00:01
Hello and welcome.
00:03
This module focuses on the estimate costs
process and
the PMBOK guide.
00:10
It's very important that you pay particular
attention to this module because there
will undoubtedly be questions in the exam
about cost estimating
techniques, and as such, the difficulty
level is rated as medium
because you may not have heard of or used a
lot of these cost estimating
techniques. But none of them are
particularly difficult and hence the
memorization required is low.
00:40
The estimate costs process is one of four
cost
management knowledge area processes in total
and the second of three
planning processes.
00:51
The first planning process was planned cost
management, which provided
us with our cost management plan and we're
going to use that cost
management plan to estimate our costs
because it's going to provide
guidance on the particular estimating
techniques we are going to use
and the level of estimating we look to
achieve.
01:14
Of course, once we have our individual cost
estimates, we can take those
and also our project schedule, combine those
two things together
and develop or determine our project budget.
01:28
Once we have our project budget and our
individual cost estimates, we can then
control costs by looking at each of them and
compare what's
actually occurring in terms of costs and
budget and see if there's a
variance between them.
01:47
The particular domain task that the estimate
cost process helps us understand
better is the planning task to which says
develop
the cost management plan based on the
project scope, schedule
resources approved project charter and other
information using
estimating techniques in order to manage
project costs.
02:10
And in fact, this particular planning task
covers all
three of the project cost management
knowledge area planning
processes, so it covers the developed cost
management
plan. It covers the estimate costs, and it
also covers the
determined budget process.
02:33
The key theme of this process is that it
focuses on the
development of individual cost estimates
using a variety of
cost estimating techniques and the
particular cost estimating technique that you
choose to use will reflect the level of
information you have
and the level of certainty you desire.
02:55
Keep that in mind.
02:57
Estimating is simply a forecast of a likely
future
state and it's only as good as the technique
you use
and the information that you have at hand.
03:09
The more information you have at hand, the
better your estimate will be.
03:14
Often at the beginning of a project, we
don't have all the information at hand
because of progressive elaboration.
03:21
So our cost estimates may have a greater
degree of uncertainty at the beginning of the
project. And as we move through the project,
they'll become more refined and more
accurate. In order to estimate our
costs, these are the particular inputs that
we could use if they were
appropriate. The first one is particularly
necessary, though,
and that's our cost management plan, which
as we know is an output from
the plan. Cost management process and the
cost management plan
itself provides guidance to us on exactly
how we're going to
estimate costs.
04:01
It's going to contain information about the
particular techniques to use the software, to
use the personnel, to use the level of
acceptable uncertainty and how to
deal with that uncertainty.
04:14
We may also choose to use the human resource
management plan because
typically. Personnel on a project make up
the largest
cost, so we will want to know how the
management of people
and our project will affect our costs.
04:31
And this could be such things as employment
conditions or holiday
pay or vacations.
04:38
All of these things may impact upon our
project costs, of course, in
order to accurately estimate our project
costs.
04:46
We'll also want our scope baseline and
remember, this is an
output from one of the scope management.
04:52
planning areas develop scope and the scope
baseline
includes three key elements, and they are
the project scope
statement, the work breakdown structure and
the Work Breakdown Structure
Dictionary. So with all of that information,
we've got an excellent
description of all the things we're trying
to estimate in terms of
cost. The project schedule, which is an
output from
the developed schedule process as necessary
as well in terms of
the timing of costs.
05:28
How much of the costs are going to be
incurred early on on the project?
How much of the costs are going to be
incurred later on the project because there
can be a time value to money as well, and we
may need to take that into account.
05:41
In applying and developing contingencies, for
example, with our cost estimates.
05:47
We may also want our risk register, because
if
we've done it comprehensively, it will
include an analysis of
cost uncertainty on our project.
06:00
And we need to take a look at that
uncertainty and how it affects our cost
estimates. If there was no uncertainty in
our project, our estimates would probably
be highly accurate and not subject to change
throughout the project.
06:14
If, however, we've identified many areas of
uncertainty or risk,
each of those could impact upon our
individual cost estimate or the
range of estimates that we give the final
two inputs
our enterprise environmental factors, which
in this case will include such things
as market conditions.
06:36
The rate of inflation.
06:39
Employment conditions, all of which could
adversely affect our
individual cost estimates, as is also the
rate of borrowing
or financing our project organizational
process assets
that may be useful as an input include our
particular organizational
cost, estimating checklists, our project
management methodology and
sometimes our finance team may give us some
advice and processes to follow
for cost estimating as well.
07:13
So once we have those particular inputs, we
can then move on to
select from the following list the
appropriate tools and techniques to
help us develop our individual cost
estimates.
07:27
Now the great thing about these tools and
techniques I'm about to show you is many of
them we also saw in the development of
individual time
estimates. So if you remember the process
estimate, activity
durations from time management.
07:43
Many of these estimating techniques also
appeared there.
07:48
The first tool and technique that we will
use will be exPERT judgment.
07:53
And remember, you're an exPERT about project
costs.
07:56
Your project team members are an exPERT
about project costs.
08:01
You may also choose to consult others,
particularly professionals like
quantity surveyors, whose job it is to do
accurate cost
estimating. You may also choose to consult
other exPERTs, like accountants or members of
your finance team, for other aspects of cost
estimates.
08:20
Other tools and techniques that you may
choose to use include analysis, estimating
now analysis estimating simply means taking
an analogy or something
similar from the past.
08:32
And using that to give yourself a new
estimate.
08:38
Sometimes analysis is to make it can be
quite inaccurate, but it can always be done
quickly. Sometimes it can actually be quite
accurate, particularly
if you've done the recent activity in the
last three to six months.
08:51
So, for example, in terms of cost
estimating, you could use analysis,
estimating and say six months ago we did a
project where
this component cost us $3000 for this
project.
09:05
We need two of these components.
09:07
Therefore, our cost estimate is $6000.
09:11
That's an analogous estimate.
09:14
A parametric estimate, on the other hand,
involves taking two numbers and
multiplying them together.
09:20
Remember that the word metric is Latin for
number.
09:25
So we need two numbers.
09:27
So for example, we could find out that a
cubic meter of
concrete cost $200 a cubic meter.
09:35
And we need 10 cubic meters.
09:38
And therefore our parametric estimate would
be 10 times 200 would be
$2000 for the concrete that we need.
09:47
Bottom up estimating is generally considered
to be the most accurate, but
also the most time consuming because it
relies heavily on the existence
of a work breakdown structure because the
bottom up part of this
term refers to going all the way down to the
lowest level of
your work breakdown structure, whether it's
work, package
level or activity level, and then for each
of those giving a
reliable cost estimate.
10:18
And then aggregating or adding up each of
those estimates
upwards to give a combined total of your
cost estimate.
10:27
Obviously, as you can see, it can be very
accurate, but as I said,
it takes extra time and energy and you must
have a work
breakdown structure in place to be able to
do that.
10:42
A theft total technique that you may find
useful is the three point
estimating technique sometimes called the
PERT formula
PERT P-E-R-T standing for the program
evaluation and review
technique. And we'll look closely at some
examples of the three point estimating
technique shortly.
11:02
Other tools and techniques that we may find
useful include reserves analysis,
obviously a cost estimate is just a guess at
what you think
an activity will cost at some point in the
future if that
cost estimate is to be incurred in a week's
time.
11:20
It might be quite accurate, but if it's to be
incurred in a year's time, it may not be so
accurate. And therefore you may need to
calculate a reserve
a contingency reserve in this case, which is
for known unknowns in your
project. There are many ways to calculate
contingency reserve.
11:38
One of the easiest is to simply take
historical information from previous projects
about how accurate your cost estimates were
and apply those to the current
estimates. So, for example, you may
have historical information gathered over
the last two years that says that you
routinely underestimate your costs by 20 per
cent.
12:02
What a fantastic lesson to have learned, and
now you can use that to
routinely add 20 per cent to your cost
estimates as a contingency
reserve. Remember that contingency reserves
are always
included in the approved project budget.
12:19
Now this may differ from your actual
experience, but for the purposes of the exam,
the contingency reserve should be treated as
under the control of the project manager
and approved as part of a total project
budget.
12:33
The other aspect of contingency reserves
that you may not currently follow is that
if that contingency or that uncertainty
doesn't manifest, you must return
the contingency reserve to the organization
and not simply put it aside
to use at some point in the future.
12:50
Another aspect or tool or technique that we
could use is the cost of
quality. Now we see this again when we come
to plan quality management,
perform quality assurance and control
quality processes and the quality management
knowledge area. This is the sincere
consideration that must be given
to decisions about quality and how they
impact upon your individual
cost estimates.
13:15
Sometimes, if the cost estimates are getting
too high, you may be asked
to reduce the quality of what you're
producing in an effort to
reduce project costs.
13:27
Well. Reducing the quality certainly
reduces.
13:33
The cost of the estimate, but it doesn't
reduce the actual cost.
13:38
It simply transfers it to further on in the
product life cycle.
13:44
And the cost of poor quality will manifest
and higher
maintenance or higher operational costs or
even impact
negatively on your reputation and lose your
business in the future.
13:57
So if assessing the cost of quality in an
attempt to lower your project
cost estimates, keep in mind that it's not
really lowering the cost.
14:07
It's simply transferring the cost to outside
of the project life cycle to
further points and the product life cycle.
14:16
Another total technique that you may choose
to use is project management software.
14:22
Obviously, we wouldn't expect you to have a
notebook open and write down all your project
cost estimates and use a calculator to add
them all up and continually change them, so
we turn to project management software.
14:33
And there's many versions of very, very good
project management software out there in
the market, ranging from simple spreadsheets
up to dedicated project
software right up to ERP systems that
control all all of an
organization's finances.
14:50
Another total technique that you will find
useful is called vendor bed analysis.
14:56
This is where you go out to the external
marketplace, to
external contractors, and you ask them for a
price or a
cost estimate on a particular piece of work.
15:09
Now, before receiving their price back, you
develop
an expected range of that price with vendor
bid analysis.
15:19
You then look at their bid or their price
and you make sure they've captured
everything they should have captured.
15:26
Make sure they're not deliberately bidding
low because they know that you've missed
something out in the statement of work to be
performed as part of that external
work. So vendor bid analysis as you double
checking and developing a
reasonable expectation of the price you will
receive from external
vendors as part of developing individual
cost estimates.
15:49
You may also choose to use group decision
making techniques, obviously
compiling a whole range of individual cost
estimates.
15:57
Involves talking to a whole range of
exPERTs, sometimes in groups.
16:01
And how do you get people in groups to make
decisions effectively?
Well, it starts with getting them to think
about all the possible options with group
creativity techniques like brainstorming,
thinking laterally, the
nominal group technique where you get the
group to think about the decisions going
forward and which ones you will follow and
which ones you're not.
16:21
And of course, the Delphi technique where you
ask exPERTs
anonymously for their opinion in order to
avoid bullying, groupthink or
peer pressure. And once you have those range
of decisions put
before you that you can then use specific
decision making techniques like
consensus, majority or dictatorship through
a single leader to
make the decisions.
16:45
But it's always a good idea as part of your
cost management plan to make these
decisions early on.
16:54
Let's take a closer look at some of those
tools and techniques I've already mentioned
analogous estimating.
17:01
Analogous estimating and simply taking an
analogy from a previous project and
extrapolating from that.
17:07
What the current cost estimate will be.
17:10
So for example, you could say that on a
previous project, the new
servers cost $20,000 and we need twice as
many on this project,
and therefore our analysis estimate is
$40,000.
17:24
Obviously, the more recent that you've done
the work, the better the analogy will
be. Using an analogous estimate of a project
five years in the past won't be
very accurate. Parametric
estimating is taking a unit measure and
multiplying it by a known amount
to get a particular cost estimate.
17:46
So for example, as I've already mentioned,
if we find out that concrete
cost $200 per cubic meter and you need 10
cubic meters, you're
parametric cost estimate is $2000 simply two
hundred
times ten. That's a parametric estimate.
18:05
The particular form of estimate you choose
to use will reflect the level of
information you have, the level of time you
have and the level of certainty you want.
18:14
Please keep that in mind.
18:17
Now we move on to some formulas now, we've
already seen this particular
formula. The three point estimate.
18:25
In the development of our project schedule
with estimate activity durations
there, we saw the formula with a little T
rather than a little C, the
T standing for time.
18:37
And this instance, the Little C, stands for
cost.
18:41
I choose to remember it with that eight of
the T or the C.
18:44
So the formula is simply our optimistic
estimate,
plus four times our most likely estimate,
plus our pessimistic
estimate divide by six in this case to give
us a weighted average.
18:59
There is a simpler form of this equation
that gives us a simple average,
and that is simply to take our optimistic.
19:07
Add it to our most likely.
19:09
Add that to our pessimistic and then simply
divide by three.
19:12
That's a simple average form of the same
formula, but the one that we're
interested in is the one that gives a
greater weighting to our most likely cost
estimate. And as with the simple average, we
had three
numbers and we divided by three to get the
average.
19:30
And this case, we actually have six numbers.
19:33
If you take a look, this one optimistic
number one pessimistic number.
19:38
And this four most likely numbers.
19:41
So we have six numbers in total.
19:43
Hence, why we divide by six.
19:46
We can also calculate the standard
deviation, and this is useful for
determining a range of certainty.
19:54
Are we 68 per cent certain?
95 per cent certain, 99 per cent certain of
our range of cost
estimates? And to calculate this, we use a
simple formula called a
heuristic or rule of thumb.
20:07
This is isn't actually the formula for
calculating standard deviation.
20:12
That formula is a fairly lengthy formula
known only to statisticians
for the purposes of the exam.
20:20
We use pessimistic minus optimistic, divided
by
six, and it gives us something close enough
and of use to us.
20:30
Another variable that we could calculate
would be the variance, which is
simply the standard deviation squared.
20:38
Now, for the purposes of the exam, you need
to read the question carefully.
20:43
The question may give you the variance and
ask you to calculate two standard
deviations either side of the mean.
20:50
So the first thing you need to do is to take
that variance and determine the square
root of it. So if your variance was $25,
the square root of that would be $5.
21:03
That's your standard deviation.
21:06
So let's take a look at some examples of the
three point or PERT estimating
technique. Let's say we have a pessimistic
estimate of
one hundred and fifty dollars to complete
this activity, yet we've got an optimistic
estimate of $50 to complete this activity.
21:24
But a most likely estimate of $80 to
complete this activity.
21:29
Of course, when presented with this range of
estimates, the challenge is how do we justify
which one we use?
And this is where the three point estimating
technique.
21:39
Shows its strength, what we do using the
formula
is we add our optimistic $50 to four times
our most
likely, which is $80 to our pessimistic of
one hundred and fifty dollars
divide all of those by six.
21:57
So we have $50 plus $320 plus
$150 divided by six, which gives us $520
divide by
six, which gives us a three point estimate
of
$86.66.
22:15
And that's the figure we could include.
22:18
But moving on for that to standard
deviations, if we wanted to
take a look and say, well, we know that the
mean is
$86.66 Or $86.66, what's the range of
certainty
that you have that you can deliver that cost
or that activity for that cost?
So we're going to use standard deviation
here, and we need to know that one
standard deviation.
22:44
Either side of the mean equals sixty eight
percent of the population.
22:49
Two standard deviations either side of the
mean equals 95 per cent of the
population three standard deviations either
side.
22:58
The mean equals 99 per cent of the
population.
23:02
And as a point of interest, once we get to
quality management, you'll see that six
standard deviations, or Six Sigma, as a
quality tool equals
99.999 Per cent of the population.
23:16
But for the purposes of three point
estimating, we're only interested in one, two
and three standard deviations either side of
the mean.
23:23
So let's use our previous example where we
had a mean of
$86.66. But remember, this was built up on a
pessimistic estimate of
$150 and an optimistic estimate of $50.
23:36
And therefore our standard deviation being
pessimistic minus optimistic over
six is $150 minus $50 divide by
six, which gives us a standard deviation of
$16.66.
23:52
So that means we could say with certainty
that we are 68 per
cent confident that we will deliver this
activity
for eighty six dollars and sixty six cents
plus or minus sixteen
point sixty six cents or if we wanted to go
to 95 per
cent certainty of delivering this activity
or two standard deviations, either side of
the mean, we would say we are 95 per cent
confident we would deliver
this activity for $86.66 Plus or minus
$33.32.
24:29
Now you need to know those formulas for the
exam, because you may get a question that
asks you about the range of certainty and
how to express it in terms of standard
deviations. So a tip when you start the
exam and you're putting down your brain dump
on your note paper put down the three point
estimating technique formula.
24:50
The standard deviation formula.
24:51
And the variance formula as well.
24:53
And as I've already said, you don't need to
remember it in two forms of the T and the
little C. Just remember it as the O, the M
and the P.
25:02
It's the same formula for both cost and time
estimating.
25:07
We've already talked about group decision
making techniques and group creativity
techniques. There's a big overlap between
the two.
25:15
But if we need a group of people to help
think about a good cost estimate, these are
some of the techniques we could use
brainstorming which has given me to think
outside the box and a bit creatively about
all the possible cost estimate
permutations. And then once we have them
using the nominal group
technique to get them to vote on which of
those cost estimate ideas and decisions
should be taken forward.
25:40
A technique that I particularly like is the
Delphi technique, and this is
designed to get around one of those large
group scenarios where you've got the loudest
person talking whose opinion gets forced on
everybody else or you've got
introverts or junior staff who who don't
feel they can talk in that environment.
25:58
So the Delphi technique is designed to get
around that you simply ask these people
to be involved in your cost estimating
excised but anonymously, they don't know who
else is being asked or how many other people
are being asked.
26:11
You've seen them information in this case
about the cost estimating advice you
want. They provide that advice back to you.
26:20
You collate that advice and seen it all the
way back out to all the experts without
identifying individual respondents and give
them time to think about the
other information provided they may choose
to change their opinion.
26:34
And this way, you get exPERTs having
considered opinion without peer pressure or
groupthink or bullying.
26:41
And once you have all those cost estimates
coming in in terms of making the
actual decision, as I've already said, it
would be really useful if your cost
management plan outlined how the final
decision would be made.
26:55
Are you going to use consensus where all the
experts must agree on the
particular cost estimates?
Are you going to use? A majority of over 50
per cent have to agree or a simple
majority of the largest voting block wins?
Or are you going to allocate the decision to
a single decision maker?
All of these things should be decided
upfront and put into your cost management
plan. So.
27:22
Using these tools and techniques on these
outputs, these are the possible outputs, we
could get individual activity cost
estimates.
27:32
So all of our individual activities now have
a cost estimate assigned to them.
27:37
Now these cost estimates can change
throughout the life of a project at the
beginning of the project.
27:43
We may not have that much information about
our activity or that
activity may not actually be programmed to
occur for 12 months.
27:53
And those conditions are cost estimates will
be
inaccurate, and we need to recognize that we
also may want to have a
basis of estimates, which is further
information about how we arrived
at our estimates, the assumptions we've
made, the information we had at hand, the
information we didn't have at hand.
28:14
All of these are valuable basis of
estimates.
28:17
So when we come to reinstate or check the
estimates, we know the
assumptions we made.
28:24
We may also want to update particular
project documents,
and these project documents could be a
commitment to continuous improvement.
28:34
With our lessons learned, historical
information to help future analysis estimates
be made or any other aspect of our cost
management process that we think
should be updated.
28:46
Now, when we come to describing costs,
there's some Standard
terminology we can use.
28:53
You'll need to know these for the exam, so
pay particular attention
here. Generally, we've found that the
question the exam will either focus
on either end of the extreme of this range.
29:05
It will either ask you to know what an order
of magnitude estimate is or a control
estimate. But if you're giving an estimate
of,
say, $50 to $200, then that's what we call
an
order of magnitude estimate minus 50 to plus
100 per cent is the range.
29:26
Is also a rough order of magnitude estimate,
a conceptual estimate.
29:32
A preliminary estimate with a range of minus
20 to plus 30 per cent,
a definitive estimate with a range of minus
15 to plus 20 per cent
and a control estimate with a range of minus
10 to plus 15 per
cent.. There's a little sentence there at
the top that may help you remember this for
the exam and that is controlling definitely
beats
preliminary concepts by an order of
magnitude that may
help you remember them for the exam, but do
pay particular attention to this.
30:05
We generally expect at least one question
the exam to expect you to know how to
describe your range of estimates.
30:14
So in summary, the estimate costs process
has gone
out and used the most appropriate estimating
technique to estimate an
individual cost for each activity.
30:27
And has also expressed a level of certainty
or uncertainty in your cost
estimate and perhaps accounted for it with
some form of contingency
reserve. Thank you.
30:39
This has been an introduction to the
estimated cost process in the PMBOK guide.