00:04
Issue management is an essential part of the
project manager's job.
00:08
We've seen how to execute a project from
start to finish without issues, but there
will always be some.
00:14
That's why it's a good idea to have a look
now at a detailed case study to show how
detailed planning, good interpersonal skills
and, of course, issue management
combined to keep a project on track.
00:25
Let us set the scene.
00:27
It's early March and the project is
progressing well.
00:30
Rey, our project manager, starts her
Wednesday with the next project status
meeting. She begins her usual routine,
writing down the participants and starting
with the overall status of the project.
00:42
Last week everything was green.
00:44
Construction works are progressing very
well.
00:47
Rey is feeling confident.
00:48
Then Richard, the lead engineer, shares this
week's status.
00:54
There have been a few slowdowns this week,
but the construction team managed to catch
up. We are now back on track and will
complete the walls very soon as per the
schedule. Perfect.
01:05
Thanks, Richard.
01:08
Rey continues. Let's move to the next key
workstream.
01:12
Car manufacturing.
01:14
She turns to the head of manufacturing.
01:17
Jeff, you have not participated the last two
meetings.
01:20
How are things progressing?
Yes, I was on holiday the last two weeks.
01:26
And unfortunately, my report is not
positive.
01:29
The manufacturing is experiencing a delay.
01:33
The marketing manager responds immediately.
01:36
How big is this delay?
We plan to complete a car every four weeks.
01:42
However, it takes us more than five weeks per
car for six cars.
01:46
This means we need a total of 32 weeks,
eight more than the 24
planned. So the delay is about 30%.
01:55
My apologies. We will do our best to catch
up.
02:00
Quiz moment. What would your reaction be?
One Respond rigidly.
02:06
Ask for immediate resolution.
02:08
Demand that Jeff fixes it all in two weeks
time.
02:11
He is responsible for the car manufacturing.
02:14
To respond calmly, try to understand more
about the issue and
what the impact is after that.
02:22
Work out what can be done to resolve it.
02:25
Three respond calmly.
02:28
He has apologized, so you cannot yell at
him.
02:31
Hopefully next things will be better.
02:35
Answer. You need to carefully analyze the
situation.
02:41
Emotions must stay under control not only
the project manager's emotions, but also
those of the other stakeholders.
02:47
Finger pointing is not good practice.
02:50
Therefore, answer one is wrong.
02:53
Answer three is also wrong.
02:55
You are emotionally under control, but you
have not planned any action to address the
issue. Hoping it will be better next week is
not going to help.
03:03
You need actions.
03:05
So as you probably guessed, answer two is
the best.
03:12
Rey responds calmly.
03:14
Thanks for sharing, Jeff.
03:16
Is clear. We have an issue and the delay is
serious.
03:19
Do you know why the assembling is moving so
slow?
The marketing manager interrupts nervously.
03:27
The exhibition cars are the most important
thing.
03:30
There's no point in the whole project if we
don't have the cars.
03:33
Your department is responsible for getting
this fixed as soon as possible.
03:37
Victoria, you're in charge of HR.
03:39
You need to recruit more people.
03:42
Jeff responds. Defensively, the workers are
doing their best.
03:46
We even added one more person to work only
on the exhibition models.
03:50
It's not their fault.
03:52
Then suddenly the whole room is speaking
over each other, pointing fingers, making
excuses. Things are getting out of hand.
04:00
Rey knows she needs to take control of her
meeting and interrupts the crowd.
04:05
Everybody, please let me recap.
04:08
We have an issue in the manufacturing stream
which we cannot resolve during this meeting.
04:12
I will address all the details afterwards.
04:16
I will add an action for me and Jeff to meet
and discuss an action plan this afternoon.
04:21
Jeff, is that okay for you?
Jeff confirms.
04:25
Rey writes this in the Project Diary.
04:28
Great. We will resolve this in due course.
04:31
For now, we must continue with the meeting
as there are still areas we need to discuss
if we are going to make this project a
success.
04:39
Okay. Let's see the last workstream.
04:42
Recruitment and training of the staff.
04:44
Victoria, how are we looking?
All is progressing well.
04:48
We posted the job offer on various sites two
weeks ago and have already scheduled a few
interviews. No concerns at this point.
04:56
Rey grins.
04:58
Okay, team, thank you for today.
05:00
Any other questions?
No. Okay.
05:03
I will email you all the minutes of the
meeting and we will see each other next week.
05:08
Whoo! Tough day.
05:10
Quiz moment. What is Rey's best course of
action?
One. The issue is huge and the whole project
can fail
immediately. Write an email to the sponsor
explaining there is a high chance the project
will be delayed. Suggest that new people
should be recruited in manufacturing
to meet with Jeff and discuss the details
behind the issue and their possible
resolution. After the meeting, send a note
to the sponsor informing them on the issue.
05:39
Three. Calm down.
05:41
Stress does not help anyone.
05:43
Wait until next week to see what the
progress will be.
05:47
Answer. Same as before.
05:51
Answer to balances emotions and comes up
with correct actions to take.
05:56
Rey writes down the meeting's minutes and
sends it out.
05:59
She now has time to think out the problem.
06:02
This is a significant delay, over 30%.
06:06
And we are already a few weeks in.
06:09
A quick calculation shows that at this pace
they will need an extra eight weeks, which is
late August after the target completion date
and is also after the project
completion date.
06:19
Maybe I shouldn't waste time and go straight
to the sponsor to start the process of hiring
more people to help out.
06:25
Although that doesn't sound right, let me
check my notes from the
365 project management course I took.
06:32
I have a section on issues.
06:34
Maybe you can help me organize my thoughts.
06:38
Ah, yes, I remember.
06:40
React, read, respond, resolve or repeat.
06:45
Hmm. That's right.
06:47
If I do go to the project sponsor, it's my
responsibility to bring more information
and possibly a suggested solution.
06:54
I'll see Jeff in a bit and work on the first
two steps.
06:57
React and read.
06:59
I will, however, write in pencil the root
cause of the delay.
07:04
Slower production and manufacturing.
07:09
Rey goes to Jeff's office.
07:11
She sees his name and title on the door.
07:13
Jeff Vader, head of manufacturing.
07:17
The two meet.
07:19
Hi, Jeff. Hey, Rey.
07:21
How are you? How was your vacation?
Very nice. Thanks. We went skiing.
07:27
There wasn't much snow during the first few
days, so we went for a hike and climbed a
mountain. It was amazing.
07:32
Felt like I was on top of the galaxy.
07:35
Anyhow, let's get back to work.
07:37
We are in a bad situation.
07:40
Unfortunately we are.
07:42
Please tell me more about the delay.
07:44
What has been done so far to react to the
issue and increase the speed or production?
Jeff responds.
07:52
As soon as I came back and found out about
the delay, I added one more mechanic to work
on the project cars.
07:58
Rey adds the comment into the React box,
Rey continues, Has that helped
increase the speed of manufacturing?
Jeff Checks notes?
Not really.
08:09
It seems my mechanics are not actually
causing the delay.
08:13
I spoke to our shift lead.
08:14
He confirmed the mechanical works are done
as per expectation.
08:18
However, the software engineers are
delivering their part too late.
08:23
Rey puzzles. Software engineers.
08:26
Can you tell me more about the car
manufacturing process, the main stages from A
to Z? It is time that we read this situation
more carefully.
08:36
Jeff agrees and begins.
08:39
Simply said it works like this.
08:41
With the help of robots, the mechanics work
on the chassis the core of the
automobile doors are then assembled and the
body goes through the painting salon.
08:51
Then mechanics install the engine, the
transmission, etc.
08:54
Electronics and software from basic driver
controls to Bluetooth media are then
programmed and tested by the IT department.
09:01
Once ready interiors are assembled and the
mechanics complete the installation.
09:06
Voila! Rey responds.
09:09
Oh, so it's not the mechanics on the
assembly line that are late, but the software
unit. Yes.
09:15
Jeff says okay seems my initial guess of the
root cause has to be
updated. Rey erases the previous and updates
the root cause.
09:25
Rey then asks, Have you discussed the issue
with the software team?
I wanted to push them to be faster, Jeff
responds.
09:34
I spoke to their manager.
09:35
However, he was not very cooperative and
said it's not possible to do everything so
fast and that they are really busy.
09:43
Rey opens her diary.
09:45
Okay. We need to talk to them.
09:48
I will organise a meeting for tomorrow
morning.
09:51
Rey set up a meeting in the calendar 9:30
a.m.
09:54
inviting Jeff and the IT manager Arthur
Deeto.
09:57
She also invites the three software team
members Bee, Bill and Abe.
10:01
Rey's happy this is organised tomorrow.
10:04
She will understand the issue with it better
and be able to suggest the solution.
10:08
Probably one or two additional engineers
will have to be hired for the IT unit the
next day. Rey is drinking coffee in the
kitchen, chatting with a few other
colleagues, then goes into the meeting room
a few minutes early to read through her
notes. Again, Arthur Bee, Bill and Abe,
enter the room and soon
after. Jeff.
10:28
Rey opens the meeting and explains the
progress of the project and the issue with
the delay in production.
10:33
She also shares that she had a conversation
with Jeff and it seems the capacity of the IT
team is insufficient to deliver on time.
10:41
Arthur jumps in.
10:43
I heard that people are expecting us to
develop, test and complete the software and
electronics faster, but that is just
impossible.
10:51
Everyone knows these are complex tasks.
10:54
Rey replies, okay, I understand and thank
you for the efforts.
10:58
However, we need to solve this.
11:00
I was thinking of requesting additional
resources for your team.
11:04
Arthur sits back in his chair.
11:06
Well, I am not sure this is needed, but even
so, this will not help your project much.
11:11
Recruitment and training would take 2 to 3
months and the showroom needs to be
operational before that race stops to
reflect again.
11:18
Where did she go wrong?
Have the expectations been set wrongly or
are the guys not dedicating the agreed amount
of time to the project cars?
It was supposed to be around 20% of their
time.
11:30
Let's check. Rey directs her question toward
Bee, Bill and Abe.
11:34
Can you tell me on average how much time you
work on the project cars every day.
11:39
They respond in unison.
11:41
Quite a lot recently.
11:43
Maybe three or 4 hours a day.
11:44
Some days even more.
11:47
Very quickly calculates.
11:49
Out of an eight hour working day, this is
close to 50%.
11:53
But how is that possible?
They dedicate two times more on the project
and still there's a delay.
11:59
So it can't be a resource problem.
12:01
So it's probably a wrong estimation of the
duration of their tasks.
12:05
She scratches out the issue again.
12:07
Let's check. Guys, I suppose the I.T.
12:10
and electronics work on the
prototype/project cars is quite different
from what you do every day.
12:15
Does it take you much longer?
Well, no, not really.
12:19
It is quite similar.
12:21
Rey is perplexed.
12:23
What can possibly be the reason then?
Expectations, resources, duration,
estimations all seem to be okay.
12:31
Rey concentrates while the rest continue the
discussion.
12:34
She closes her eyes, starts breathing
slowly.
12:38
She opens her mind to all possibilities and
sees tasks,
activities, scope.
12:46
That's it. She remembers the memo from the
management meeting, which Sonia gave her
during the initiation phase.
12:52
It was about what features and gadgets the
exhibition cars should have.
12:57
Rey asks the IT team.
12:59
Can you please describe the activities you
perform on the project cars?
What are the most time consuming ones?
Bee, Bill and Abe are quick to answer.
13:08
Well, we do the standard computerisation GPS
radio monitor connection,
but what takes the most time is installing
the driving support gadgets.
13:18
Rey is starting to see the big picture.
13:20
What are the driving support gadgets?
Bee, Bill and Abe continue driving control
such as cruise control mirrors.
13:27
Signalisation when cars are nearby, front
sensor to signal if the car in front is
stopping too quickly and if you are
approaching it.
13:35
It is the testing of those that take a good
50 to 60% of our time.
13:40
The force is strong with Rey now.
13:42
She's figured it out.
13:44
She clearly remembers the memo from the
initiation phase when defining the scope and
requirements. The management discussed that
point and decided that for the exhibition
cars, these systems are not necessary.
13:55
The cars will only be displayed and will not
be used for test drives.
13:59
Only the internal computerization is needed.
14:02
The monitor, audio and video.
14:04
Bingo. Rey has finally completed step two.
14:08
Read the situation to find the root cause.
14:12
But it wasn't an easy one.
14:14
Jeff Arthur Rey exclaims, I know what our
root cause is.
14:18
I feel a disturbance in the scope.
14:22
The driving support systems should not be
developed for the project cars as we do in
normal manufacturing.
14:27
For these, we need only the basics.
14:31
Bill, Bee Abe, were you told that?
They all look at each other and respond
together.
14:37
No. Arthur interjects.
14:41
I remember there was some conversation
around that, but I need to check the details.
14:46
In the afternoon, Arthur replies, confirming
this requirement on the scope has indeed been
agreed as per the memo.
14:52
Rey knows the next step is to implement the
solution and asks if Bee, Bill and Abe can be
instructed to reprioritize their tasks and
skip this part.
15:00
As of today.
15:01
Arthur confirms this has already been done a
few minutes ago.
15:05
Great. Rey goes back to her project plan and
Gantt-Chart.
15:08
She quickly calculates when the car
production will finish, if the I.T.
15:12
guys can now move quicker.
15:14
Unfortunately, it's too late to be ready by
the established due date.
15:18
Actually, four more weeks will be needed on
top.
15:22
Hmm. But Rey is an excellent planner, and
she had put five weeks in
between the target production completion
date and the week when the cars will be
positioned in the showroom.
15:32
A hidden buffer.
15:33
So issue resolution, knowledge and good
planning saved the galaxy today.
15:39
Rey checks the Issue resolution lists and
see there is one more step to check if the
solution is working and the issue resolved.
15:47
She will have to repeat step three if the
solution is not effective or even step two if
it comes to light, there is a different root
cause.
15:54
She adds this as a first agenda item for the
next project status meeting to be able to
control progress.
16:01
Finally, Rey sends a summary to the sponsor
explaining the issue, the
root cause and the implemented solution, and
the sponsor replies.
16:10
Thanks, Rey. You have taken the right
actions and I am confident the team will
succeed with the new plan.
16:15
Regards, Sonia.
16:17
During the next few project status meetings,
the actual results show the
manufacturing is moving at the expected
pace.
16:25
Rey can now validate the issue has been
resolved.
16:29
The life of a project manager is a dynamic
one, and how they deal with problems
will make or break them.
16:36
Keeping a cool head and having controls like
this one will ensure they always come out on
top. So that brings us to the end of the
execution phase of the project.
16:46
Next lesson, we'll bring this whole thing to
a close.
16:50
Nice job.