.
00:36
Let's transform our planned value and earned
value into dollar amounts.
00:42
Let's say the budget for the build walls
activity is $200,000.
00:47
This would mean each war would cost $50,000.
00:50
And our earned value so far is 1.8 walls.
00:55
To convert this into dollars, we multiply it
by the number of dollars.
00:58
So 1.8 times 50,000 equals 90,000.
01:04
We do the exact same thing for planned
value.
01:07
So 2.0 walls multiplied by 50,000 equals
100,000.
01:14
Okay. Once we've calculated, planned and
earned value, we need to
add the actual cost to the equation.
01:22
Like the good project manager you are.
01:25
You have been recording how much money has
been spent up to this point.
01:30
That said, it's time for a formula.
01:33
The calculation for cost variance goes like
this.
01:37
You can see from your budget you have spent
$83,000 on wall so
far. So the formula would be earned value
minus actual
cost. So $90,000.
01:50
-$83,000, which equals $7,000.
01:55
This is a positive number, which means we
are doing better than planned and are
under budget.
02:02
As you can guess, if it was a negative
number, the opposite would be true.
02:07
So while your team is behind schedule, they
are spending less on
the walls. Now let's predict the future with
the
cost performance index.
02:20
Once again, we divide.
02:22
So it's earned value divided by actual cost,
$90,000
divided by $83,000, which equals
1.08. Because the same rules apply.
02:35
If the number is above one, then we will be
under budget if the work continues at the
same rate of spending.
02:41
If the number is below one, then we expect
to be over budget.
02:46
Awesome stuff. With this information, we can
see that we are behind on
time, but ahead on budget.
02:52
And if you remember our triple constraint
triangle.
02:57
We've become a bit unbalanced.
03:00
Even if we save money on the project but are
over the deadline, then the project is still
a failure. So you must focus on fixing the
area where the problem lies.
03:10
By performing these calculations, you can
see that perhaps if you spend some of the
extra money you saved and hire more labor,
then you'll get the work back on schedule and
balance out the triangle.
03:21
Next lesson we'll talk about controlling
quality.
03:24
We need to make sure that the output we're
generating is to the standard we want.
03:29
There's no point in saving money in time if
what we produces of the lowest quality.
03:34
Thanks for watching.